Master Controller Art. 860.04 SECTION 859. TRANSCEIVER

859.01 Description. This work shall consist of furnishing and installing a

transceiver with necessary connections for proper operation.

859.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Transceiver ........................................................................................ 1073.03 CONSTRUCTION REQUIREMENTS

859.03 Installation. The transceiver shall be connected to the communication

interface panel. The transceiver shall be assigned a unique address in the master controller.

859.04 Basis of Payment. This work will be paid for at the contract unit price

per each for TRANSCEIVER. The interface panel, all necessary harnesses, and the programming of the controller and the master controller shall be included in this item. SECTION 860. MASTER CONTROLLER

860.01 Description. This work shall consist of furnishing and installing a

master controller with the necessary connections for proper operation.

860.02 Materials. Materials shall be according to the following.

Item Article/Section

a.Master Controller ............................................................................... 1073.04 CONSTRUCTION REQUIREMENTS

860.03 Installation. Installation of the master controller shall be as follows.

a.Communication. The contractor shall install communication hardware and software as shown in the plans. Initial communication setup charges will be paid for according to Article 109.05.
b.Housing and Cabinet. The model and serial numbers shall be affixed on the front of the housing and shall be readily visible. One circuit breaker rated at 10 A shall be provided.
c.Software. Software shall be provided and distributed as shown on the plans.

860.04 Basis of Payment. This work will be paid for at the contract unit price

per each for MASTER CONTROLLER.

Get an email when 859 changes

Illinois revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Illinois Standard Specifications for Road and Bridge Construction, 2022 Edition. Pages 740–740 of 1,217. View official source ↗

Ask about this section

Scoped to Illinois Standard Specifications for Road and Bridge Construction, Section 859 — TRANSCEIVER. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.