214GRADING AND SHAPING DITCHES

IL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 119–119 Save this section

Ask about Section 214

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Art. 214.01 Grading and Shaping Ditches Other means of locating existing farm underdrains approved by the Engineer will be paid for according to Article 109.04. SECTION 214. GRADING AND SHAPING DITCHES

214.01 Description. This work shall consist of grading and shaping existing

ditches according to the lines, grades, and cross sections shown on the plans. CONSTRUCTION REQUIREMENTS

214.02 General. All surplus and unsuitable material shall be disposed of

according to Article 202.03.

214.03 Method of Measurement. This work will be measured for payment in

feet (meters) along the centerline of the ditch. The volume of any surplus or unsuitable material removed will be measured for payment according to Article 202.07.

214.04 Basis of Payment. This work will be paid for at the contract unit price

per foot (meter) for GRADING AND SHAPING DITCHES. Earth excavation for surplus material and removal and disposal of unsuitable material will be paid for according to Article 202.08. LANDSCAPING SECTION 250. SEEDING

250.01 Description. This work shall consist of preparing the seed bed and

placing the seed and other materials required in seeding operations on the shoulders, slopes, and other areas.

250.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Seeds ................................................................................................ 1081.04
b.Agricultural Ground Limestone .......................................................... 1081.07
c.Fertilizer ............................................................................................. 1081.08

250.03 Equipment. Equipment shall be according to the following.

Item Article/Section

a.Disk ................................................................................................ 1101.08(a)
b.Slope Harrow ................................................................................. 1101.08(b)
c.Hydraulic Seeder ........................................................................... 1101.08(c)
d.Cultipacker ..................................................................................... 1101.08(d)

Get an email when 214 changes

Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 119–119 of 1,217. View official source ↗

Ask about this section

Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 214 — GRADING AND SHAPING DITCHES. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.