Slope Wall Art. 511.02 Rail elements shall be extruded in modular lengths of 30 ft (9 m), except for end/terminal sections, over expansion joints, or sections curved to a radius of 2300 ft (700 m) or less. Each rail element shall be attached to no less than two posts. All joints in rails shall be spliced as detailed. Three aluminum shims per post, one at 1/8 in. (3 mm) and two at 1/16 in. (2 mm), shall be provided for 25 percent of the posts. Shims shall be similar to base plate in size and holes.
509.09 Method of Measurement. This work will be measured for payment in
place in feet (meters). The length measured will be the overall length along the top longitudinal railing member through all posts and gaps.
509.10 Basis of Payment. This work will be paid for at the contract unit price
per foot (meter) for STEEL RAILING, or ALUMINUM RAILING, of the type specified; STEEL RAILING (TEMPORARY); TUBULAR THRIE BEAM RETROFIT RAIL FOR BRIDGES; PEDESTRIAN RAILING; BICYCLE RAILING; BRIDGE FENCE RAILING; BRIDGE FENCE RAILING (SIDEWALK); PARAPET RAILING; and PIPE HANDRAIL. SECTION 510. RESERVED SECTION 511. SLOPE WALL
511.01 Description. This work shall consist of constructing a reinforced
concrete or bituminous coated aggregate slope wall on a prepared earth bed.
511.02 Materials. Materials shall be according to the following.
d.Bituminous Materials (Note 2) ................................................................ 1032 Note 1. The aggregate used for bituminous coated aggregate slope wall shall be crushed stone conforming to Article 1004.01 for Class D quality, except that one of the following options shall apply. COARSE AGGREGATE QUALITY QUALITY TEST Option 1 Option 2 Na2SO4 Soundness 5 Cycle, Max. % Loss Illinois Modified AASHTO T 104 35 25 Los Angeles Abrasion, Max. % Loss Illinois Modified AASHTO T 96 45 65 The aggregate gradation shall be RR 2 according to Article 1005.01(c). Note 2. The bituminous material used for the bituminous coated aggregate slope wall shall be RS-2 or RC-70. Art. 511.03 Slope Wall CONSTRUCTION REQUIREMENTS
511.03 General. Preparation of the earth bed, excavation, backfilling, and
disposal of surplus material shall be according to Section 502.
a.Reinforced Concrete Slope Wall. Reinforced concrete slope wall shall be according to Section 503 and constructed in alternating sections, each approximately 9 ft (2.7 m) in width. Concrete slope walls shall be reinforced with welded wire reinforcement, supported 2 in. (50 mm) below the upper surface of the slope wall by concrete blocks. A clear distance of 2 in. (50 mm) shall be maintained between the welded wire reinforcement and the outside face of any vertical or inclined anchor or cutoff wall. The welded wire reinforcement shall be continuous across construction joints and shall extend into each section a minimum of 6 in. (150 mm) from any adjacent previously placed section. Adjacent sections of welded wire reinforcement shall be lapped a minimum of 6 in. (150 mm).
b.Bituminous Coated Aggregate Slope Wall. Bituminous coated aggregate slope wall shall consist of crushed aggregate placed on the prepared slope, shaped and compacted to the satisfaction of the Engineer. After the aggregate has dried to the satisfaction of the Engineer, the bituminous material shall be applied at a minimum rate of 1 gal/sq yd (4.5 L/sq m). The rate shall be sufficient to penetrate and bind together the particles in the upper 2 in. (50 mm) of the crushed aggregate. The adjacent structure shall be protected from bituminous material to prevent spattering or discoloration.
511.04 Method of Measurement. This work will be measured for payment as
follows.
a.Contract Quantities. The requirement of the use of contract quantities shall be according to Article 202.07(a).
b.Measured Quantities. This work will be measured for payment in place and the area computed in square yards (square meters). The area for measurement will include the upper, sloped surface of the wall. Anchor and cutoff walls will not be measured for payment.
511.05 Basis of Payment. Reinforced concrete slope walls will be paid for at
the contract unit price per square yard (square meter) for SLOPE WALL of the thickness specified. Concrete protected according to Article 1020.13(d) may be paid for at the adjusted unit prices according to Article 503.22. Bituminous coated aggregate slope walls will be paid for at the contract unit price per square yard (square meter) for BITUMINOUS COATED AGGREGATE SLOPEWALL, of the thickness specified. Piling Art. 512.04 SECTION 512. PILING
512.01 Description. This work shall consist of furnishing and driving piles.
512.02 Materials. Materials shall be according to the following.
l.Controlled Low-Strength Material (CLSM) .............................................. 1019 Note 1. Pile encasement in rock shall be Class SI concrete. CONSTRUCTION REQUIREMENTS
512.03 Precast Concrete and Precast, Prestressed Concrete Piles.
Precast concrete piles shall be manufactured according to Section 1042 and precast, prestressed concrete piles shall be manufactured according to the Department’s “Manual for Fabrication of Precast, Prestressed Concrete Products” in effect on the date of invitation for bids.
a.Splicing. Splicing of precast concrete or precast, prestressed concrete piles for the purpose of driving additional length will not be allowed.
b.Extensions. Extensions on precast concrete or precast, prestressed concrete piles shall be avoided; but when necessary, they shall be made as shown on the plans.
c.Reinforcement. Construction requirements for reinforcement bars shall be according to Section 508.
512.04 Metal Shell Piles. Metal shell piles shall consist of a steel shell with a
welded end plate which is driven into place and filled with concrete. The walls of all shells shall be not less than the minimum specified as shown on the plans.
a.Splicing. Splicing of metal shell piles shall be as follows.
1.Planned Splices. All field or shop splices necessary to furnish pile lengths up to the estimated lengths as shown on the plans shall be considered to be planned splices and may be used when allowed per
Article 512 — 10. The location of planned splices shall be approved by the
Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.
Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 414–416 of 1,217. View official source ↗
Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 511 — SLOPE WALL. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.