B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Landscaping & Erosion (900+)

966All necessary equipment and personnel shall be provided to ensure the tests are

IN · 2024 Standard SpecificationsBook pages 989990View official source ↗

966 All necessary equipment and personnel shall be provided to ensure the tests are safely conducted. The Electronics Technician shall be present to witness the tests. A cabinet shall pass every test to be accepted. If the cabinet fails, the problem shall be corrected and a new test shall be arranged. The technician shall be given at least 36 h advance notice of the test.

809.07 Clean-Up

When the installation is completed, all disturbed portions of the construction area 80 shall be cleaned and all excess excavation or other materials shall be disposed of in accordance with 104.05 and 203.10. The site shal l be restored to its original condition.

809.08 Method of Measurement

ITS controller cabinet foundations will be measured per each installed, complete and in place. ITS controller cabinets will be measured by the number of units installed, complete and in place. 809.09 Basis of Payment ITS controller cabinet foundations will be paid for at the contract price per each. 90 ITS controller cabinets, complete, in place, will be paid for at the contract unit price per each. Payment will be made under: Pay Item Pay Unit Symbol ITS Controller Cabinet Foundation ........................................... EACH ITS Controller Cabinet .............................................................. EACH The cost of all cabinet accessories, mounting hardware, anchor bolts, handles, setup and wiring shall be included in the cost of the ITS controller cabinet. The cost of all grading necessary for installation of the foundations and the final clean-up of the area shall be included in the cost of the ITS controller cabinet foundation. The cost of padlocks shall be included in the cost of the ITS controller cabinet. 809.07 967 DIVISION 900 – MATERIALS DETAILS