Base and Subbase Courses
300.1General Description
This specification applies to all base and subbase courses, except asphaltic concrete. Additional requirements for each type of base and subbase are described in the appropriate sections for specific base and subbase type construction. 300.1.01 Definitions General Provisions 101 through 150. 300.1.02 Related References
Form OMR-TM-141 Daily Truck Weights Form 474 Tally Sheet 300.1.03 Submittals General Provisions 101 through 150. 278 278 278 278 278 278 278 278 278
300.2Materials
Find the specifications for materials to be used and the references for them under the appropriate section for each base and subbase type construction. Ensure that each material meets the requirements for the type specified. Incorporate only materials that meet the Engineer’s approval. Admixtures meeting the requirements of Subsection 831.2.03 and approved for use in stabilized bases or subbases shall be governed by the requirements as outlined in Laboratory Standard Operating Procedure No. 5, Quality Control of Portland Cement and Blended Hydraulic Cements and Quality Control of Fly Ash and Granulated Blast-Furnace Slag.
The Engineer has the authority to classify materials at the source and require the materials to be excavated in the proper sequence so that each kind will reach its destination at the best location for that material in the finished work. The Engineer has the authority to reject any unsuitable materials.
Follow the provisions of Subsection 106.10, Local Material Sources to obtain materials from local sources outside the right-of-way. 300.2.01 Delivery, Storage, and Handling
Store material at a plant site with enough space for separate stockpiles, bins, or stalls for each size of aggregate. Keep aggregates separated until delivery to the plant feeders for proportioning. Keep the storage yard neat and the stockpiles, bins, and stalls accessible for obtaining samples.
300.3Construction Requirements
300.3.01 Personnel Supply all personnel and equipment necessary for obtaining samples from base plants and delivering them to the plant laboratory. 300.3.02 Equipment Ensure that all equipment for constructing base and subbase courses is of an approved design and in satisfactory condition before construction begins. The equipment required for each type of base or subbase will be determined according to the construction method used.
The central mixing plant will not be approved for proportioning, batching, or mixing unless a field laboratory meeting the requirements of Section 152 is available for the exclusive use of the Engineer or Inspector. Design, coordinate, and operate plants so that the mixture is produced within the specified tolerances. The requirements are as follows.
Before any mixture is delivered to the project, check all scales with standard weights for accuracy and for agreement with each other. If weight proportioning is used, provide accurate scales so all ingredients of the mixture can be weighed separately. Use scales that are accurate to within 0.5 percent of the measured load. Support scales with rigid supports so that vibration from the plant does not interfere with accurate readings. 279 279 279 279 279 279 279 279 279
Use springless dial scales of a standard make and design for weight boxes and hopper. Inspect and seal scales when the Engineer determines it necessary to assure accuracy. Ensure that at least ten 50 lb. (25 kg) weights are available for testing the scales.
With each plant, include a motor truck scale with a platform large enough to accommodate the entire length of any vehicle used. Ensure that the scale is certified according to Section 109 and is large enough to weigh the largest anticipated load. Do not measure weights greater than the rated capacity of the scales. Ensure that the weights of the aggregate batches in the truck before delivery to the project are within two percent of the sum of the weights of the batch ingredients. Complete Forms OMR-TM-141 (Daily Truck Weights) and Form 474 (Tally Sheet) for each day’s production and submit them to the Engineer.
Equip each central mix plant with an approved mixer. If Portland cement is required, begin mixing immediately after the cement is added to the coarse aggregate and soil mortar. Continue mixing until a homogeneous and uniform mixture is produced. If the equipment does not produce a homogeneous and uniform mixture that meets these specifications, the Engineer will require the Contractor to make the changes necessary to accomplish this result. Any adjustments made to the charge in a batch mixer or the rate of feed to a continuous mixer must ensure a complete mix of all of the material. Correct dead areas in the mixer where the material does not move or is not sufficiently agitated, by reducing the volume of material or by making other adjustments.
Add Portland cement, bituminous materials, aggregates, or other ingredients in such a manner that they are uniformly distributed throughout the mixture during the mixing operation.
In all plants, proportion water by weight. Provide a means for the Engineer to verify the amount of water per batch or the rate of flow for continuous mixing. Use spray bars to evenly distribute moisture throughout the mixture.
Use sampling equipment approved by the Engineer to obtain samples before combining them with other ingredients or introducing them into the mixer. Use sampling equipment to provide an accurate representation of the furnished material.
Continuous mixing plants shall use a feeder system that accurately proportions aggregate from each bin by weight. Equip each feeder with a device that can change the quantity of material being fed. Use a feeder with adjustments that can be securely fastened. Ensure that the plant has an interlocking system of feeders and conveyors that can be synchronized to supply a continuous flow of aggregate, including a positive flow of dry and liquid additives for mixing. Provide an electronic belt-weighing device to monitor the combined aggregates. Ensure that there are meters for maintaining the aggregates and additives at varying production rates. 280 280 280 280 280 280 280 280 280
Use an electronic control package capable of tracking which accepts a signal from the belt-weighing device and signals to continuously vary the dry and liquid additive feeder speed and maintain the feed rate. Proportion dry additives with a gravimetric (depleting weight) system meeting the following requirements: • The dry additive gravimetric (depleting weight) system includes an isolation vessel supported by load cells independent of the fines silo. • Use load cells in conjunction with an electronic scale package having remote digital display and the necessary controls. Continuously weigh the material being metered with a positive displacement feeder mounted on the discharge of the isolation vessel.
Use a control package that has a plant interlock shutdown capability. Plants must be able to shut down if actual flow rates differ from desired flow rates excessively. If the flow rate deviates excessively, an alarm shall sound at any of the aggregate, dry additive, or liquid additive metering devices. Provide a monitoring station to control the entire operation that shows continuous quantitative data on the production and proportioning of the mix ingredients.
Equip plants that use portable electric power generators with a frequency meter (graduated and accurate to one hertz) and a voltmeter (graduated and accurate to two volts), installed in the power circuit.
Use a mixer equipped with enough paddles or blades to produce a uniform and homogeneous mixture. Replace paddle blades that show more than 25 percent wear in the face area. Use paddles that can be adjusted to angular positions on the shafts and that can be reversed to retard the flow of the mix. Keep the mixer level.
Equip the mixer with a surge hopper. Use a surge hopper that automatically discharges the mixture when it reaches a predetermined level.
Use weigh boxes and hoppers that are suspended on scales, large enough to hold a full batch without spilling or needing hand raking, and equipped with a device for accurately weighing each size of aggregate. Provide a convenient and accurate means of obtaining samples of aggregates from each bin before the material enters the mixing chamber. Equip each bin compartment with a bin level indicator that automatically stops weighing when a bin is empty.
Include an approved, leak-proof batch mixer in the plant. Use a mixer fast enough or equipped with enough paddles or blades to produce a properly and uniformly mixed batch. Replace paddles and blades that show more than 25 percent wear in the face area.
Weigh cement on scales separate from the aggregate batching scales. Ensure that all scales meet the requirements of Section 109.
Introduce bituminous material into the mixer through spray bars and weigh it on scales separate from the aggregate batching scales.
Use a time-locking device that automatically limits mixing time. Do not mix materials less than 30 seconds. 281 281 281 281 281 281 281 281 281
For in-place mixing operations, use mixers that meet the following requirements:
Use approved rotary-type multiple pass mixers with sufficient tines that mix cement, soil or soil-aggregate, and water uniformly for the full depth of the course.
Use approved traveling mixing plants to pick up the aggregate, soil, or other materials from the windrow or roadway. Use plants equipped with a bottom shell or pan that pick up and mix the material while it is separated from the foundation material during at least 50 percent of the mixing cycle. Use plants that mix the material for the full depth of the section. Ensure that travelling plants move forward with successive increments the length and width of the roadbed so that the roadbed is compacted and finished in one operation. Ensure that none of the materials being mixed are lost or segregated. Use plants mounted on wheels or crawler tracks wide enough so that they will not rut or damage the mixed surface when loaded to capacity.
Use plants with a pressurized metering device that introduces water during mixing.
Ensure that devices for proportioning water and materials to be mixed accurately measures the specified
amounts while the machine is in motion.
For bituminous stabilization, use plants equipped with a metering device that accurately measures the
bituminous material into the mixer within the tolerances specified in Section 302.3.05.B. Ensure that the meter
indicator dial has a scale with divisions indicating gallons (liters).
If mixing equipment does not produce a homogeneous and uniform mixture, make the changes necessary to
produce this result, as required by the Engineer.
When the material is to be mixed in-place, use an approved mechanical cement spreader to uniformly and
accurately spread the cement. Do not use pneumatic tubes to transfer the cement from the tanker to the material
to be stabilized.
Use an approved mechanical spreader that meets the following requirements to uniformly spread the mixture:
• A height-adjustable strike-off plate to obtain the specified thickness of the finished base
• A self-propelled spreader with rollers to contact the truck tires and push the truck without skewing the
spreader or truck
• A hopper large enough to prevent spilling or wasting the material
Use static rollers that meet the following requirements. Use self-propelled static rollers on cement stabilized base.
In this context, “roller” describes a wheel made of a flat metal surface; “wheel” describes a rubber wheel of
the automotive type.
When base widening is specified, use at least one trench roller. Use a trench roller that has a guiding roller or
wheel that operates in tandem with the compression roller on the area to be compacted or with the auxiliary
wheel or roller.
Ensure that the trench roller is equipped with an auxiliary wheel or roller, mounted on a height-adjustable axle.
The contact surface of the auxiliary wheel or roller must be adjustable to at least 10 in. (250 mm) above and
2 in. (50 mm) below the rolling plane of the compression roller. If this adjustment is not sufficient to compact
the subgrade to the Plan elevation, adjust the contact surface the necessary amount.
If the steering roller or wheel operates in tandem with the auxiliary wheel or roller, it does not need to be
height-adjustable. 282282282282282282282282282
Ensure that the auxiliary wheel or roller operates on the surface of the pavement adjacent to the area to be
compacted, and at a distance from the edge of the pavement that no damage occurs. Keep the height
adjustment of the auxiliary wheel or roller such that the compression roller will develop a smooth, compacted
surface true to crown.
Use gas-propelled trench rollers equipped with reversing, smooth operating friction clutches. Ensure that
friction clutches have smooth operating brakes of ample capacity. Use either hand-powered or power-
operated steering devices.
The compression per inch (25 mm) width of compression roller shall not be less than 300 lbs. (545 kg) and not
greater than 365 lbs. (660 kg). If necessary, use a hollow compression roller and secure the minimum weight
with liquid ballast. The trench roller must compact a minimum width of at least 15 in. (375 mm).
Fit rollers with adjustable spring scrapers that can scrape in both directions.
Use three-wheel or tandem steel-wheel rollers. Use self-propelled rollers equipped with cleaning devices to
prevent material from adhering to the wheels.
For base or subbase materials, use 3-wheel rollers on base or subbase materials that have a minimum weight
of 10 tons (9 Mg) and a minimum compression of 325 pounds per inch (580 kg/100 mm) of width for the rear
wheels.
Use steel wheel tandem rollers with a minimum weight of 10 tons (9 Mg) and a minimum compression of
225 pounds per inch (400 kg/100 mm) of width for the rear drum.
Use pneumatic-tire rollers with a minimum contact pressure of 50 psi (345 kPa) per wheel.
Equip rollers to uniformly distribute the load between all wheels.
Use multiple axle, multiple wheel rollers with wheels staggered on the axles and spaces between each wheel
to provide uniform compaction for the full compacting width of roller.
Ensure that the air pressure of any tire does not vary more than 5 psi (35 kPa) from the established pressure.
Operate rollers between 3 mph (5 kph) and 8 mph (13 kph), unless otherwise directed by the Engineer.
Use vibratory or static compaction sheepsfoot rollers of sufficient size and weight to obtain the desired
compaction.
Use an approved vibratory roller designed to activate the frequency of vibration and the roller movement
separately. Ensure that the weight and amplitude of the roller can compact the surface to specifications with a
minimum number of passes.
Use bituminous transfer pumps that include a valve for sampling bituminous materials.
Specifications for the Fine Grading Machine are included in either a Special Provision or a Supplemental
Specification in the proposal or in the current Supplemental Specification book. 283283283283283283283283283
300.3.03 Preparation
When alternate methods of construction are provided without restriction, the Contractor may select these
alternate methods at will, provided the equipment and organization are suited to the method selected. Before
starting construction, discuss the proposed method with the Engineer. The method selected must:
• Spread base or subbase material uniformly without damaging the subgrade, subbase, or the material
being placed
• Mix the materials until they are homogeneous
• Use the specified water and cement or bitumen content
• Compact throughout the depth of the course to the density specified
• Complete the work within the specified time limits
Organize the work and equipment so that spreading, compacting, and finishing the base or subbase is a
continuous operation. Do not exceed minimum or maximum time limits where the detailed Specifications require
them, except in unusual cases where permitted by the Engineer.
Remove grass, weeds, roots, and other debris from local materials pits. Adhere to the requirements of
Subsection 107.23, Environmental Considerations when performing this work. Include the cost in the prices bid for
the pertinent Pay Items. This work is not considered as clearing and grubbing.
If the subgrade does not meet the requirements of Section 209 for surface, compaction, and stability, repair all
defective portions until it meets the requirements of that Section. Remove unsuitable materials and replace with
acceptable material, if necessary. Compact the subgrade as specified in Section 209.
Have enough prepared subgrade meeting the requirements of Section 209 for at least one day of base
construction before beginning work.
If a subbase is required, prepare it according to the requirements for surface and compaction. Ensure that it is
stable enough to support the equipment that will place the base material without rutting or pumping. Repair all
defective portions and replace any unsuitable material with acceptable material, if the subbase does not meet the
requirements of the specifications.
300.3.04 Fabrication
General Provisions 101 through 150.
300.3.05 Construction
Keep materials pits well drained while materials are being removed from them. After removing materials, leave pits
in the condition required by Section 106 and Section 160.
Mine all local materials pits within the pit boundaries and grid depths established by the Engineer.
Mine all materials from top to bottom. Mix materials in the pit before hauling to the roadbed or plant.
Place materials in windrows or stockpiles with a dragline or backhoe. Blend the gradation and moisture strata
from each pit to a uniform mixture.
When a rim ditch is required and its depth exceeds the specified grid depth of soil-cement material, include only
the material above the grid depth as base material. Use this material for the windrow or stockpile of material to be
used for soil-cement base unless the Engineer determines that below-the-grid material is satisfactory. 284284284284284284284284284
Only use ladder pans and scrapers for stockpiling and windrowing in pits that are less than 18 in (450 mm) deep.
After the preliminary mixing, prevent the coarse materials from segregating from the fine materials with loading
equipment that continues to blend the material.
The Engineer will determine the proportions of the materials to be used in compounding the base or subbase.
The Engineer will determine the analysis basis of the components.
Change the mix, if required by the Engineer, to ensure that the finished base meets the requirements of
these specifications.
Control the moisture content according to the specified requirements for each type of base or subbase.
Add water uniformly, allow it to evaporate or aerate, and roll the materials as often as necessary, to control the
moisture content within the limits specified.
Because the maximum thickness of base or subbase materials to be mixed or spread in one course varies
with the equipment used, it is subject to the Engineer’s approval. Ensure that the thickness meets the
requirements of Subsection 300.3.05.C.5, Compaction.
Ensure that widening work conforms to Section 150.
When widening in traffic areas, excavate an area that can be completed in the same day.
When widening pavement on which there is traffic on both sides, stagger operations to keep the widening
trench open in one lane of traffic at a time.
Compact the entire thickness of all bases and subbases to the specified maximum dry weight per cubic foot
(meter), as determined by the method specified in the Section for each base or subbase.
If any base or subbase is more than 6 in. (150 mm) thick, construct according to the following table for
layer thickness:
Material Layer Thickness
Topsoil, Sand-Clay, or Chert Two equal layers, or one layer not to exceed 8 in. (200 mm)
Graded Aggregate Two equal layers, or one layer not to exceed 8 in. (200 mm)
Cement Stabilized Graded Aggregate Two equal layers, or one layer not to exceed 8 in. (200 mm)
Cement Stabilized Soil Aggregate Two equal layers, or one layer not to exceed 8 in. (200 mm)
Sand Bituminous Two equal layers, or one layer not to exceed 8 in. (200 mm)
Soil-Cement One layer not to exceed 8 in. (200 mm)
Produce a smooth, uniform surface that complies with these specifications.
Rebuild any areas that do not meet the requirements or remove or add material to the area until the Engineer
approves of the work. 285285285285285285285285285
300.3.06 Quality Acceptance
Ensure that the mixture and the materials used meet the following quality controls:
• Before producing any mixture for the project, calibrate the electronic sensors, devices, or settings for
proportioning all mixture ingredients by scale weight. Calibrate in the presence of the Engineer, the
proportioning of every ingredient for all rates of production.
• Maintain a dated, written record of the most recent calibration. Post the calibration at the base plant and
make the record available for the Engineer’s inspection at all times. Format records as graphs, tables,
charts, or mechanically prepared data. If the material changes, the rate of production changes by more
than +/- 20%, the plant is not producing base material for more than two weeks, or if a component
affecting the ingredient proportions has been repaired, replaced, or adjusted, check and recalibrate
the proportions.
• Verify the moisture of the mixture being produced. Perform checks on ingredient proportioning and verify
truck weight as directed by the Engineer.
Provide quality control personnel and all necessary equipment to perform and document moisture tests.
Perform moisture tests at a frequency of at least one test per hour of base plant production.
During construction: If materials that do not meet these specifications are placed on the roadway at any time
during construction, remove and replace them with acceptable materials as a part of the Pay Item for the base or
subbase being constructed.
After construction: Promptly correct defects discovered in the surface finish, thickness, or compaction of the
completed base or subbase before the work is accepted.
• If the base, subbase, or shoulders are deficient in thickness and it is determined that the subgrade
elevation is high, remove the materials, lower the subgrade, and reconstruct the course, according to these
specifications at no cost to the Department.
• If job conditions permit and the Engineer mandates, correct areas deficient in thickness by raising the
elevation of the surface or adding material to the course.
• In other cases, the Engineer may determine that the defective portions must be entirely removed. Add, mix,
spread, and compact new material according to the specifications and at no cost to the Department.
• If a surface is less than 3 in. (75 mm) deep, scarify the area to a depth of at least 3 in. (75 mm), except in
the case of stabilized bases or subbases. Mix and compact the new and old materials.
• Repair stabilized bases or subbases according to Section 301, Section 302, Section 310, or Section 316,
whichever is applicable.
300.3.07 Contractor Warranty and Maintenance
General Provisions 101 through 150.
300.4Measurement
Base and Subbase courses will be measured in accordance with the specification section for the item.
Bituminous prime will not be measured for separate payment.
300.4.01 Limits
General Provisions 101 through 150. 286286286286286286286286286
300.5Payment
Base and Subbase courses will be paid for in accordance with the specification section for the item. Include the cost
of furnishing and applying bituminous prime in the Unit Price Bid for each individual Base Item according to the
applicable provisions of Section 412.
No separate payment will be made for adding water or for aerating or rolling for the purpose of adding water. Include
the cost of controlling moisture content in the prices bid for the pertinent Pay Items.
Separate payment will be made only for clearing and grubbing listed in the proposal or required in the plans and
designated a Pay Item by the Engineer.
No separate payment will be made for stripping excavation unless shown on the plans and included in the proposal as
a Pay Item.
300.5.01 Adjustments
If the Contractor for the subbase or base is responsible for the subgrade under another Pay Item, no additional
payment will be made for any repairs made to the subgrade, except as provided in Section 209.
If another party (not the Contractor) is responsible for the subgrade, removing unsuitable materials will be paid for
according to the Earthwork Item in the Contract.
Include compaction, scarification, and any other preparation necessary for the subgrade in the Unit Price Bid for the
pertinent base course.. 287 287 287 287 287 287 287 287 287