for Highway Construction Page 187 of 71 5 SECTION 303 – AGGREGATE BASE
303.01 Description.
Provide, place, and construct 1 or more courses of aggregate on a prepared surface.
303.02 Materials.
Provide aggregate as specified in 703. The Department will accept the aggregate from the windrow or roadway. If purchased and stockpiled, acceptance will be at the crushing plant. The Contractor may use crushed glass in base. Uniformly blend the crushed glass with the aggregate. Ensure the glass -aggregate blend meets the aggregate gradation specified. The Contractor may use glass crushed to ¾ inch minus up to approximately 15 percent by weight of aggregate base . Place the glass -aggregate base material at least 1 foot below unpaved surfaces. The Contractor may use glass crushed to 5/16 inch minus up to approximately 15 percent by weight in aggregate base , with no restriction on location. Use the following standard methods for tests: Compaction Standard for Coarse Granular Materials by Use of the Vibratory Spring- load Compactor ......................................................... Idaho IT 74 In-Place Density and Moisture Content of Soil and Soil Aggregate by Nuclear Methods (Shallow Depth) ................................................. AASHTO T 310 Method B Instead of Idaho IT 74, if approved, the maximum dry density of aggregate base may be determined as follows: Moisture Density Relations of Soils ........................................................... AASHTO T 180 Method D Prepare and submit an Idaho IT 74 density curve or an AASHTO T 180 Method D moisture density curve for the aggregate base before placing. This testing is incidental .
303.03 Construction Require ments.
303.04 Method of Measurement.
The Engineer will measure acceptably completed work as follows:
303.05 Basis of Payment .
The Department will pay for accepted quantities as follows: ___ Aggregate Type __ Base ................................................................. Ton or CY ___ Aggregate Type __ Stockpile ........................................................... Ton or CY ___ Aggregate Type __ Load/Haul/Place ............................................... Ton or CY A separate pay ment will not be made for glass used in aggregate base . for Highway Construction Page 189 of 71 5 SECTION 304 – RECONDITIONING
304.01 Description.
Recondition the surface of an existing road, shape the shoulders, and dispose of surplus material.
304.02 Materials.
Not specified.
304.03 Construction Requirements.
Scarify the roadbed, including the shoulders to the depth and width specified. Pulverize the scarified material so 5 percent or less of this material, exclusive of gravel or stone, is retained on a 2 -inch sieve. Moisten and compact the pulverized material to the required density. Blade and water the surface, if directed, and continue blading and watering during the rolling operations. Satis factorily main tain the surface until the base or surface course has been placed. Apply additional water to prevent checking or raveling, if needed. Excavation and repair soft spots as specified in 205 .03.E .
304.04 Method of Measurement.
The Engineer will measure acceptably completed work as follows:
304.05 Basis of Payment .
The Department will pay for accepted quantities as follows: Pay Item Pay Unit Reconditioning ........................................................................................ Station or Mile Water for Reconditioning ........................................................................ MG Excavation of Soft Spots ......................................................................... CY Soft Spot Repair ..................................................................................... CY The Department will pay for removal and disposal of unsuitable material under excavation of soft spots. The Department will pay for backfill material used to replace unsuitable material under its respective item or as extra work (104.02) . The Department will not pay for the Contractor’s optional replacement material.