GA · 2021 Standard SpecificationsBook pages View official source ↗

Section 22 2—Aggregate Drainage Courses

222.1General Description

This work includes installing aggregate drainage courses. The drainage courses shall conform to the Specifications and to the lines, grades, and dimensions shown on the Plans or directed by the Engineer. 222.1.01 Defi nitions General Provisions 101 through 150. 222.1.02 Related References

A.Standard Specifications
SECTION 109 — Measurement and Payment
SECTION 208 — Embankments
SECTION 209 — Subgrade Construction
SECTION 806 — Aggregate for Drainage
B.Referenced Documents

General Provisions 101 through 150. 222.1.03 Submittals General Provisions 101 through 150.

222.2Materials

Ensure that materials meet the requirements of the following Specifications: Material Subsection Type I Aggregate Drainage Course 806.2.01 Type II Aggregate Drainage Course 806.2.02 Type III Drainage Blanket Material 806.2.03

222.2.01 Delivery, Storage, and Handling General Provisions 101 through 150.

222.3Construction Requirements

222.3.01 Personnel General Provisions 101 through 150.

255 255 255 255 255 255 255 255 255 255

SECTION 222 — Aggregate Drainage Courses

222.3.02 Equipmen t

A.Embankment or Subgrades

To spread a uniform layer of coarse or fine aggregate without segregation and compact it to the specified requirements, use hauling and spreading equipment approved by the Engineer.

B.Other Surfaces

On any other surface, including wet and unstable areas, use trucks for end -dumping, and bulldozers and road machines for spreading. 222.3.03 Preparation General Provisions 101 through 150. 222.3.04 Fabrication General Provisions 101 through 150. 222.3.05 Construction Construct the roadbed according to the lines, grades, and typical cross -sections shown on the Plans and according to Section 208 and Section 209. Use coarse aggregate, drainage course, and drainage blanket material as follows: Type I Aggregate Drainage Course Use in a trench around pipe or in the shoulder in conjunction with a trench. Type II Aggregat e Drainage Course Use as a drainage blanket under sidewalks, curbs and gutter, and beneath the pavement system or shoulders. Type III Drainage Blanket Material Use on parts of the roadway shown on the Plans as requiring a drainage blanket.

A.Prepared Embankments or Subgrades
1.Place the Material

Spread the material uniformly to obtain the compacted depth required on the Plans and as follows:

a.The maximum thickness of each course is 6 in. (150 mm) compacted, except as noted in Subsection

222.3.02.B, Other Surfaces.

b.If installing an underdrain system immediately under or adjacent to the aggregate drainage course,

connect the drainage course directly to the underdrain system.

c.After placing the pavement, make the subbase outside of the pavement flush with the outside pavement edge. Do not cut cement- stabilized subbase—keep it in place.
d.When necessary, cover a shoulder drainage course with a second layer of shoulder pavement to prevent contaminating the aggregate drainage material.
2.Compact the Material

Compact the material according to the following procedures, and have the Engineer approve it.

a.Unless specified otherwise by the Engineer, begin rolling on the outer edge of the drainage course and

progress toward the center. On super -elevated curves or shoulders, begin rolling on the lower edge and progress toward the higher edge.

256 256 256 256 256 256 256 256 256 256

SECTION 222 — Aggregate Drainage Courses
b.For a Type II aggrega te drainage course, roll when the moisture content of the material is at or near the

optimum moisture.

c.Roll until the surfaces of each layer are uniformly compacted.
d.Compact the final layer with a steel wheel roller weighing no less than 10 tons (9 Mg) o r a vibratory roller

approved by the Engineer.

e.If a layer is deficient in required thickness by more than 3/4 in. (19 mm), scarify the surface and add more

material to the thin area. Compact again according to the Specifications.

B.Other Surfaces
1.Prepare the Area
a.Before placing drainage material, excavate or trench low areas for positive drainage as directed by the

Engineer.

b.Excavate trenches and undercutting to the dimensions and grades indicated on the Plans.
2.Drain the Area

Drain unstable or wet areas when the area is in the subgrade or the original ground surface is an embankment area or a trench. Spread drainage material to the requirements on the Plans or as directed by the Engineer.

3.Compact the Material

Compact drainage material until stable. 222.3.06 Quality Assurance General Provisions 101 through 150. 222.3.07 Contractor Warranty and Maintenance General Provisions 101 through 150.

222.4Measurement

Aggregate drainage course is measured by the ton (megagram) or cubic yard (meter). When measured by the ton (megagram), the weight is determined by approved truck scales at the job site, or by other scales approved in advance. When measured by the cubic yard (meter), the loose volume is determined as specified in Section 109. 222.4.01 Limits General Provisions 101 through 150.

222.5Payment

Aggregate drainage course of the type specified will be paid for at the Contract Unit Price per ton (megagram) or per cubic yard (meter). Payment will be made under: Item No. 222 Aggregate Drainage Course, Type____ Per ton (megagram) Item No. 222 Aggregate Drainage Course, Type ____ Per cubic yard (meter). Item No. 573 Underdrain Pipe including Drainage Aggregate ____ in(mm) Per linear foot (meter)

257 257 257 257 257 257 257 257 257 257

SECTION 222 — Aggregate Drainage Courses

222.5.01 Adjustments If the average thickness for any 1- mile (1600 m) increment exceeds the specified thickness by more than 1 in. (25 mm), the Department will reduce the Contractor’s payment for the excess material. The Department will calculate the excess material by multiplying how much average thickness exceeded the allowable 1 in. (25 mm) tolerance by the surface area of the course.

258 258 258 258 258 258 258 258 258 258