Art. 503.01 Concrete Structures does not contain a pay item for rock excavation for structures and this item is required, it will be paid for according to Article 109.04. Removal and disposal of unstable and/or unsuitable material will be paid for at the contract unit price per cubic yard (cubic meter) for REMOVAL AND DISPOSAL OF UNSUITABLE MATERIAL FOR STRUCTURES. When the contract does not contain a pay item for removal and disposal of unstable and/or unsuitable material for structures and this item is required, it will be paid for according to Article 109.04. Where it is necessary to excavate below the plan bottom of footing elevation, the excavation will be paid for at the contract unit prices for the class of excavation involved. Furnishing and placing the crushed stone, gravel, or other material will be paid for according to Article 109.04. Cofferdams, when specified, will be paid for at the contract unit price per each for COFFERDAM (TYPE 1) or COFFERDAM (TYPE 2), at the locations specified. When added to the contract, cofferdams will be paid for according to Article 109.04. Tree removal and protection of existing plant material will be paid for according to Section 201. Additional suitable material required for backfilling within the roadbed, will be paid for according to Article 109.04. When ordered by the Engineer in writing, cofferdam inspection by a certified diver will be paid for according to Article 109.04. SECTION 503. CONCRETE STRUCTURES
503.01 Description. This work shall consist of constructing cast-in-place
concrete structures.
503.02 Materials. Materials shall be according to the following.
Item Article/Section
503.03 Equipment. Equipment shall be according to the following.
Item Article/Section
503.04 Excavation and Backfill. Excavation and backfill shall be according
to Section 502. Substructures, foundations, and footings shall be constructed in open excavation wherever practicable.
503.05 Falsework. The falsework shall be designed, constructed, and
maintained for the required loads and site conditions. The Contractor shall submit detailed plans and computations for falsework, prepared and sealed by an Illinois Licensed Structural Engineer, for examination by the Engineer. If such plans are not satisfactory to the Engineer, the Contractor shall make such changes in them as may be required. For continuous concrete slab and cast-in-place concrete girder bridges, falsework shall be provided for the full length of each continuous unit and the full width of the structure. For calculating the strength of falsework, a weight (mass) of 150 lb/cu ft (2400 kg/cu m) shall be assumed for the concrete. The design of the falsework shall take into account the weight of the concrete and also other loads incidental to the construction operations. All falsework shall be designed and constructed to provide the necessary rigidity and to support the imposed loads without appreciable settlement or deformation. The Contractor shall make allowance for the deflection, shrinkage, and settlement of falsework, in addition to the allowance for the amount of dead load deflection and camber shown on the plans. A method satisfactory to the Engineer shall be used to detect any settlement that may occur during the placing of the concrete. Falsework bents shall be founded upon piling driven to a capacity sufficient to support the load without appreciable settlement. If the soil is firm and well compacted, the Contractor may, as an alternate, place falsework bents upon concrete footing or mud sills of sufficient size that the pressure on the soil will not exceed 1 1/2 tons/sq ft (145 kPa) or the Contractor may support falsework from the piers or abutments, provided sleeves for any tie bolts can be cast into the concrete. Sleeves or other appurtenances cast into the concrete shall be constructed so as to permit their removal to a depth of at least 1 1/2 in. (40 mm) from the face without injury to the concrete. Drilling into existing piers or abutments that are to remain as a part of the final structure will not be permitted for the support of falsework. The Engineer may require the Contractor to use screw jacks or hardwood wedges to take up any settlement in the form work, either before or during the placing of the concrete. Falsework supporting forms for cast-in-place concrete shall remain in place until tests show that the concrete has attained the required flexural strength and the curing period is completed. In the absence of tests to determine the flexural strength, the falsework shall remain in place until at least 14 days have elapsed after the placing of the concrete, exclusive of days in which the temperature falls below 45 °F (7 °C). When either fly ash or ground granulated blast-furnace slag has been used in the concrete mixture, falsework shall remain in place a minimum of 28 days from the time of concrete placement in the absence of strength tests. Art. 503.06 Concrete Structures No superimposed load, either dead or live, will be allowed upon the bridge or component during the period the falsework is required to remain in place. If longitudinal construction joints are provided in the roadway of any superstructure, the falsework shall not be released under one portion adjacent to such a joint until the concrete in that portion has attained the required strength and the concrete has been placed in the portion on the opposite side of such joint. The falsework shall not be removed from either side of such joint until all the concrete has attained the required flexural strength and the curing period is completed. A compressive strength established through field testing to be equivalent to the required flexural strength may be used if approved by the Engineer. Falsework shall be removed in such a manner as to permit the concrete to take uniformly and gradually the stress due to its weight (mass).
503.06 Forms. Forms shall be set and maintained to the lines and grades
shown on the plans, and shall be tight to prevent concrete leakage. For continuous concrete slab and cast-in-place concrete girder bridges, forms shall be provided for the full length and width of each continuous unit formed. The Contractor shall submit detailed plans for forms for review and approval by the Engineer. A weight (mass) of 150 lb/cu ft (2400 kg/cu m) shall be assumed for the concrete in the design of the forms. The design of the forms shall provide for accommodation of incidental loads, settlement, deadload deflection, shrinkage, and deformation of the form components. The forms shall provide the structural capacity required to produce finished concrete to the lines and grades specified on the plans. Forms shall be constructed of wood or metal. Supporting or attaching forms by welding to or drilling or cutting holes in beams will not be allowed. Wood forms for exposed surfaces shall be made of dressed lumber or plywood. Except for curved and special surfaces, wood forms shall be surfaced on both sides and both edges and shall be sized to uniform thickness. Metal forms shall be of such thickness that they will remain true to shape. All bolts and rivet heads in contact with concrete shall be countersunk. Clamps, pins, and other connecting devices shall be designed to hold the forms rigidly in place and to allow removal without injury to the concrete. Metal forms which do not present a smooth surface or line up properly shall not be used. Metal forms shall be free from rust, grease, or other foreign matter. Forms shall be filleted at all sharp corners. Triangular moldings used for fillets or V-shaped notches shall have two equal sides. Where the size of the molding is specified, the dimension stated shall be the width of each of the equal sides. Moldings for fillets and notches shall be 3/4 in. (19 mm). The moldings for corners on handrails and handrail posts shall be 1/2 in. (13 mm). All moldings shall be cut with true edges, surfaced on all sides, and not warped, cracked, or frayed. Forms shall be given a bevel or draft in case of all projections, such as girders and copings. Concrete Structures Art. 503.06 When directed by the Engineer, temporary openings shall be provided in the bottom of forms for cleaning out all extraneous material immediately prior to placing concrete. Tie rods, bolts and anchorages within the forms shall be constructed so as to permit their removal to a depth of at least 1 1/2 in. (40 mm) from the face without injury to the concrete. Wire ties, when used, shall be cut back at least 1/2 in. (13 mm) from the face of the concrete upon removal of the forms, except on surfaces not exposed to view, they may be cut flush. All fittings for metal ties shall be of such design that, upon their removal, the cavities which are left will be of the smallest practicable size. Prior to reinforcement bar placement, forms shall be coated with form oil. When the surfaces are not exposed to view, wood forms may be saturated with water, in lieu of form oil, immediately prior to placement of the concrete. Forms shall remain in place until permission is obtained from the Engineer for their removal. For Class SI concrete substructure components that will be self- supporting after the forms are removed, and for Class BS concrete components, except those defined in Article 503.16(b), the forms shall remain in place until the concrete has attained the required flexural strength and the curing period is completed. For the remainder of cast-in-place concrete components the forms shall remain in place at least 24 hours. Superimposed loads, either dead or live, shall not be applied to a concrete component during the period the forms are required to remain in place, and until the component has attained sufficient strength to support subsequent loads. In the absence of tests to determine the flexural strength, the forms shall remain in place until at least 14 days have elapsed after placing the concrete, exclusive of days the temperature falls below 45 °F (7 °C). When either fly ash or ground granulated blast-furnace slag has been used in the concrete mixture, forms shall remain in place a minimum of 28 days from the time of concrete placement in the absence of strength tests. A compressive strength established through field testing to be equivalent to the required flexural strength may be used if approved by the Engineer. The method of form removal shall not result in damage to the concrete. If forms are removed prior to the completion of the required curing period, curing shall be resumed with an approved curing method for the remainder of the curing period. Additional requirements for form liners and bridge deck forms shall be as follows.
503.07 Placing and Consolidating. No concrete shall be placed on ice,
snow, or frozen foundation material. The method and manner of placing concrete shall be such as to avoid segregation or separation of the aggregates or the displacement of the reinforcement. The external surface of all concrete shall be thoroughly worked during the operations of placing in such a manner as to work the mortar against the forms to produce a smooth finish free of honeycomb and with a minimum of water and air pockets. Open troughs and chutes shall extend as nearly as practicable to the point of deposit. Dropping the concrete a distance of more than 5 ft (1.5 m) or depositing a large quantity at any point and running or working it along the forms will not be permitted. The concrete for walls with an average thickness of 12 in. (300 mm) or less shall be placed with tubes so that the drop is not greater than 5 ft (1.5 m). For self-consolidating concrete, the maximum distance of horizontal flow from the point of deposit shall be 15 ft (4.6 m). The distance may be increased if the dynamic segregation index (DSI) at the maximum flow distance is 10.0 percent or less according to ITP SCC-8 (Option C). The maximum distance using the DSI shall be 25 ft (7.6 m). In addition, this specified horizontal flow distance shall apply to precast products. In the case of precast prestressed concrete products, refer to the Department’s “Manual of Fabrication for Precast Prestressed Concrete Products” for the specified horizontal flow distance requirements. When the form height for placing the self-consolidating concrete is greater than 10 ft (3.0 m), direct monitoring of form pressure shall be performed by the Contractor according to ITP SCC-10. The monitoring requirement is a minimum, and the Contractor shall remain responsible for adequate design of the falsework and forms. The Contractor shall record the formwork pressure during concrete placement. This information shall be used by the Contractor to prevent the placement rate from exceeding the maximum formwork pressure allowed, to monitor the thixotropic change in the concrete during the pour, and to make appropriate adjustments to the mix design. This information shall be provided to the Engineer during the pour. When concrete is pumped, the equipment shall be suitable in kind and adequate in capacity for the work and arranged so that vibrations will not damage freshly placed concrete. Aluminum pipe or conduit will not be permitted in pumping or placing concrete. Mixed concrete shall be supplied to maintain continuous operation of the pumping equipment. Art. 503.07 Concrete Structures When air entrained concrete is pumped, an accessory or accessories shall be incorporated in the discharge components to minimize air loss. The maximum allowable air loss caused by the pumping operation shall be 3.0 percent with the minimum air content at the point of discharge meeting the requirements of
Article 1020 — 04.
Placing of concrete shall be regulated so that the pressures caused by the concrete shall not exceed those used in the design of the forms. Special care shall be taken to fill each part of the forms by depositing the concrete as near its final position as possible, to work the coarser aggregates back from the face, and to force the concrete under and around the reinforcement bars without displacing them. Leakage through forms onto beams or girders shall not be allowed to harden and shall be removed while in a plastic state. The concrete shall be consolidated by internal vibration unless self-consolidating concrete is used. Self-consolidating concrete may be used for inaccessible locations where consolidation by internal vibration is not practicable. The self-consolidating concrete shall be rodded with a piece of lumber, conduit, or vibrator if the material has lost its fluidity prior to placement of additional concrete. The vibrator will only be permitted if it can be used in a manner that does not cause segregation as determined by the Engineer. Any other method for restoring the fluidity of the concrete shall be approved by the Engineer. The Contractor shall provide and use a sufficient number of vibrators to ensure that consolidation can be started immediately after the concrete has been deposited in the forms. The vibrators shall be inserted into the concrete immediately after it is deposited and shall be moved throughout the mass so as to thoroughly work the concrete around the reinforcement, embedded fixtures, and into the corners and angles of the forms. Vibrators shall not be attached to the forms, reinforcement bars, or the surface of the concrete. Application of vibrators shall be at points uniformly spaced and not farther apart than 1 1/2 times the radius over which the vibration is visibly effective. The vibrator shall penetrate through each successive layer and into the preceding layer sufficiently to uniformly blend the two layers together. The duration of the vibration at the points of insertion shall be sufficient to thoroughly consolidate the concrete into place but shall not be continued so as to cause segregation. When consolidating concrete in bridge decks and approach slabs, the vibrator shall be vertically inserted into the concrete for 3 - 5 seconds or for a period of time determined by the Engineer. Vibration shall be supplemented by spading when required by the Engineer. Concrete shall be placed in continuous horizontal layers and up to a maximum depth of 20 in. (0.5 m). When it is necessary by reason of an emergency to place less than a complete horizontal layer in one operation, such layer shall terminate in a vertical bulkhead. Separate batches shall follow each other closely and in no case shall the interval of time between the placing of successive batches be greater than 20 minutes. Concrete Structures Art. 503.09 If mix foaming or detrimental material is observed during placement or at the completion of a pour, the material shall be removed while the concrete is still plastic. After the concrete has taken its initial set, care shall be exercised to avoid jarring the forms or placing any strain on the ends of projecting reinforcement.
503.08 Depositing Concrete Underwater. Concrete shall not be exposed to
the action of water before setting, or deposited in water, except with the approval of the Engineer and under his/her immediate supervision. When concrete is deposited underwater, it shall be carefully placed in its final position by means of a tremie or concrete pump and shall not be disturbed after being deposited. Still water shall be maintained at the point of deposit and all form work designed to retain concrete underwater shall be watertight. The consistency of the concrete shall be carefully regulated and segregation of the materials shall be prevented. When the tremie or concrete pump line is pre-lubricated with a cement/water mixture, the excess material shall be wasted. The discharge end of the tremie or concrete pump line shall be sealed prior to starting concrete placement according to Article 1103.18. The steel pipe shall be lowered to the bottom of the excavation and filled with concrete. The steel pipe shall be lifted slightly to allow the concrete to flow out of the steel pipe and embed the discharge end in concrete. The discharge end of the steel pipe shall remain embedded in the concrete throughout concrete placement. If, at any time the discharge end is not embedded in the concrete during placement, work shall be stopped and the steel pipe brought to the surface. The steel pipe shall be resealed according to Article 1103.18 and the process restarted. All vertical movements of the steel pipe shall be done in a manner to prevent a loss of concrete embedment. Concrete placement shall be continuous. If concrete placement is interrupted for longer than 30 minutes and resistance to flow is anticipated, the steel pipe shall be brought to the surface, the discharge end resealed according to Article 1103.18, and the process restarted. Horizontal distribution shall be accomplished by halting placement, raising the steel pipe to the surface, then horizontally moving the steel pipe to its new location, reestablishing the seal according to Article 1103.18, and the process restarted. Horizontal distribution may also be accomplished by simultaneously using multiple tremie pipes. The maximum distance between tremie insertions or tremie spacings shall be limited to three times the depth of the pour. The concrete shall not be vibrated when placed underwater, and the method of depositing the concrete shall produce approximately horizontal layers.
503.09 Construction Joints. Construction joints shall be made only at
locations shown on the plans or approved by the Engineer, except in cases of breakdowns or other unforeseen and unavoidable delays. All construction joints shall be bonded unless noted otherwise. When not shown on the plans, their location shall be confined, as far as possible, to regions of low Art. 503.09 Concrete Structures shearing stress and to locations that will be hidden from view. When possible, the location of construction joints shall be planned in advance and the concrete placed continuously from joint to joint. The reinforcing steel shall extend through such joints. If a construction joint is necessary in the sloped portion of a wingwall or similar location where a featheredge would result, the joint shall be constructed so as to produce an edge thickness of not less than 6 in. (150 mm) in the succeeding layer. No construction joint shall be placed within 18 in. (450 mm) of the top of any wall or pier unless the details of the work provide for a coping having a thickness of less than 18 in. (450 mm), in which case, at the option of the Engineer, a construction joint may be made at the underside of the coping. The face edges of all joints which are exposed to view shall be carefully finished true to line and elevation. Shear keys, formed into or out from the surface of the previously placed concrete or steel dowels, shall be used where required. Shear keys formed into the concrete shall be formed by the insertion and subsequent removal of beveled wood strips which shall be thoroughly saturated with water prior to insertion. Steel dowels may, at the discretion of the Engineer, be used in lieu of keys. The size and spacing of the keys and dowels will be as determined by the Engineer. Between adjacent sections of retaining walls and abutment walls, a V-shaped groove shall be formed in the exposed face of the walls by the use of 1/2 in. (13 mm) triangular molding on each side of the joint. Care shall be exercised not to injure the concrete or break the concrete-steel bond at any time. In constructing bridge decks and approach slabs where longitudinal joints are specified, a platform shall be constructed outside the longitudinal joints and supported on the lower form, and personnel will not be permitted to stand or walk on the projecting reinforcement bars until the concrete has hardened. The Contractor, subject to approval of the Engineer, may pour a bridge deck full width with horizontal bonded construction joints between the deck and curbs, parapets, or sidewalks.
503.10 Expansion Joints. Expansion joints shall be constructed to permit
freedom of movement. After all other work is completed, all thin shells of mortar and projections of the concrete into and around the joint space that are likely to spall under movement or prevent the proper operation of the joint shall be carefully removed. Expansion joint devices shall be furnished and installed according to Section 520.
503.11 Drainage Openings. When specified, drain holes shall be
constructed in abutment walls, wingwalls, retaining walls, and culvert sidewalls. The locations of drains on all concrete superstructures shall be adjusted so as to prevent the discharge of drainage water against any portion of the structure, or directly onto any railroad, highway or unprotected embankment beneath the structure. Drains consisting only of openings formed in the deck and curbs shall be provided with a surrounding drip notch in the bottom surface of the slab. Deck drains shall be placed and securely fastened in position before the concrete is placed.
503.12 Nonmetallic Water Seals. Nonmetallic water seals shall be installed
as shown on the plans. Provisions shall be made to adequately support the water seal during construction. The projecting edges and ends of partially embedded water seals shall be protected from damage. Art. 503.13 Concrete Structures When splices are required, they shall be made by heating or vulcanizing to form continuous watertight joints. For the polyvinylchloride water seal, the heat shall be sufficient to melt but not char the plastic.
503.13 Foundations and Footings. When concrete footings are constructed
in excavation other than rock, forms shall be used for all vertical surfaces, except when the excavation can be made and will remain true to the required lines and grades until the concrete is placed in the excavated space. When forms are omitted, the entire excavated space shall be filled with concrete to the elevation of the top of the footing. When concrete footings are constructed in rock, if the forms are omitted, the entire space shall be filled with concrete up to the top of the footing, or to the top of the rock if the latter is lower. In all cases, where sumps are required for the disposal of water, they shall be constructed outside the footing areas and forms shall be used for the footings at each sump. The concrete footing for each substructure unit shall be placed monolithically, except when joints are specified. Vertical construction and expansion joints shown on the plans in abutments and wing walls shall not extend through the footing. In retaining walls or other structures, where joints extend through the footing, the water seal required in the joints between adjacent sections of wall need not extend below the top of the footing. When concrete encasement is specified, this work shall include the furnishing and placing of the reinforcement required for encasement and any excavation necessary to construct it.
503.14 Seal Coats in Cofferdams. When conditions are encountered which
render it impractical to dewater a cofferdam before placing concrete, the Contractor will be permitted to construct a concrete seal coat. Seal coats will not be authorized, except where properly constructed cofferdams cannot be dewatered satisfactorily by ordinary means. The seal coat shall be constructed below the elevation of the footing and will not be considered a part of the footing. Seal coats shall be designed to withstand the hydrostatic pressure taking into account the resistance afforded by the cofferdam and foundation piles or drilled shafts. Seal coats shall be constructed of Class SC concrete. When seal coat concrete is required underwater it shall be placed according to
Article 503 — 08.
503.15 Surface Finish. Depressions resulting from the removal of ties, and
holes left by attachments to rod or bolt anchorages, shall be neatly pointed with a grout mixed in the proportions of, and color matched to, the concrete being treated. Air pockets or rough places larger than 1/2 in. (13 mm) diameter shall be pointed as specified in the foregoing paragraph. Honeycombed areas shall be chipped out by the Contractor and inspected by the Engineer before being pointed. Concrete Structures Art. 503.15 After being pointed, form liners and all other surfaces that will be exposed to view after completion of the work, except those surfaces specified in Articles 503.16(a) and (b)(1), shall be given a normal finish.
503.16 Concrete Superstructures. The concrete in bridge decks, approach
slabs, or other monolithic superstructures shall be placed in one continuous operation between expansion or construction joints specified. Sidewalks, curbs, and medians shall be placed monolithically with the superstructure unless a construction joint is specified. When falsework is utilized to support steel or precast concrete beams during erection, the falsework shall be removed prior to pouring the deck. The concrete bridge deck or top riding surface of the superstructure shall be constructed so that the top of the finished surface shall be at the final plan elevation after taking into account any anticipated deflection of the supporting members due to the weight of the deck, median, and parapets. Fogging equipment shall be in operation unless the evaporation rate is less than 0.1 lb/sq ft/hour (0.5kg/sq m/hour) and the Engineer gives permission to stop. The evaporation rate shall be determined according to the following formula. ) ( 10 ) 4 . 0 1 )(( 65 . 2 5 . 2 Englishx VrT T Eac ) ( 10 ) 4 ]( ) 18 ( ) 18 [( 565 . 25 . 2 Metricx VT rT E ac Where: E = Evaporation Rate, lb/sq ft/h (kg/sq m/h) cT = Concrete Temperature, °F (°C) aT = Air Temperature, °F (°C) r = Relative Humidity in percent/100 V = Wind Velocity, mph (km/h) The Contractor shall provide temperature, relative humidity, and wind speed measuring equipment. Fogging equipment shall be adequate to reach or cover the entire pour from behind the finishing machine or vibrating screed to the point of curing covering application, and shall be operated in a manner which shall not accumulate water on the deck until the curing covering has been placed. If there is a delay of more than ten minutes during concrete placement, wet burlap shall be used to protect the concrete until operations resume. Concrete placement operations shall be coordinated to limit the distance between the point of concrete placement and concrete covered with curing material. The distance shall not exceed 35 ft (10.7 m). For pour widths greater than 50 ft (15 m), the distance shall not exceed 25 ft (7.6 m).
Article 424 — 06, except the surface shall not be divided by grooves.
503.17 Curing. Concrete shall be cured according to Article 1020.13.
503.18 Waterproofing. The surfaces of concrete structures designated on
the plans shall be waterproofed as follows.
Article 502 — 10 are met.
503.19 Protective Coat Application. A protective coat shall be applied to the
entire top surface of bridge decks, approach slabs, hubguards, and the top and inside vertical faces of sidewalk, parapets, end posts, and wings when the concrete is at least 14 days old. This work shall be performed after saw cut grooving, and before the bridge is marked and opened to traffic. Before the protective coat is applied, the concrete surface shall have at least a 48-hour drying period since the last rain and shall be cleaned to remove all oil, grime, and loose particles which would prevent the mixture from penetrating the concrete. Immediately prior to application of the protective coat, the surface shall be blown with oil-free compressed air. After the surface is clean and before applying protective coat, relief joints being sealed according to Section 588 shall be covered with a masking tape to prevent protective coat from contacting the vertical faces of the joint. The protective coat shall consist of two applications of the mixture and each application shall be at a rate of 50 sq yd/gal (11 sq m/L) or less. The protective coat shall be sprayed on the surface using hand methods or with a mechanical spraying machine which will perform the work in a satisfactory manner. The spray nozzle(s) shall be within 18 in. (450 mm) of the concrete or as directed by the Engineer. The interior of the distributor tank shall be thoroughly cleaned prior to placing the protective coat therein. Unless otherwise directed by the Engineer, the Concrete Structures Art. 503.21 temperature of the concrete and air shall be 40 °F (4 °C) or higher at the time of application. The second application of the protective coat shall be made when, in the opinion of the Engineer, the concrete has regained its dry appearance. Traffic shall be prohibited from the area until the concrete has regained its dry appearance. If an application of sand is required by the Engineer for blotter material, it will be paid for according to Article 109.04.
503.20 Opening Structures to Traffic. Concrete structures shall be opened
to traffic according to Articles 503.05, 503.06, and 1020.13.
503.21 Method of Measurement. This work will be measured for payment as
follows.
Article 508 — 10.
Bridge deck grooving will be measured for payment in place and the area computed in square yards (square meters). No deductions will be made for grooving omissions at deck drains, expansion joints, longitudinal joints, or lane lines. Art. 503.21 Concrete Structures Protective coat will be measured for payment in place and the area computed in square yards (square meters). Form liner textured surfaces will be measured for payment in place and the area computed in square feet (square meters). Joint fillers, water seals, drain holes, floor drains and welded wire reinforcement, except when specified, will not be measured for payment. Rubbed finish will be measured for payment in place and the area computed in square feet (square meters).
503.22 Basis of Payment. This work will be paid for at the contract unit price
per cubic yard (cubic meter) for CONCRETE STRUCTURES, CONCRETE SUPERSTRUCTURE, and CONCRETE SUPERSTRUCTURE (APPROACH SLAB). Other cast-in-place concrete for structures will be paid for at the contract unit price per cubic yard (cubic meter) for CONCRETE HANDRAIL, CONCRETE ENCASEMENT, and SEAL COAT CONCRETE. Reinforcement bars will be paid for according to Article 508.11. Expansion bolts, when specified, will be paid for according to Article 540.08. Rubbed finish will be paid for at the contract unit price per square foot (square meter) for RUBBED FINISH. Form liner textured surfaces will be paid for at the contract unit price per square foot (square meter) for FORM LINER TEXTURED SURFACE. Floor drains, other than frames and grates, will be paid for at the contract unit price per each for FLOOR DRAINS. Texturing of bridge decks and approach slabs by saw cut grooving will be paid for at the contract unit price per square yard (square meter) for BRIDGE DECK GROOVING. Protective coat will be paid for at the contract unit price per square yard (square meter) for PROTECTIVE COAT. Concrete protected according to Article 1020.13(d) may be paid for at the adjusted unit prices which will be the following percentages of the contract unit price for the classes of concrete involved. These adjustments will be made only when they are authorized in writing by the Engineer. No adjustment will be made in the contract unit prices for any concrete if winter work is necessary to meet the required completion dates specified in the contract. Precast Concrete Structures Art. 504.02 UNIT PRICE ADJUSTMENTS Percent Type of Construction Adjustment in Unit Price For concrete in substructures, culverts (having a waterway opening of more than 10 sq ft (1 sq m)), pump houses, and retaining walls (except concrete pilings, footings, and seal coats): When protected by: Protection Method II 115 % Protection Method I 110 % For concrete in superstructure (approach slab): When protected by Method I or II 107 % For concrete in superstructures: When protected by: Protection Method II 123 % Protection Method I 115 % For concrete in footings: When protected by Method I or II 107 % For concrete in slope walls: When protected by Method I 107 % SECTION 504. PRECAST CONCRETE STRUCTURES
504.01 Description. This work shall consist of the construction of structures
or portions thereof, with precast concrete or precast, prestressed concrete structural members.
504.02 Materials. Materials shall be according to the following.
Item Article/Section
CONCRETE STRUCTURES in other states