Art. 214.01 Grading and Shaping Ditches Other means of locating existing farm underdrains approved by the Engineer will be paid for according to Article 109.04. SECTION 214. GRADING AND SHAPING DITCHES
214.01 Description. This work shall consist of grading and shaping existing
ditches according to the lines, grades, and cross sections shown on the plans. CONSTRUCTION REQUIREMENTS
214.02 General. All surplus and unsuitable material shall be disposed of
according to Article 202.03.
214.03 Method of Measurement. This work will be measured for payment in
feet (meters) along the centerline of the ditch. The volume of any surplus or unsuitable material removed will be measured for payment according to Article 202.07.
214.04 Basis of Payment. This work will be paid for at the contract unit price
per foot (meter) for GRADING AND SHAPING DITCHES. Earth excavation for surplus material and removal and disposal of unsuitable material will be paid for according to Article 202.08. LANDSCAPING SECTION 250. SEEDING
250.01 Description. This work shall consist of preparing the seed bed and
placing the seed and other materials required in seeding operations on the shoulders, slopes, and other areas.
250.02 Materials. Materials shall be according to the following.
Item Article/Section
250.03 Equipment. Equipment shall be according to the following.
Item Article/Section
Get an email when 214 changes
Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.