480EARTH SHOULDERS AND MEDIANS

IL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 308–309 Save this section

Ask about Section 480

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Earth Shoulders and Medians Art. 480.03 Existing raised reflective pavement markers shall be protected during the crack or joint sealing operations. Tracking of sealant material will not be allowed. If sealant materials are applied to the markers, such material shall be removed.

452.05 Method of Measurement. This work will be measured for payment as

follows.

a.Joint or Crack Routing or Sawing. Routed or sawed joints or cracks will be measured for payment in feet (meters) along the routed or sawed joint or crack.
b.Joint or Crack Filling. Filling of joints or cracks will be measured for payment in pounds (kilograms) of sealant used. The amount of sealant used will be determined by counting the containers or sealant used, multiplied by the indicated pounds (kilograms) of each container.

452.06 Basis of Payment. This work will be paid for at the contract unit price

per foot (meter) for JOINT OR CRACK ROUTING (PC CONCRETE PAVEMENT AND SHOULDER) and JOINT OR CRACK ROUTING HOT-MIX ASPHALT SHOULDER; and per pound (kilogram) for JOINT OR CRACK FILLING. Furnishing and installing backer rod when required by the Engineer will be paid for according to Article 109.04. SHOULDERS SECTION 480. EARTH SHOULDERS AND MEDIANS

480.01 Description. This work shall consist of constructing earth shoulders

and medians. CONSTRUCTION REQUIREMENTS

480.02 General. The shoulder and median shall be constructed with earth

which is free from vegetation, roots, sod or other objectionable material. The shoulders and medians may be constructed and finished with a blade grader. The earth in shoulder and median areas shall be compacted as specified in Article 205.06, except that the earth in the area between curb or gutter and sidewalk shall be compacted in a manner meeting the approval of the Engineer. Prior to final blading and shaping of the shoulders and medians, they shall be rolled with a pneumatic-tired roller meeting the requirements of Article 1101.01.

480.03 Rigid Type Surfacing, Curb, Gutter, or Curb and Gutter. At

locations where shoulders or medians are constructed adjacent to a portland cement concrete pavement, portland cement concrete base course, curb, gutter, or curb and gutter, placing of the earth for the shoulders or medians shall be completed and the Art. 480.04 Aggregate Shoulders earth compacted, shaped and finished to the lines, grades and cross sections shown on the plans after the surfacing, curb, gutter, or curb and gutter has been constructed.

480.04 Nonrigid Type Surfacing. At locations where shoulders or medians

are constructed adjacent to nonrigid type surfacing such as aggregate base or surface course, or any hot-mix asphalt surface course not constructed on a portland cement concrete base course, the following shall apply.

a.When the Base or Surface Course is constructed in a trench. Before the material for the base or surface course is deposited, earth shall be roughed in for the shoulders. The earth shall be placed so that it will be possible to retain and compact the edges of the base or surface course. After the base or surface course has been constructed, the balance of the earthwork required to complete the shoulders and median shall be performed, and the shoulders and median shall be shaped and trimmed to the lines, grades and cross sections shown on the plans.
b.When the Base or Surface Course is not constructed in a trench. Before the base or surface course is constructed, the earthwork required to complete the shoulders and median shall be shaped and trimmed to the lines, grades and cross sections shown on the plans.

480.05 Basis of Payment. This work will not be measured or paid for

separately. SECTION 481. AGGREGATE SHOULDERS

481.01 Description. This work shall consist of furnishing, placing, shaping,

and compacting aggregate on a prepared subgrade adjacent to the edges of the completed pavement structure or stabilized shoulder.

481.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Coarse Aggregate .............................................................................. 1004.04
b.RAP Material (Note 1) ............................................................................. 1031 Note 1. Reclaimed asphalt pavement (RAP) may be used as aggregate wedge shoulders Type B.

481.03 Equipment. Equipment shall be according to the following.

Item Article/Section

a.Tamping Rollers ................................................................................. 1101.01
b.Pneumatic-Tired Rollers .................................................................... 1101.01
c.Three-Wheel Rollers (Note 1) ............................................................ 1101.01
d.Tandem Rollers (Note 1) ................................................................... 1101.01
e.Vibratory Machine (Note 2)
f.Aggregate Spreaders ......................................................................... 1102.04

Get an email when 480 changes

Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 308–309 of 1,217. View official source ↗

Ask about this section

Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 480 — EARTH SHOULDERS AND MEDIANS. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.