HOT MIX ASPHALT - GENERAL CONSTRUCTION REQUIREMENTS
330-1 Description.
This Section specifies the basic equipment and construction requirements for hot mix asphalt (including warm mix asphalt) pavements and bases. Establish and maintain a quality control system that provides assurance that all materials, products and complete d construction submitted for acceptance meet Contract requirements.
330-2 Quality Control (QC) Requirements .
330-2.1 Minimum QC Requirements: Perform as a minimum , the following activities
necessary to mai ntain process control and meet S pecification requi rements:
330-2.2 Personnel Qualifications: Provide QC Technicians in accordance with
Section 105.
330-3 Limitations of Operations.
330-3.1 Weather Limitations: Do not transport asphalt mix from the plant to the
roadway unless all weather conditions are suitable for the paving operations.
330-3.2 Limitations of Paving Operations:
330-3.2 1 General: Place the mixture only when the surface upon which it is to
be placed has been previously prepared, is intact, firm, dry, clean, and the tack or prime coat, FY 2023-24 Return to Table of Contents with acceptable s pread rate, is properly broken or cured. Do not place friction course until the adjacent shoulder area has been dressed and grassed.
330-3.2 2 Ambient Air Temperature: Place the mixture only when the air
temperature in the shade and away from artificial heat meets requirements of Table 330-1. The minimum ambient temperature requirement may be reduced by 5ºF when using warm mix technology, if mutually agreed to by both the Engineer and the Contractor. Table 330-1 Ambient Air Temperature Requirements for Paving Layer Thickness or Asphalt Binder Type Minimum Temperature (°F) ≤ 1 inch 50 Any mixture > 1 inch containing a PG asphalt binder with a high temperature designation ≥ 76°C 45 Any mixture > 1 inch containing a PG asphalt binder with a high temperature designation < 76°C 40 FC-5(1) 65 (1)As an exception, place the mixture at temperatures no lower than 60ºF, only when approved by the Engineer based on the Contractor’s demonstrat ed ability to achieve a satisfactory surface texture and appearance of the finished surfa ce. For mixtures containing PG 76 -22 binder, t he minimum ambient temperature may be further reduced to 55ºF when using warm mix technology, if agreed to by both the En gineer and the Contractor.
330-3.2 3 Rain and Surface Conditions: Immediately cease transportation of
asphalt mixtures from the plant when rain begins at the roadway. Do not place asphalt mixtures while rain is falling, or when there is water on the surface to be covered. Once the rain has stopped, standing water has been removed from the tacked surface to the satisfaction of the Engineer, and the temperature of the mixture caught in transit still meets the requirements as specified in 320 -6.3, the Co ntractor may then place the mixture caught in transit. For windrow paving, immediately cease dumping of asphalt material when rain begins at the roadway. Stop paving operations while rain is falling or where there is water on the surface to be covered. Remove windrowed asphalt mixture exposed to rain. Once the rain has stopped, standing water has been removed from the tacked surface to the satisfaction of the Engineer, and the temperature of the mixture caught in transit still meets the requirements as specified in 320 -6.3, the Contractor may then windrow the remaining material caught in transit.
330-3.2 4 Wind: Do not place the mixture when the wind is blowing to such an
extent that proper and adequate compaction cannot be maintained or when sand, dust, etc., are being deposited on the surface being paved to the extent the bond between layers will be diminished.
330-4 Surface Preparation .
330-4.1 Cleaning: Before placing the mixture, clean the surface of the base or underlying
pavement of all loose and deleterious material by the use of power brooms or blowers, supplemented by hand brooming where necessary.
330-4.1 1 Application over Asphalt Membrane Interlayer (AMI): Where an
asphalt mix is to be placed over a newly constructed AMI, do not sweep or otherwise disturb the cover material before placing the asphalt mix, unless directed by the Engineer.
330-4.2 Tacking: Apply a tack coat on all existing pavement surfaces that are to be
overlaid with an asphalt mix as specified in Section 300 and between successive layers of all asphalt mixes. Apply tack on a clean surface. FY 2023-24 Return to Table of Contents Do not place tack while rain is falling or when there is water on the surface to be tacked. Once the rain has stopped, standing water has been removed from the surface to be tacked to the satisfaction of the Engineer, the Contractor may then apply tack. Apply a tack coat on freshly primed bases only w hen directed by the Engineer.
330-5 Paving Equipment.
330-5.1 General Requirements: Use mechanically -sound equipment capable of
consistently meeting Specification requirements.
330-5.2 Asphalt Paver :
330-5.2 1 General: Provide a self-propelled asphalt paver that can be steered , and
is equipped with a receiving and distribution hopper and a mechanical screed. Use a mechanical screed capable of adjustment to regulate the depth of material spread and to produce the desired cross slope. When asphalt mix is placed in windrows, operate windrow pickup equipment so substantially all of the mixture deposited on the roadbed is picked up and loaded into the paver. Prevent the windrow pickup equipment from contaminating the mixture.
330-5.2 2 Automatic Screed Control: For all asphalt courses placed with an
asphalt paver, equip the paver with automatic longitudinal screed controls of either the skid type, traveling stringline type, or non -contact averaging ski type with a minimum length of 25 feet. On the final layer of asphalt base, overbuild, structural courses, and friction courses, use the joint matcher instead of the skid, traveling stringline, or non -contact averaging ski on all passes after the initial pass . Equip the asphalt paver with el ectronic cross slope controls.
330-5.2 3 Screed Width: Provide an asphalt paver with a screed width greater
than 8 feet when required to pave full width lanes. Do not use extendable screed strike -off devices that do not provide preliminary compaction of the mat in place of fixed screed extensions. Use a strike -off device only on irregular areas that would normally be done by hand and on shoulders 5 feet or less in width. When using the strike -off device on shoulders , instead of an adjustable screed extens ion, demonstrate the ability to obtain acceptable texture, density, and thickness. When using an extendable screed device to extend the screed’s width on the full width lane or shoulder by 24 inches or greater, the Engineer will require an auger extension, paddle, or kicker device unless the Contractor can demonstrate the ability to achieve an acceptable pavement with respect to density, surface texture, and pavement smoothness without such devices .
330-5.3 Rollers :
330-5.3 1 Steel-Wheeled Rollers: Provide compaction equipment capable of
meeting the density requirements described in the Specifications. When density testing is not required, and the standard rolling pattern is used, provide a tandem steel -wheeled roller weighing 5 to 15 tons for breakdown rolling. For finish rolling, use a separate roller weighing 5 to 15 tons. Variations from these requirements shall be approved by the Engineer.
330-5.3 2 Traffic Rollers: Provide compaction equipment capable of meeting the
density requirements described in the Sp ecifications. When density testing is not required, and the standard rolling pattern is used, provide a self -propelled, pneumatic -tired traffic roller equipped with at least seven smooth -tread, low pressure tires, equipp ed with pads or scrapers on each tire. Maintain the tire pressure between 50 and 55 psi or as specified by the manufacturer. Use rollers with a minimum weight of 6 tons. Do not use wobble -wheeled rollers. Variations from these requirements shall be approve d by the Engineer. FY 2023-24 Return to Table of Contents
330-5.3 3 Prevention of Adhesion: Do not allow the mixture to adhere to the
wheels of any rollers. Do not use fuel oil or other petroleum distillates to prevent adhesion. Do not use any method which results in water being sprinkled dir ectly onto the mixture.
330-5.4 Coring Equipment: Furnish a suitable saw or drill for obtaining the required
density cores.
330-5.5 Hand Tools: Provide the necessary hand tools such as rakes, shovels, and other
similar tools, and a suitable means for kee ping them clean. Do not use diesel fuel or other petroleum -based solvents contained in an open container for cleaning purposes on the paver.
330-6 Placing Mixture.
330-6.1 Requirements Applicable to All Pavement Types:
330-6.1 1 Alignment of Edges: Place all asphalt mixtures by the stringline
method to obtain an accurate, uniform alignment of the pavement edge. As an exception, pavement edges adjacent to curb and gutter or other true edges do not require a stringline. Control the unsupported pavement edg e to ensure it will not deviate from the stringline more than plus or minus 1.5 inches.
330-6.1 2 Paving Width: If necessary due to the traffic requirements, place the
mixture in strips in such a manner as to provide for the passage of traffic. As an opt ion, where the road is closed to traffic, place the mixture to the full width with machines traveling in echelon.
330-6.1 3 Mix Temperature: Maintain the mix temperature at the time of paving
within the master range as defined in 320-6.3. Take mix temperatures on the roadway at the minimum frequency indicated in 320 -6.3. Any load, or portion of a load, of asphalt mix on the roadway with a tempe rature outside of the master range shall be rejected for use on the project. Immediately notify the Engineer of the rejection. Remove any windrow material not meeting the temperature requirements of 320-6.3.2 from the area of deficient temperature and r eplace with new asphalt meeting the temperature requirements.
330-6.1 4 Speed of Paver: Establish the forward speed of the asphalt paver based
on the rate of delivery of the mix to the roadway , but not faster than the optimum speed needed to adequately c ompact the pavement.
330-6.1 5 Thickness and Spread Rate of Layers: Construct each layer as
defined in the following Table 330-2: Table 330-2 Thickness and Target Spread Rate Requirements Mix Type Specification Section and Article Type SP 334-1 Type FC 337-8 Type B 234-8 ATPB 287-8
330-6.1 5.1 Thickness Control: Ensure the spread rate is within plus or
minus 10% of the target spread rate. When determining the spread rate, use, at a minimum, an average of five truckloads of mix and at a maximum, an average of 10 truckloads of mix , except for windrow paving, use an average of three truckloads of mix. When the average spread rate is FY 2023-24 Return to Table of Contents beyond plus or minus 10% of the target spread rate, monitor the thickness of the pavement layer closely and a djust the construction operations. When the average spread rate for two consecutive days is beyond plus or minus 10% of the target spread rate , stop the construction operation until the issue is resolved.
330-6.1 5.2 Maximum Spread Rate Tolerances: When an individual
spread rate, measured in accordance with 330 -6.1.5.1, is beyond plus or minus 20% of the target spread rate, stop the construction operation until the issue is resolved. Address the unacceptable pavement in accordance with 330 -9.5. The f ollowing areas are exempt from a work stoppage based solely on the calculated spread rate: median crossovers, turnouts, variable thickness overbuild courses, leveling courses, miscellaneous asphalt pavement, as well as, turn lanes and ramps less than 1,000 feet. As an exception, the Engineer may allow the Contractor to leave areas in place if it is determined by the Engineer that the deficiency is not a significant detriment to the pavement quality. For areas of deficient thickness, a reduction to the pay item quantity will be made in accordance with 330 -9.5.2.
330-6.1 6 Correcting Defects: Before starting any rolling, check the surface;
correct any irregularities; remove all drippings, sand accumulations from the screed, and fat spots from any source; and replace them with satisfactory material. Do not skin patch. When correcting a depressi on while the mixture is hot, scarify the surface and add fresh mixture.
330-6.1 7 Hand Work: In limited areas where the use of the paver is impossible
or impracticable, the Contractor may place and finish the mixture by hand .
330-7 Compacting Mixture.
330-7.1 General Requirements : When density testing for acceptance is required, select
equipment, sequence, and coverages of rolling to meet the specified density requirement. Regardless of the rolling procedure used, complete the final rolling before the su rface temperature of the pavement drops to the extent effective compaction may not be achieved or the rollers begin to damage the pavement. No vibratory compaction in the vertical direction will be allowed for layers one inch or less in thickness or , if the Engineer or Contract Documents limit compaction to the static mode only. Compact these layers in the static mode only. Other non -vertical vibratory modes of compaction will be allowed, if approved by the Engineer ; however, no additional compensation, cost or time, will be made.
330-7.2 Standard Rolling Procedure: When density testing for acceptance is not
required, propose an alternative ro lling pattern to be approved by the Engineer or use the following standard rolling procedure:
330-7.3 Rolling Procedures: Use procedures that will uniformly compact the pavement
layer to the desired density level , while meeting the appropriate smoothness requirements, without damaging the pavement surface, crushing aggregate or leaving excessive roller marks , roller heads, or ripples . While rolling is in progress, monitor the surface continuously, and adjust the compaction operations to comply with the surface requireme nts.
330-7.4 Compaction of Areas Inaccessible to Rollers: Use hand tamps or other
satisfactory means to compact areas which are inaccessible to a roller, such as areas adjacent to curbs, gutters, bridges, manholes, etc.
330-7.5 Correcting Defects: Do not allow the compaction equipment to deposit
contaminants onto the pavement surface. Remove and replace any areas damaged by such deposits as directed by the Engineer. Correct any depressions that develop before completing the rolling by loosening the mixtur e and adding new mixture to bring the depressions to a true surface. Should any depression remain after obtaining the final compaction, remove the full depth of the mixture, and replace it with enough new mixture to form a true and even surface. Correct al l defects before laying the subsequent course.
330-7.6 Use of Traffic Roller : Use a traffic roller on the first overbuild course . Use a
traffic roller or vibratory roller (unless restricted by the Contract Documents) on the first structural layer placed o n an AMI.
330-7.7 Compaction at Bridge Structures: Compact asphalt mixtures placed over
bridge decks and approach slabs using static compaction only. Use the standard rolling procedure described in 330 -7.2 or an alternative procedure approved by the Engineer.
330-8 Joints.
330-8.1 General: When laying fresh mixture against the exposed edges of joints, place it
in close contact with the exposed edge to produce an even, well -compacted joint after rolling.
330-8.2 Transverse Joints: Place the mixture as continuously as possible to minimize
transverse joints. When constructing permanent transverse joints, meet the surface requirements as defined in 330 -9. Construct temporary transverse joints in such a manner to allow traffic to pass over it. When resuming the paving operation, construct a transverse joint by cutting back on the previous ly placed pavement at a location where the straightedge requirements are met. At the project limits, tie into the adjoining pa vement layers as shown in the Plans.
330-8.3 Longitudinal Joints: Place each layer of pavement so all longitudinal
construction joints are offset 6 to 12 inches laterally between successive layers. Plan offsets in advance so th e longitudinal joints of the friction course are not in wheel path areas. The longitudinal joints for friction course layers should be within 6 inches of the lane edge or at the center of the lane. The Engineer may waive this requirement where offsetting is not feasible due to the sequence of construction.
330-8.4 Placing Asphalt Next to Concrete Pavement: When placing asphalt next to
concrete pavement, construct the joint as shown in the Plans.
330-9 Surface Requirements.
330-9.1 General : Construct a smoo th pavement with good surface texture and the proper
cross-slope.
330-9.2 Texture of the Finished Surface of Paving Layers: Produce a finished surface
of uniform texture and compaction with no pulled, torn, raveled, crushed or loosened portions and free o f segregation, bleeding, flushing, sand streaks, sand spots, or ripples. Some examples of pavement deficiencies are displayed at the following URL: FY 2023-24 Return to Table of Contents https://www.fdot.g ov/programmanagement/Implemented/URLinSpecs/Pavement.shtm . Address any pavement not meeting the requirements of this specification in accordance with 330 -9.5. For dense -graded structural and dense-graded friction course mixtures , in areas not defined as density testing exceptions per 334 -5.1.2, obtain for the Engineer , three 6-inch diameter roadway cores at locations visually identified by the Engineer to be segregated. For areas that the Engineer identifi es as being segregated, obtain and submit cores within 30 days of notification . The Engineer will determine the density of each core in accordance with FM 1- T166 and calculate the percent G mm of the segregated area using the average G mb of the roadway cores and the QC sublot G mm for the questionable material. If the average percent G mm is less than 89.5, address the segregated area in accordance with 330 -9.5. Do not use asphalt concrete mixtures containing aggregates that cause a different color appearanc e in the final wearing surface unless the section is greater than or equal to one mile in length and across the full width of the pavement, including shoulders and turn lanes. Exceptions to these requirements will be permitted if approved by the Engineer.
330-9.3 Cross Slope: Construct a pavement surface with cross slopes in compliance with
the requirements of the Contract Documents. Furnish a four-foot-long electronic level accurate to 0.1 degree, approved by the Engineer for the control of cross slope. Make this electronic level available at the jobsite at all times during paving operations.
330-9.3 1 QC Calibration and Comparison : Calibrate the electronic levels a
minimum of once per day before paving operation s begin, in accordance with manufacturer’s instructions. Compare the QC level with the Verification level before paving operations begin, and at any time as directed . If the comparison between the QC and Verification levels is within plu s or minus 0.2%, the QC level is considered to compare favorably and can be used for measurement and acceptan ce of cross -slopes. If the levels do not compare favorably, perform a second comparison using another calibrated electronic level ( Department or Contractor) for resolution. If the resolution level compares favorably with the QC level, the QC level is considered to be verified. If the resolution level does not compare favorably with the QC level, discontinue the use of the QC electronic level and obta in another approved electronic level that meets the requirements of this specification. The Contractor assumes all risk associated with placing the pavement at the correct cross slope.
330-9.3 2 Cross Slope Measurement: Measure the cross slope of the compacted
pavement surface by placing the level at the center of the lane and perpendicular to the roadway centerline. Record all measurements to the nearest 0.1% on an approved form and submit the data to the Engineer .
330-9.3 2.1 Cross Slope Measurement Frequency:
330-9.3 2.2 Cross Slope Deviations and Corrections : Calculate the
absolute deviation of each cross-slope measurement and the average of the absolute deviations of ten consecutive cross slope measurements. The absolute deviation is the positive value of a deviation. In superelevated sections, w hen the number of measurements is less than ten, average the absolute deviation of all measurements. If the average absolute deviation of any cross-slope measurement falls outside the acceptance tolerance shown in Table 330 -3, stop the paving operation and make adjustments until the problem is resolved to the sati sfaction of the Engineer. Address, in accordance with 330 -9.5, all individual cross slope deviations outside the acceptance tolerance s shown in Table 330-3. Complete all corrections before placement of the final pavement surface layer. For pavement with multiple layers, the deficient areas for the structural course may be left in place, if approved by the Engineer. For friction course layers, make correction s in accordance with 330 -9.5. The limits of deficient areas requiring correction may be verified and adjusted with more accurate measurement methods, including survey instruments, upon approval of the Engineer and at no cost to the Department. Should the Contractor wish to have any required corrections waived, submit a request to the Engineer for approval. The Engineer may waive the corrections at no reduction in payment if the deficiencies are sufficiently separated so as not to affect the pavement’s overall traffic safety, surface drainage , ride quality, or surface texture . For intersections, tapers, crossovers, transitions at the beginning and end of the project, bridge approaches and similar areas, adjust the cross slope to match the actual site conditions or as directed by the Engineer. Table 330-3 Cross Slope Acceptance Tolerance Roadway Feature Individual Absolute Deviation Average Absolute Deviation Tangent section (including turn lanes) 0.4% 0.2% Superelevated curve 0.4% 0.2% Shoulder 0.5% 0.5% In the event the distance between two edges of deficient areas is less than 100 feet, the correction work shall include the area between the deficient areas.
330-9.3 3 Verification: The Engineer will verify the Contractor’s cross slope
measurements by randomly taking a minimum of ten cross slope measurements per lane per mile in tangent sections, at control points in transition sections, and a minimum of three cross slope measurements in fully superelevated sections . The Engineer will measure the cross slope of the compacted pavement surface by placing the level at the center of the lane and perpendicular to the roadway centerline .
330-9.3 3.1 Cross Slope Deviations and Corrections: If the average
absolute deviation or an individual cross slope deviation falls outside of the acceptance tolerance in Table 330-3, immediately make a comparison check at the QC test locations to verify the QC measurements in the section. If the comparisons are beyond the acceptable compar ison tolerance in accordance with 330 -9.3.1, stop the paving operations until the issue is resolved to the FY 2023-24 Return to Table of Contents satisfaction of the Engineer. Correct any cross slope not meeting the individual deviation acceptance tolerance in accordance with 330 -9.5 at no cost to the Department. The Engineer reserves the right to check the pavement cross slope at any time by taking cross slope measurements at any location.
330-9.4 Pavement Smoothness: Construct a smooth pavement meeting the requirements
of this Specification.
330-9.4 1 General: Furnish a 15-foot manual and a 15-foot rolling straightedge
meeting the requirements o f FM 5-509. Obtain a smooth surface on all pavement courses placed, and then straightedge all layers as required by this Specification .
330-9.4 2 Test Method : Perform all straightedge testing in accordance with
FM 5-509 in the outside wheel path of each lane. The Engineer may require additional testing at other locations within the lane.
330-9.4 3 Traffic Control: Provide traffic control in accordance with Section 102
and Standard Plans, Index 102-607 or 102 -619 during all testing. When traffic control cannot be provided in accordance with Index 102-607 or 102 -619, submit an alternative Traffic Control Plan as specified in 102 -4. Include the cost of this traffic control in the Contract bid prices for the asphalt items.
330-9.4 4 Process Control Testing: Assume full responsibility for controlling all
paving operations and processes such that the requirements of these Specifications are met at all times.
330-9.4 5 QC Testing:
330-9.4 5.1 General : Straightedge the final Typ e SP structural layer and
friction course layer in accordance with 330 -9.4.2, with the exception that if the method of acceptance is by laser profiler, then straightedging of the friction course layer is not required unless otherwise stated in the Specific ations. If the project’s method of acceptance is by laser profiler, areas not suitable for testing with the laser profiler will be tested and accepted by straightedging. Test all pavement lanes and ramps where the width is constant and document all deficiencies in excess of 3/16 inch on a form approved by the Engineer.
330-9.4 5.2 Straightedge Exceptions: Straightedge testing will not be
required in the following areas: shoulders, intersections, tapers, crossovers, sidewalks, shared use paths, parking lo ts, raised crosswalks, speed tables, and similar areas , or in the following areas when they are less than 250 feet in length: turn lanes, acceleration/deceleration lanes and side streets. The limits of the intersection will be from stop bar to stop bar for both the mainline and side streets. As an exception, in the event the Engineer identifies a n objectionable surface irregularity in the above areas, straightedge and address all deficiencies in excess of 3/8 inch in accordance with 330 -9.5. The Engineer may waive straightedge requirements for transverse joints at the beginning and end of the project, at the beginning and end of bridge structures, at manholes, and at utility structures if the deficiencies are caused by factors beyond the control of the Contractor, as determined by the Engineer. In addition, the Engineer may also waive the straightedging requirements on ramps and superelevated sections where the geometrical orientation of the pavement results in an inaccurate measurement with the rolling straightedge.
330-9.4 5.3 Intermediate Layers and Temporary Pavement : When the
design spee d is 55 mph or greater and the intermediate Type SP layer or temporary pavement is to be opened to traffic, if the Engineer identifies a n objectionable surface irregularity , FY 2023-24 Return to Table of Contents straightedge and address all deficiencies in excess of 3/8 inch within 72 hours of placement in accordance with 330 -9.5.
330-9.4 5.4 Final Type SP Structural Layer: Straightedge the final
Type SP structural layer in accordance with 330 -9.4.2, either behind the final roller of the paving train or as a separate operation. Notify the En gineer of the location and time of straightedge testing a minimum of 48 hours before beginning testing . The Engineer will verify the straightedge testing by observing the QC straight edging operations. Address all deficiencies in excess of 3/16 inch in accordance with 330 -9.5. When the final structural course is to be opened to traffic and the design speed is 55 mph or greater, if any defect is 3/8 inch or greater, the Engineer may require deficiencies to be corrected within 72 hours after opening to traffic.
330-9.4 5.5 Friction Course Layer: Where required per 330 -9.4.5.1, and
in areas noted in 330 -9.4.6.2 as not suitable for testing with the Laser Profiler, s traightedge the friction course layer in accordance with 330 -9.4.2, either behind the fi nal roller of the paving train or as a separate operation upon completion of all paving operations . Notify the Engineer of the location and time of straightedge testing a minimum of 48 hours before beginning testing . The Engineer will verify the straighted ge testing by observing the QC straightedging operations. Address all deficiencies in excess of 3/16 inch in accordance with 330 -9.5.
330-9.4 6 Acceptance:
330-9.4 6.1 Straightedge Acceptance: For areas of roadways where the
design speed is less than 55 miles per hour, and for areas of roadways where the design speed is greater than or equal to 55 miles per hour which are noted in 330 -9.4.6.2 as not suitable for testing with the Laser Profiler, acceptance for pavement smoothness of the friction course will be based on verified QC measurements using the straightedge as required by 330 -9.4.5. The Engineer will verify the straightedge testing by observing the QC straightedging operations.
330-9.4 6.2 Laser Acceptance: For areas of high speed roadways where
the design speed is equal to or greater than 55 miles per hour, acceptance testing for pavement smoothness of the friction course (for mainline traffic lanes only) will be based on the Laser Profiler. Ramps, acceleration and deceleration lan es, and other areas not suitable for testing with the Laser Profiler will be tested and accepted with the straightedge in accordance with 330 - 9.4.5.5 and 330 -9.4.6.1. The pavement smoothness of each lane will be determined by a Laser Profiler furnished and operated by the Department in accordance with FM 5-549 and a report issued with the Ride Number (RN) reported to one decimal place. If corrections are made , as required following Laser Acceptance, the pavement will not be retested for smoothness using the Laser Profiler. For this testing , the pavement will be divided into 0.1 mile segments. Partial segments equal to or greater than 0.01 mile will be considered as a 0.1 mile segment. The pavement will be accepted as follows :
330-9.5 Unacceptable Pavement:
330-9.5 1 Corrections : Address all areas of unacceptable pavement at no cost to
the Department . Retest all corrected areas and assure the requirements of these Specifications are met.
330-9.5 1.1 Structural Layers: Correct all deficiencies, as defined in the
Specifications, in the Type SP structural layers by r emoving and replac ing the full depth of the layer, extending a minimum of 50 feet on both sides (where possible) of the defective area for the full width of th e paving lane. The following options only apply if the structural layer is not the final surface layer :
330-9.5 1.2 Friction Course: Correct deficiencies in the friction course or
final surface layer by r emoving and replac ing the full depth of the layer, extending a minimum of 50 feet on both sides (where possible) of the defective area for the full width of the paving lane. As an exception, t he Engineer may allow the Contractor to leave these areas in place if it is determined by the Engineer that the deficiency is not a significant detriment to the pavement quality. A reduction to the pay item quantity will be made in accordance with 330 -9.5.2.
330-9.5 2 Reduction in Pay Item Quantity : When the En gineer elects to waive
corrections, the Department will reduce the pay quantity for the pay item in question by the amount of material within the defective area . For all mix types, when the measured deficiency lane length is less than 5 feet, use 5 feet fo r the deficiency lane length when determining the pay reduction. When the pay quantity is in tons, the Department will base the reduction on the volume of material within the defective area (the deficiency lane length by the lane width by layer thickness) multiplied by the maximum specific gravity of the mix as determined through the following equation: Quantity (tons) = L x W x t x Gmm x 0.0024 Where: L = Deficiency Lane length (ft.) FY 2023-24 Return to Table of Contents W = Lane width (ft.) t = Layer thickness (in.) Gmm = Maximum specific gravity from verified mix design For FC-5 open-graded friction course, the Department will base the reduction on the area within the defective area (the deficiency lane length by lane width) multiplied by a spread rate of 80 pounds per square yard as determined through the following equation: Quantity (tons) = L x W x 0.0044 Where: L = Deficiency Lane length (ft.) W = Lane width (ft.)
330-10 Protection of Finished Surface.
Keep sections of newly compacted asphalt concr ete, which are to be covered by additional courses, clean until the successive course is laid. Do not dump embankment or base material directly on the pavement. Dress shoulders before placing the friction course on adjacent pavement. Equip blade graders operating adjacent to the pavement during shoulder construction with a 2 inch by 8 inch or larger board, or other attachment providing essentially the same results, attached to their blades so it extends below the blade edge and protects the pavement surface from damage by the grader blade. To prevent rutting or other distortion, protect sections of newly finished dense -graded friction course and the last structural layer before friction course from traffic until the surface temperature has cooled below 160ºF. The Contractor may use artificial methods to cool the pavement to expedite paving operations. The Department may direct the Contractor to use artificial cooling methods when maintenance of traffic requires opening the pavement to traffic at the earliest possible time. FY 2023-24 Return to Table of Contents SECTION 334 SUPERPAVE ASPHALT CONCRETE
334-1 Description.
334-1.1 General : Construct a Superpave Asphalt Concrete pavement with the type of
mixture specified in the Contract Documents , or when offered as alternates, as selected. Superpave mixes are identified as Type SP-9.5, Type SP-12.5 or Type SP-19.0. Obtain Superpave Aspha lt Concrete from a plant that is currently on the Department’s Production Facility Listing. Producers seeking inclusion on the list shall meet the requirements of Section 105. Producers must meet the requirements of Section 320 for plant and equipment and the general construction requirements of Section 330.
334-1.2 Traffic Levels: The requirements for Type SP Asphalt Concrete mixtures are
based on the design traffic level of the project. The traffic levels for the project are as specified in the Contract Documents.
334-1.3 Gradation Classification: The Superpave mixes are classified as fine and are
defined in 334 -3.2.2. The equivalent AASHTO nominal maximum aggregate size Superpave mixes are as follows: Type SP-9.5................................ ............................... 9.5 mm Type SP-12.5................................ ........................... 12.5 mm Type SP-19.0................................ ........................... 19.0 mm
334-1.4 Thickness: The total thickness of the Type SP asphalt layers will be the plan
thickness as shown in the Contract Documents. Before paving, propose a thickness for each individual layer meeting the requirements of this specification, which when combined with other layers (as applicable) will equal the plan thickness. For construction purposes, the plan thickness and individual layer thickness will be converted to spread rate based on the maximum specific gravity of the a sphalt mix being used, as well as the minimum density level, as shown in the following equation: Spread rate (lb/yd2) = t x G mm x 43.3 Where: t = Thickness (in.) ( plan thickness or individual layer thickness) Gmm = Maximum specific gravity from the verified mix design The weight of the mixture shall be determined as provided in 320 -3.2. For target purposes only, spread rate calculations should be rounded to the nearest whole number. Note: Plan quantities are based on a G mm of 2.540, corresponding to a spread rate of 110 lb/yd2-in. Pay quantities will be based on the actual maximum specific gravity of the mix being used.
334-1.4 1 Layer Thicknesses: The allowable layer thicknesses for Type SP
Asphalt Concrete mixtures are as fol lows: Type SP-9.5................................ ................. 1 to 1-1/2 inches Type SP-12.5................................ ............... 1-1/2 to 3 inches Type SP-19.0................................ ..................... 2 to 4 inches FY 2023-24 Return to Table of Contents