218Blanket for Fill Slopes

GA · 2021 Standard Specifications✓ Full text on BuildSpecBook pages 258–259 Save this section

Ask about Section 218

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

218.1 General Description

This work includes placing a blanket material on fill slopes as shown on the plans.

218.1.01 Definitions

General Provisions 101 through 150.

218.1.02 Related References

A. Standard Specifications Section 893—Miscellaneous Planting Materials B. Referenced Documents General Provisions 101 through 150.

218.1.03 Submittals

General Provisions 101 through 150.

218.2 Materials

Use blanket material that meets the requirements on the plans or in the Special Provisions. Ensure that plant topsoil meets the requirements of Subsection 893.2.01.

216.2.01 Delivery, Storage, and Handling

General Provisions 101 through 150.

218.3 Construction Requirements

218.3.01 Personnel

General Provisions 101 through 150.

218.3.02 Equipment

General Provisions 101 through 150.

218.3.03 Preparation

General Provisions 101 through 150.

218.3.04 Fabrication

General Provisions 101 through 150.

218.3.05 Construction

A. Remove Vegetation, Roots, and Trash Remove vegetation, roots, trash, or materials that hinder the preparation of a proper bed for grassing as a part of this Item. B. Plant Topsoil To reduce plant topsoil loss from erosion, place the soil shortly before and in conjunction with grassing operations, unless otherwise directed. After placing material, replace material lost from erosion at no additional expense to the Department.

218.3.06 Quality Acceptance

General Provisions 101 through 150.

218.3.07 Contractor Warranty and Maintenance

General Provisions 101 through 150.

218.4 Measurement

The quantity of material placed and accepted under this Item is measured in cubic yards (meters), loose measure, in the vehicles at the point of dumping.

218.4.01 Limits

General Provisions 101 through 150.

218.5 Payment

Payment will be made under: Item No. 218 Blanket for fill slopes Per cubic yard (meter)

218.5.01 Adjustment

General Provisions 101 through 150.

Get an email when 218 changes

Georgia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction of Transportation Systems, 2021 Edition. Pages 258–259 of 2,050. View official source ↗