338-1Description
Construct value added asphalt pavement consisting of asphalt concrete structural course and asphalt concrete friction course, subject to a three year warranty period after final acceptance of the Contract in accordance with 5 -11. For purposes of this Specification, the Responsible Party, as designated herein, is responsible for performance of the value added asphalt pavement including continued responsibility for performing all remedial work associated with pavement distresses exceeding threshold values determined in accordance with this Section, and as to which notice was provided to the Responsible Party. The work specified in this Section will not be paid for directly, b ut will be considered as incidental to other Contract items.
338-2Materials and Construction Requirements
Meet the following requirements: Hot Bituminous Mixtures - Plant, Methods and Equipment ................................ ........................... Section 320 Hot Bituminous Mixtures - General Construction Requirements ................................ ...................... Section 330 Superpave Asphalt Concrete ............................... Section 334 Asphalt Concrete Friction Courses ....................... Section 337
338-3Responsible Party
Prior to any value added asphalt pavement being placed on the project, the Contractor shall designate a Responsible Party to accept responsibility for maintaining the value added asphalt pavement, when remedial work is required. When the scope of the asphalt work is only milling and resurfacing, a nd there is no construction of the embankment, subgrade or base below the pavement included in the Contract, the Responsible Party may be either the Contractor or the Department approved subcontractor performing the value added asphalt pavement work. When the construction of the embankment, subgrade or base below the pavement is included in the Contract, in addition to the construction of the asphalt concrete structural course and asphalt concrete friction course, the Contractor shall be considered as the Responsible Party. When the Responsible Party is a subcontractor, the subcontractor must be pre -qualified with the Department in the category of asphalt, and such designation must be made to the Department by the Contractor. The proposed subcontractor must execute and submit to the Department a form, provided by the Department, prior to or concurrent with the Contractor’s request to sublet any value added asphalt pavement work, stipulating that the subcontractor assumes all responsibility as the Responsible Party for the value added asphalt pavement within the three-year warranty period. Failure to timely designate the Responsible Party will result in the Contractor being the Responsible Party unless otherwise agreed to in writing by the Department. Upon final acceptance of the Contract in accordance with 5 -11, the Contractor’s responsibility for maintenance of all the work or facilities within the project limits of the Contract will terminate in accordance with 5 -11; with the sole excepti on that the obligations set 323 FY 2023-24 Return to Table of Contents forth in this Section for value added asphalt pavement will continue thereafter to be the responsibility of the Responsible Party as otherwise provided in this Section.
338-4Statewide Disputes Review Board
The Statewide Dispu tes Review Board in effect for this Contract will resolve any and all disputes that may arise involving administration and enforcement of this Specification. The Responsible Party and the Department acknowledge that use of the Statewide Disputes Review Board is required, and the determinations of the Statewide Disputes Review Board for disputes arising out of this Specification will be binding on both the Responsible Party and the Department, with no right of appeal by either party. Meet the requirements o f 8-3.
338-5Pavement Evaluation and Remedial Work
338-5.1General: The Department’s Pavement Condition Survey Program, along with
observations by the Engineer, will be used as the basis for determining the extent and the magnitude of the pavement distre sses occurring on the project. In the event the level of distress exceeds any of the threshold values defined below, remedial work as described in 338 -5.5 by the Responsible Party will be required. The Department will monitor the pavement for distresses and may require remedial action at any time. For evaluation purposes, the project will be subdivided into LOTs of 0.1 mile per lane. When the segment is less than 0.1 mile, the segment will be called a partial LOT. For purposes of threshold values and rem edial work, partial lots and lots will be treated as lots. The Department may conduct a Pavement Condition Survey of the value added pavement following the final acceptance of the project, and at intermediate times throughout the warranty period with findi ngs provided when considered by the Department to be the obligation of the Responsible Party . The final survey, if determined by the Engineer to be necessary, will be conducted before the end of the warranty period with results provided to the Responsible Party for those conditions exceeding contract threshold values requiring remedial action that the Department believes to be an obligation of the Responsible Party. The Department will be responsible for all costs associated with the surveys. If the survey findings, intermediate or final, are to be disputed by the Responsible Party, written notification must be submitted to the Engineer within 30 calendar days of the date of receipt of the information from the Department. During the warranty period, the Responsible Party may monitor the project using nondestructive methods and may participate with the Department in the Pavement Condition Surveys upon request. The Responsible Party shall not conduct any coring, milling or other destructive meth ods without prior approval by the Engineer.
338-5.2Category 1 Pavement: For purposes of this Specification, Category 1 pavement
is defined as mainline roadways, access roads and frontage roads with a design speed of 55 mph and greater. Threshold values and associated remedial work for Category 1 value added asphalt pavement are specified in Table 338-1.
324 FY 2023-24 Return to Table of Contents Table 338-1 Category 1 Pavements Type of Distress Threshold Values Remedial Work Rutting (1) Depth > 0.25 inch Remove and replace the distressed LOT(s) to the full depth of all layers and to the full lane width (2) Ride (3) RN < 3.5 Remove and replace the friction course layer for the full length and the full lane width of the distressed LOT(s)(4) IRI > 110 inches/mile Settlement/Depression(5) Depth ≥ 1/2 inch Propose the method of correction to the Engineer for approval prior to beginning remedial work Cracking (6) Cumulative length of cracking > 30 feet for Cracks > 1/8 inch Remove and replace the distressed LOT(s) to the full depth of all layers, and to the full lane width (7) Raveling and/or Delamination affecting the Friction Course (8) Any length Remove and replace the distressed area(s) to the full distressed depth and the full lane width for the full distressed length plus 50’ on each end Pot holes and Slippage Area(s) (8) Observation by Engineer Remove and replace the distressed area(s) to the full distre ssed depth and the full lane width for the full distressed length plus 50’ on each end Bleeding (9) Loss of surface texture due to excess asphalt, individual area ≥ 10 sf. Remove and replace the distressed area(s) to the full distressed depth and the full lane width for the full distressed length plus 50’ on each end
For any LOT that cannot be surveyed by Laser Profiler, the ru t depth will be determined manually in accordance with the Flexible Pavement Condition Survey Handbook, with the exception that the number of readings per LOT will be one every 20 feet. For a partial LOT, a minimum of three measurements not exceeding 20 feet apart will be made. When the average of the measurements obtained manually exceeds 0.30 inch or if any individual measurement exceeds 0.6 inch, remedial work will be required.
preparation and submittal of a signed and sealed engineering analysis report, demonstrating the actual extent of the distressed area(s). Remedial work must be performed in accordance with Table 338-1 unless approved otherwise by the Engineer.
FM 5-549. Use RN Warranty Threshold for projects that used RN for construction acceptance and International Roughness Index
Responsible Party, propose the method of correction to the Engineer for approval prior to beginning the remedial work.
foot intervals. The longitudinal construction joint at the lane line will not be considered as a crack.
by preparation and submittal of a signed and sealed engineering analysis report, demonstrating the actual extent of the distr essed area(s). Remedial work must be performed in accordance with Table 338-1 unless approved otherwise by the Engineer.
displayed at the following URL: https://www.fdot.gov/programmanagement/Implemented/URLinSpecs/Pavement.shtm
URL: https://www.fdot.gov/programmanagement/Implemented/URLinSpecs/Pavement.shtm 325 FY 2023-24 Return to Table of Contents
338-5.3Category 2 Pavement: For purposes of this Specification, Category 2 pavement
is defined as mainline roadways, access roads and frontage roads with a design speed less than 55 mph, approach transition and merge areas at toll booths , ramps, acceleration and deceleration lanes (including tapers) , turn lanes , parking areas , rest areas, weigh stations , and agricultural inspection stations. Threshold values and associated remedial work for Category 2 value added asphalt pavement are specified in Table 338-2.
Table 338-2 Category 2 Pavements Type of Distress Threshold Values Remedial Work Rutting(1) Measured by Laser Profiler: See Table 338 -1 See Table 338 -1
Manual Measurement: Avg. Depth > 0.4 inch Remove and replace 1.5 inch(1a) the full lane width for the area plus 50 feet Cracking Cumulative length of cracking > 300 feet for Cracks > 1/8 inch See Table 338 -1 Surface Deterioration (2) See Table 338 -1 See Table 338 -1 Settlement/Depression(3) Depth ≥ 1/2 inch See Table 338-1
For any LOT that cannot be surveyed by the Laser Profiler, the rut depth will be determined manually in accordance with the
Flexible Pavement Condition Survey Handbook, with the exception that the number of readings per LOT will be one every 20
feet. For partial LOT, minimum of three measurements not exceeding 20 feet apart will be checked. When the average of the
measurements obtained manually exceeds 0.40 inch, or if any individual measurement exceeds 0.6 inch, remedial work will be
required.
Friction Course; Pot holes; Slippage Area(s); and Bleeding; all as defined and footnoted in Table 338-1.
(3)Settlement/Depression: Depth of the settlement/depression to be determined by a 6 foot manual straightedge.
338-5.4Category 3 Pavement: For purposes of this Specification, Category 3 pavement
is defined as bicycle paths, walking paths, median crossovers, shoulders and other areas as
determined by the Engineer.
Threshold values and associated remedial work for Category 3 value added
asphalt pavement are specified in Table 338-3. 326FY 2023-24Return to Table of Contents
Table 338-3
Category 3 Pavements
Type of Distress Threshold Values Remedial Work
Rutting N/A N/A
Cracking
Cumulative length
of cracking > 500
feet for Cracks >
1/8 inch
See Table 338-1
Surface Deterioration (1) See Table 338-1 See Table 338-1
Settlement/Depression (2) Depth ≥ 1/2 inch See Table 338-1
Friction Course; Pot holes; Slippage Area(s); and Bleeding; all as defined and footnoted in Table 338-1. Raveling of FC-5 for
Category 3 Pavements is excluded from this requirement.
338-5.5Remedial Work: The Responsible Party will perform all necessary remedial
work described within this Section at no cost to the Department. If the pavement distresses
exceed threshold values and it is determined that the cause of the distress is due to the
embankment, subgrade, base or other activities performed by the Contractor, the Responsible
Party will be responsible for performing all remedial work associated with the pavement distress.
Should an impasse develop in any regard as to the need for remedial work or the extent required,
the Statewide Disputes Review Board will render a final decision by majority vote.
Remedial work will not be required if any one of the following conditions is
found to apply:
Department is deficient. The Department will make available a copy of the original pavement
thickness design package and design traffic report to the Responsible Party upon request. The
Responsible Party is responsible for performing all remedial work associated with the pavement
distress if the pavement design is provided by the Contractor.
Equivalent Single Axle Loads in the design lane) has increased by 25% or more than the
Accumulated ESALs used by the Department for design purposes for the warranty period for the
pavement design life. In calculating ESALs, the average annual daily traffic (AADT) will be
obtained from the Department’s traffic count data and the T24 (percent heavy trucks during a
24 hour period) will be obtained from the Department’s traffic classification survey data.
underlying layers that were not part of the Contract work.
or its actions, unless the third party was performing work included in the Contract.
turn lane, turn out, or median cross over was caused by turning movements and not a materials or
construction issue.
If a measured distress value indicates remedial action is required per Table 338-1,
Table 338-2 and/or Table 338-3, the Responsible Party must begin remedial work within
45 calendar days of notification by the Department or a ruling of the Statewide Disputes Review
Board. The Disputes Review Board will determine the allowable duration for the completion of
the remedial work, but not to exceed six months. 327FY 2023-24Return to Table of Contents
In the event remedial action is necessary and forensic information is required to
determine the source of the distress, the Department may core and/or trench the pavement. The
Responsible Party will not be responsible for damages to the pavement as a result of any forensic
activities conducted by the Department.
As applicable to distress criteria for rutting, ride and cracking for Category 1 and
Category 2 pavements, when two LOTs requiring remedial action are not separated by three or
more LOTs not requiring remedial action, the remedial work shall be required for the total length
of all such contiguous LOTs, including the intermediate LOTs not requiring remedial action.
Additionally, for Category 1 and Category 2 pavements, where such areas of
remedial action are required due to raveling, slippage or bleeding are separated by less than
1,000 feet, the remedial work will be required for the entire area contiguous to the distressed
areas, including intermediate areas otherwise requiring no remedial action.
The Responsible Party has the first option to perform all remedial work that is
determined by the Department to be their responsibility. If, in the opinion of the Engineer, the
problem poses an immediate danger to the traveling public and the Responsible Party cannot
provide temporary mitigation for the defect within 4 hours of written notification and restore the
pavement to its original design condition within 72 hours of written notification, the Engineer
has the authority to have the remedial work performed by other forces. Temporary mitigation
includes the use of traffic control systems such as barricades, drums, or other approved devices
to secure the area including lane closures if necessary, and constructing temporary repairs
making it safe for the roadway user until the defect can be restored to its original design
condition. The Responsible Party is responsible for all incurred costs of the work performed by
other forces should the problem (remedial work) be determined to be the responsibility of the
Responsible Party. Remedial work performed by other forces does not alter any of the
requirements, responsibilities or obligations of the Responsible Party.
The Responsible Party must complete all remedial work to the satisfaction of the
Engineer. Any disputes regarding the adequacy of the remedial work will be resolved by the
Statewide Disputes Review Board. Approval of remedial work does not relieve the Responsible
Party from continuing responsibility under the provisions of this Specification.
Notify the Engineer in writing prior to beginning any remedial work. Meet the
requirements of the Specifications when performing any remedial work. Perform all signing and
traffic control in accordance with the current edition of the Department’s Standard Plans. Provide
maintenance of traffic during remedial work at no additional cost to the Department. Lane
closure restrictions listed in the original Contract will apply to remedial work. Written requests
to obtain permission for lane closures for either forensic investigation or remedial work must be
made to the Engineer 48 hours in advance of any lane closures. Do not perform any lane closures
until written permission is given by the Engineer.
If remedial work necessitates a corrective action to overlying asphalt layers,
pavement markings, signal loops, adjacent lanes, roadway shoulders, or other affected Contract
work, perform these corrective actions using similar products at no additional cost to the
Department.
338-6Responsible Party’s Failure to Perform
Should the Responsible Party fail to timely submit any dispute to the Statewide Disputes
Review Board, fail to satisfactorily perform any remedial work, or fail to compensate the
Department for any remedial work performed by the Department and determined to be the
Responsible Party’s responsibility in accordance with this Specification, the Department will 328FY 2023-24Return to Table of Contents
suspend, revoke or deny the Responsible Party’s certificate of qualification under the terms of
has been satisfactorily performed (or full and complete payment for remedial work performed by
others made to the Department), whichever is longer. Should the Responsible Party choose to
challenge the Department’s notification of intent for suspension, revocation or denial of
qualification and the Department’s action is upheld, the Responsible Party will have its
qualification suspended for an additional minimum of six months.
The remedial work is not an obligation of the Contractor’s bond required by
Section 337.18, Florida Statutes. 329FY 2023-24Return to Table of Contents
MISCELLANEOUS ASPHALT PAVEMENT
339-1Description
Construct asphalt pavement in areas where vehicular traffic does not travel, such as pavement under guardrail, bicycle paths, median pavement, sidewalks, etc. Also, chemically treat the underlying soil to prevent plant growth.
339-2Materials
For the pavement, use any plant -mixed hot bituminous mixture meeting the requirements of a mix design verified by the Engineer, except do not use open -graded friction course (F C-5). For bicycle paths, use a mixture that produces a finished pavement which will not distort or mar under bicycle or mower wheel loads. In general, the Engineer will accept the mixture on the basis of visual inspection with no further testing required.
339-3Foundation and Soil Treatment
Shape the soil in areas where pavement is to be constructed, to a surface true to the lines, grades and typical sections shown in the Plans. Compact the soil to a firm state. Immediately before placing the pavement, uniformly apply a pre -emergent herbicide in accordance with the requirements of 7 -1.7, to the foundation soil. Ensure that the herbicide carries an approved label for use under paved surfaces, and that herbicide is applied in accordance with directions on the label. Prevent damage to any adjacent vegetation during herbicide application. Replace, at no expense to the Department, any plants damaged as the result of soil treatment outside designated areas.
339-4Placing Mixture
Uniformly place the hot bitum inous mixture by machine or hand methods at the rate of spread or dimensions indicated in the Plans or as otherwise directed by the Engineer. If posts are to be constructed within the pavement area, the Contractor may cut holes for installation through the completed pavement. After completing installation of posts and compaction of the backfill material, patch the area around each post with fresh hot bituminous mixture. If directed by the Engineer, place miscellaneous asphalt pavement prior to placement of the final surface course.
339-5Compacting Mixture
Uniformly compact the hot bituminous mixture with lightweight rollers or vibratory compactors as directed by the Engineer. The Contractor may use hand tamps for compaction in areas which are inaccessible to other compaction equipment. The Engineer will not require a specific density.
339-6Surface Requirements
Provide a finished surface that is reasonably smooth, of uniform texture, and shaped so as to drain without ponding of water. 330 FY 2023-24 Return to Table of Contents