233Haul Roads Section 23 3

GA · 2021 Standard SpecificationsBook pages View official source ↗

Section 23 3—Haul Roads

233.1General Description

This work includes maintaining and repairing haul roads that are county roads and city streets within the State of Georgia. Haul roads on the State Highway System are not included. 233.1.01 Definitions Haul roads: Routes used for transporting materials to a Project. Haul roads include routes described in the Contract and alternate routes approved by the Engineer. 233.1.02 Related References

A.Standard Specifications
SECTION 109 — Measurement and Payment
SECTION 209 — Subgrade Construction
SECTION 317 — Reconstructed Base Course
SECTION 400 — Hot Mix Asphaltic Concrete Construction
SECTION 412 — Bituminous Prime
SECTION 413 — Bituminous Tack Coat
SECTION 424 — Bituminous Surface Treatment
B.Referenced Documents

Form HD -561 Form HD -561A 233.1.03 Submittals If substituting a different road for a haul road designated in the Contract, conduct an inspection o f the proposed haul road in conjunction with the Engineer and the governmental agency or political subdivision charged with the control and maintenance of the route. • After the inspection, prepare an agreement using Form HD- 561A, which states existing cond itions, maintenance conditions during hauling, and restoration after hauling is completed. • Sign the agreement together with the governmental agency or political subdivision. • Submit the agreement for the Engineer’s approval before hauling materials on the proposed route.

275 275 275 275 275 275 275 275 275 275

SECTION 233 — Haul Roads

233.2Materials

Restore haul roads with materials that meet the requirements of the following Specifications: Material Section Stabilizer Aggregate (Type I) 209 Reconstructed Base Course 317 Asphaltic Concrete 400 Bituminous Prime 412 Bituminous Tack Coat 413 Bituminous Surface Treatment 424

If any of the above materials are specified in the original Contract under a modified Specification, furnish materials for haul road maintenance and restoration under the same modified Specification. 233.2.01 Delivery, Storage, and Handling General Provisions 101 through 150.

233.3Construction Requirements

Maintain the haul road to the Engineer’s satisfaction during hauling. 233.3.01 Personnel General Provisions 101 through 150. 233.3.02 Equipment General Provisions 101 through 150. 233.3.03 Preparation The Department will determine sources of local materials and commercially produced aggregates and which haul roads exist for transporting the materials. 233.3.04 Fabrication General Provisions 101 through 150. 233.3.05 Construction

A.Restoration Requirements

When hauling operations are completed, restore the haul road to a condition equal to that which existed before hauling operations were started. • The Engineer will determine the kind and amount of restoration work required and the procedures and requirements to follow. • An obligation to maintain and restore the road will not be relieved in the event that other traffic uses the haul road concurrently. • If another contractor who is also under contract with the Department hauls material over the same route, the Engineer will determine the amount of maintenance and restoration obligation for each contractor. 276 276 276 276 276 276 276 276 276 276

SECTION 233 — Haul Roads

233.3.06 Quality Acceptance

A.Inspection

When the restoration work on a haul road is completed, a joint inspection of the haul road route will be made under the jurisdiction of a governmental agency or political subdivision other than the Department. • Inspect the road in conjunction with the Engineer and the governmental agency or political subdivision charged with the control and maintenance of the restored road. • The Engineer will obtain two copies of the executed Haul Road Release, part of Form HD -561 or HD -561A. • If using a substitute road, the Contractor must obtain the forms specified above and submit them to the Engineer. 233.3.07 Contractor Warranty and Maintenance General Provisions 101 through 150.

233.4Measurement

Materials ordered by the Engineer for maintaining and restoring haul roads are measured as defined in the applicable section of the Specifications. If using a substitute haul road, materials are measured for payment according to the quantities shown on the Plans for the original haul road. Quantities of materials used above those shown on the Plans will not be measured for payment. Blading and shaping costs necessary for maintaining and restoring haul roads are not measured for payment. 233.4.01 Limits General Provisions 101 through 150.

233.5Payment

Stabilizer aggregate will be paid for under the requirements of Section 209. All materials, measured as stated above, will be paid at the Contract Price for the Items shown on the Plans and listed in the Proposal. When the Engineer orders materials other than those listed above, they will be paid on a force account basis under Subsection 109.05, Extra Work. 233.5.01 Adjustments General Provisions 101 through 150.

277 277 277 277 277 277 277 277 277 277

Source: Georgia Standard Specifications Construction of Transportation Systems, 2021 Edition. Pages of 2,050.