582HOT-MIX ASPHALT SURFACING ON BRIDGE DECKS

IL · 2022 Standard Specifications✓ Full text on BuildSpecBook pages 530–531 Save this section

Ask about Section 582

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Hot-Mix Asphalt Surfacing On Bridge Decks Art. 582.05

b.Measured Quantities. This work will be measured for payment and the area computed in square yards (square meters) of bridge deck surface covered. No measurement or allowance will be made for laps, material used for extending up curb faces or other vertical barriers, material used for extensions over lips or edges, or for repairs.

581.10 Basis of Payment. This work will be paid for at the contract unit price

per square yard (square meter) for WATERPROOFING MEMBRANE SYSTEM. SECTION 582. HOT-MIX ASPHALT SURFACING ON BRIDGE DECKS

582.01 Description. This work shall consist of constructing a hot-mix asphalt

(HMA) surface course on a prepared bridge deck.

582.02 Materials. Materials shall be according to Article 406.02.

582.03 Equipment. Equipment shall be according to Article 406.03, except

vibratory rollers will not be permitted on bridge decks. CONSTRUCTION REQUIREMENTS

582.04 General. Work shall be according to Section 406, except as specified

herein. Only a tandem roller, meeting the requirements of Table 1 of Article 406.07(a), will be permitted for breakdown rolling.

582.05 Target Density. A target density will be established from tests

conducted on a calibration strip consisting of 100 ft (30 m) of HMA surface course placed on the bridge deck. A target count rate which represents the maximum compactive effort will be determined with nuclear testing equipment within the calibration strip. Compaction of the calibration strip with the breakdown roller shall commence immediately after the surface course is placed and shall be continuous and uniform over the entire area. All rolling operations must be completed before the temperature of the mixture drops below 190 °F (90 °C). At a minimum of two random locations within the calibration strip, a growth curve consisting of a plot of counts per minute vs. number of passes with a breakdown roller will be developed. The growth curve at each random location will be established by using a nuclear gauge using a fast count or with a nuclear gauge using a 30-second timing cycle in the backscatter position. Tests will be made after each pass until the lowest count either raises or remains the same. At this time, mineral filler will be spread and a 4 minute (calibration) count will be taken in the backscatter position to establish the relative target density. Art. 582.06 Portland Cement Mortar Fairing Course The established average target density shall apply throughout the project unless there are changes in mix materials or an appreciable change in the job mix formula. The Engineer may require a new average target density to be established if there is reason to believe that the mixture being placed is not the same as the mixture used to determine the target density.

582.06 Acceptance Tests. Acceptance tests will be performed once the

average target density has been established. At least one acceptance test will be taken for each 200 ft (60 m) or portion thereof of bridge deck per paver pass. Acceptance tests on material placed in a single day shall average 98 percent of the established average target density with no one test being below 95 nor more than 103 percent of the established target density. If the above requirements for average or individual density tests cannot be obtained, placement of additional material will be discontinued until the cause of the failure is investigated and corrected. Acceptance tests will be performed with the same nuclear equipment used to establish the average target density. Acceptance tests will be for one-minute duration and the area to be tested shall be prepared with mineral filler prior to testing.

582.07 Method of Measurement. This work will be measured for payment

according to Article 406.13.

582.08 Basis of Payment. This work will be paid for according to

Article 406 — 14.

SECTION 583. PORTLAND CEMENT MORTAR FAIRING COURSE

583.01 Description. This work shall consist of placing portland cement

mortar along precast, prestressed concrete bridge deck beams as required for fairing out any unevenness between adjacent deck beams prior to placing of waterproofing membrane and surfacing.

583.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Portland Cement ............................................................................ 1001.01(a)
b.Fine Aggregate .................................................................................. 1003.02
c.Water ...................................................................................................... 1002 CONSTRUCTION REQUIREMENTS

583.03 General. This work shall only be performed when the air temperature

is 45 °F (7 °C) and rising. The mixture for portland cement mortar shall consist of three parts sand to one part portland cement by volume. The amount of water shall be no more than that necessary to produce a workable, plastic mortar. Prior to placement of the mortar fairing course, all areas where unevenness occurs between the deck beams shall be prepared according to Article 503.09(b).

Get an email when 582 changes

Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 530–531 of 1,217. View official source ↗

Ask about this section

Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 582 — HOT-MIX ASPHALT SURFACING ON BRIDGE DECKS. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.