338-1 Description.
Construct value added asphalt pavement consisting of asphalt concrete structural course and asphalt concrete friction course, subject to a three year warranty period after final acceptance of the Contract in accordance with 5 -11. For purposes of this Specification, the Responsible Party, as designated herein, is responsible for performance of the value added asphalt pavement including continued responsibility for performing all remedial work associated with pavement distresses exceeding threshold values determined in accordance with this Section, and as to which notice was provided to the Responsible Party. The work specified in this Section will not be paid for directly, b ut will be considered as incidental to other Contract items.
338-2 Materials and Construction Requirements.
Meet the following requirements: Hot Bituminous Mixtures - Plant, Methods and Equipment ................................ ........................... Section 320 Hot Bituminous Mixtures - General Construction Requirements ................................ ...................... Section 330 Superpave Asphalt Concrete ............................... Section 334 Asphalt Concrete Friction Courses ....................... Section 337
338-3 Responsible Party.
Prior to any value added asphalt pavement being placed on the project, the Contractor shall designate a Responsible Party to accept responsibility for maintaining the value added asphalt pavement, when remedial work is required. When the scope of the asphalt work is only milling and resurfacing, a nd there is no construction of the embankment, subgrade or base below the pavement included in the Contract, the Responsible Party may be either the Contractor or the Department approved subcontractor performing the value added asphalt pavement work. When the construction of the embankment, subgrade or base below the pavement is included in the Contract, in addition to the construction of the asphalt concrete structural course and asphalt concrete friction course, the Contractor shall be considered as the Responsible Party. When the Responsible Party is a subcontractor, the subcontractor must be pre -qualified with the Department in the category of asphalt, and such designation must be made to the Department by the Contractor. The proposed subcontractor must execute and submit to the Department a form, provided by the Department, prior to or concurrent with the Contractor’s request to sublet any value added asphalt pavement work, stipulating that the subcontractor assumes all responsibility as the Responsible Party for the value added asphalt pavement within the three-year warranty period. Failure to timely designate the Responsible Party will result in the Contractor being the Responsible Party unless otherwise agreed to in writing by the Department. Upon final acceptance of the Contract in accordance with 5 -11, the Contractor’s responsibility for maintenance of all the work or facilities within the project limits of the Contract will terminate in accordance with 5 -11; with the sole excepti on that the obligations set FY 2023-24 Return to Table of Contents forth in this Section for value added asphalt pavement will continue thereafter to be the responsibility of the Responsible Party as otherwise provided in this Section.
338-4 Statewide Disputes Review Board.
The Statewide Dispu tes Review Board in effect for this Contract will resolve any and all disputes that may arise involving administration and enforcement of this Specification. The Responsible Party and the Department acknowledge that use of the Statewide Disputes Review Board is required, and the determinations of the Statewide Disputes Review Board for disputes arising out of this Specification will be binding on both the Responsible Party and the Department, with no right of appeal by either party. Meet the requirements o f 8-3.
338-5 Pavement Evaluation and Remedial Work.
338-5.1 General: The Department’s Pavement Condition Survey Program, along with
observations by the Engineer, will be used as the basis for determining the extent and the magnitude of the pavement distre sses occurring on the project. In the event the level of distress exceeds any of the threshold values defined below, remedial work as described in 338 -5.5 by the Responsible Party will be required. The Department will monitor the pavement for distresses and may require remedial action at any time. For evaluation purposes, the project will be subdivided into LOTs of 0.1 mile per lane. When the segment is less than 0.1 mile, the segment will be called a partial LOT. For purposes of threshold values and rem edial work, partial lots and lots will be treated as lots. The Department may conduct a Pavement Condition Survey of the value added pavement following the final acceptance of the project, and at intermediate times throughout the warranty period with findi ngs provided when considered by the Department to be the obligation of the Responsible Party . The final survey, if determined by the Engineer to be necessary, will be conducted before the end of the warranty period with results provided to the Responsib le Party for those conditions exceeding contract threshold values requiring remedial action that the Department believes to be an obligation of the Responsible Party. The Department will be responsible for all costs associated with the surveys. If the survey findings, intermediate or final, are to be disputed by the Responsible Party, written notification must be submitted to the Engineer within 30 calendar days of the date of receipt of the information from the Department. During the warranty period, the Responsible Party may monitor the project using nondestructive methods and may participate with the Department in the Pavement Condition Surveys upon request. The Responsible Party shall not conduct any coring, milling or other destructive meth ods without prior approval by the Engineer.
338-5.2 Category 1 Pavement: For purposes of this Specification, Category 1 pavement
is defined as mainline roadways, access roads and frontage roads with a design speed of 55 mph and greater. Threshold values and associated remedial work for Category 1 value added asphalt pavement are specified in Table 338-1. FY 2023-24 Return to Table of Contents Table 338-1 Category 1 Pavements Type of Distress Threshold Values Remedial Work Rutting (1) Depth > 0.25 inch Remove and replace the distressed LOT(s) to the full depth of all layers and to the full lane width (2) Ride (3) RN < 3.5 Remove and replace the friction course layer for the full length and the full lane width of the distressed LOT(s)(4) IRI > 110 inches/mile Settlement/Depression(5) Depth ≥ 1/2 inch Propose the method of correction to the Engineer for approval prior to beginning remedial work Cracking (6) Cumulative length of cracking > 30 feet for Cracks > 1/8 inch Remove and replace the distressed LOT(s) to the full depth of all layers, and to the full lane width (7) Raveling and/or Delamination affecting the Friction Course (8) Any length Remove and replace the distressed area(s) to the full distressed depth and the full lane width for the full distressed length plus 50’ on each end Pot holes and Slippage Area(s) (8) Observation by Engineer Remove and replace the distressed area(s) to the full distre ssed depth and the full lane width for the full distressed length plus 50’ on each end Bleeding (9) Loss of surface texture due to excess asphalt, individual area ≥ 10 sf. Remove and replace the distressed area(s) to the full distressed depth and the full lane width for the full distressed length plus 50’ on each end
338-5.3 Category 2 Pavement: For purposes of this Specification, Category 2 pavement
is defined as mainline roadways, access roads and frontage roads with a design speed less than 55 mph, approach transition and merge areas at toll booths , ramps, acceleration and deceleration lanes (including tapers) , turn lanes , parking areas , rest areas, weigh stations , and agricultural inspection stations. Threshold values and associated remedial work for Category 2 value added asphalt pavement are specified in Table 338-2. Table 338-2 Category 2 Pavements Type of Distress Threshold Values Remedial Work Rutting(1) Measured by Laser Profiler: See Table 338 -1 See Table 338 -1 Manual Measurement: Avg. Depth > 0.4 inch Remove and replace 1.5 inch(1a) the full lane width for the area plus 50 feet Cracking Cumulative length of cracking > 300 feet for Cracks > 1/8 inch See Table 338 -1 Surface Deterioration (2) See Table 338 -1 See Table 338 -1 Settlement/Depression(3) Depth ≥ 1/2 inch See Table 338-1
338-5.4 Category 3 Pavement: For purposes of this Specification, Category 3 pavement
is defined as bicycle paths, walking paths, median crossovers, shoulders and other areas as determined by the Engineer. Threshold values and associated remedial work for Category 3 value added asphalt pavement are specified in Table 338-3. FY 2023-24 Return to Table of Contents Table 338-3 Category 3 Pavements Type of Distress Threshold Values Remedial Work Rutting N/A N/A Cracking Cumulative length of cracking > 500 feet for Cracks > 1/8 inch See Table 338 -1 Surface Deterioration (1) See Table 338 -1 See Table 338 -1 Settlement/Depression(2) Depth ≥ 1/2 inch See Table 338 -1
338-5.5 Remedial Work: The Responsible Party will perform all necessary remedial
work described within this Section at no cost to the Departm ent. If the pavement distresses exceed threshold values and it is determined that the cause of the distress is due to the embankment, subgrade, base or other activities performed by the Contractor, the Responsible Party will be responsible for performing a ll remedial work associated with the pavement distress. Should an impasse develop in any regard as to the need for remedial work or the extent required, the Statewide Disputes Review Board will render a final decision by majority vote. Remedial work will not be required if any one of the following conditions is found to apply:
338-6 Responsible Party’s Failure to Perform.
Should the Responsible Party fail to timely submit any dispute to the Statewide Disputes Review Board, fail to satisfactorily perform any remedial work, or fail to compensate the Department for any remedial w ork performed by the Department and determined to be the Responsible Party’s responsibility in accordance with this Specification, the Department will FY 2023-24 Return to Table of Contents suspend, revoke or deny the Responsible Party’s certificate of qualification under the terms of Section 337.16(d)(2), Florida Statutes, for a minimum of six months or until the remedial work has been satisfactorily performed (or full and complete payment for remedial work performed by others made to the Department), whichever is longer. Should the Responsible Party choose to challenge the Department’s notification of intent for suspension, revocation or denial of qualification and the Department’s action is upheld, the Responsible Party will have its qualification suspended for an additional minimum of six months. The remedial work is not an obligation of the Contractor’s bond required by Section 337.18, Florida Statutes. FY 2023-24 Return to Table of Contents SECTION 339 MISCELLANEOUS ASPHALT PAVEMENT
339-1 Description.
Construct asphalt pavement in areas where vehicular traffic does not travel, such as pavement under guardrail, bicycle paths, median pavement, sidewalks, etc. Also, chemically treat the underlying soil to prevent plant growth.
339-2 Materials.
For the pavement, use any plant -mixed hot bituminous mixture meeting the requirements of a mix design verified by the Engineer, except do not use open -graded friction course (F C-5). For bicycle paths, use a mixture that produces a finished pavement which will not distort or mar under bicycle or mower wheel loads. In general, the Engineer will accept the mixture on the basis of visual inspection with no further testing required.
339-3 Foundation and Soil Treatment.
Shape the soil in areas where pavement is to be constructed, to a surface true to the lines, grades and typical sections shown in the Plans. Compact the soil to a firm state. Immediately before placing the pavement, uniformly apply a pre -emergent herbicide in accordance with the requirements of 7 -1.7, to the foundation soil. Ensure that the herbicide carries an approved label for use under paved surfaces, and that herbicide is applied in accordance with directions on the label. Prevent damage to any adjacent vegetation during herbicide application. Replace, at no expense to the Department, any plants damaged as the result of soil treatment outside designated areas.
339-4 Placing Mixture.
Uniformly place the hot bitum inous mixture by machine or hand methods at the rate of spread or dimensions indicated in the Plans or as otherwise directed by the Engineer. If posts are to be constructed within the pavement area, the Contractor may cut holes for installation through the completed pavement. After completing installation of posts and compaction of the backfill material, patch the area around each post with fresh hot bituminous mixture. If directed by the Engineer, place miscellaneous asphalt pavement prior to placement of the final surface course.
339-5 Compacting Mixture.
Uniformly compact the hot bituminous mixture with lightweight rollers or vibratory compactors as directed by the Engineer. The Contractor may use hand tamps for compaction in areas which are inaccessible to other compaction equipment. The Engineer will not require a specific density.
339-6 Surface Requirements.
Provide a finished surface that is reasonably smooth, of uniform texture, and shaped so as to drain without ponding of water. FY 2023-24 Return to Table of Contents