Landscaping & Erosion (900+)

991Characteristics/Grades UA-I UA-II UA-III

IN · 2024 Standard SpecificationsBook pages 10091014View official source ↗

Softening Point (Ring & Ball), °C 46 - 63 63 - 85 79.5 - 96 Penetration of Original Samples(1) (0.1 mm) at 4°C, 200 g, 60 s, min…… at 25°C, 100 g, 5 s………… at 46°C, 50 g, 5 s…………. 50 - 100 100 min. 25 - 45 130 max. 15 - 35 90 max. Ductility @ 25°C, 50 mm/min, 10 mm, min.(1) 30 10 2.5 Solubility in Organic Solvents, % min.(1) 99.0 99.0 99.0 Flash Point (Cleveland Open Cup), °C, min.(1) 225 225 225 Penetration of Residue from Thin Film Oven Test, 25°C, 100 g, 5 s, (0.1 mm) min.(1) 30 15 10

(1)Test will be performed when complete physical characteristics are needed or desired.

A Type A certification in accordance with 916 shall be provided for utility asphalt. 110 The results of the above shall be shown on the certification. (e) Asphalt for Coating Corrugated Metal Pipe Asphalt for coating corrugated metal pipe shall be in accordance with the following:

Physical Properties Min. Max. Softening Point (Ring & Ball), °C 93 110 Penetration of Original Samples (0.1 mm) at 4°C, 200 g, 60 s………… at 25°C, 100 g, 5 s………… (1)

Solubility in Organic Solvents, % 99.0 Flash Point (Cleveland Open Cup), °C 232 Flow Test, mm 6.4 Shock Test 3 of 4 specimens shall pass

(1)May be 30 minimum provided all four shock tests pecimens pass.

A Type A certification in accordance with 916 shall be provided for asphalt coating to the pipe fabricator on corrugated metal pipe. The results of the above shall be shown on the certification. 120

902.02Sampling and Testing Asphalt Materials

The tests and AASHTO references are as follows:

(a)Sampling Bituminous Materials ........................... AASHTO R 66

The following exceptions to AASHTO R 66 shall apply:

1.Samples may be obtained at any time before material is

incorporated into the work. 130 902.02

992 2. Samples for all grades of asphalt emulsion shall be a minimum of 1/2 gal. The size of samples of other liquid material may be 1 qt.

3.Samples of liquid materials shall be obtained at one of the

following:

a.bulk storage tanks from sampling valves located in the

tank or line and asphalt plant storage tanks from 140 sampling valves located in the tank,

b.transports from sampling valves,
c.distributors from valves, d. other storage or locations as approved, e. sampling by other recognized devices may be

approved, and

f.sampling valves beyond the in-line blending location. (b) Water in petroleum products, except the solvent or carrier may be toluene ...................................... ASTM D95 150
(c)Density, Specific Gravity, or API Gravity of

Crude Petroleum and Liquid Products by Hydrometer Method ............................................. ASTM D1298 (d) Specific Gravity of Semi-Solid Bituminous Materials ............................................................... AASHTO T 228

(e)Specific Gravity of Solid Pitch and Asphalt ......... ASTM D71

160

(f)Flash Point (Open Cup)
1.When the flash point is higher than 175°F,

“Flash Point by Cleveland Open Cup” ....... AASHTO T 48 2. When the flash point is 175°F or lower, “Flash Point with Tag Open Cup” .............. AASHTO T 79

(g)Softening Point of Bituminous Materials,

Ring and Ball ........................................................ AASHTO T 53 170

(h)Penetration of Bitumi nous Materials .................... AASHTO T 49
(i)Loss of Heating ..................................................... ASTM D6
(j)Solubility in Organic Solvents, except the

solvent may be 1,1,1,-Trichloroethane ................. AASHTO T 44 902.02

993

(k)Inorganic Matter or Ash ....................................... AASHTO T 59

180

(l)Saybolt-Furol Viscosity ........................................ AASHTO T 72
(m)Ductility of Binder Material, except that the conditioning period of

the specimens may be shortened, and that only one normal test will be required. Shortened conditioning period: The specimen shall be allowed to cool in air for at least 30 minutes. It shall then be trimmed and placed in the water bath for a period of 60 to 90 minutes before testing. In case of failure or dispute, three normal tests will be required and specimens shall be conditioned as in AASHTO T 51. 190

(n)Float Test for Bitu minous Materials ..................... AASHTO T 50

( o ) .LQHPDWLF9LVFRVLW\RI$VSKDOWV .......................... AASHTO T 201

(p)Absolute Viscosity of Asphalts ............................ AASHTO T 202
(q)Effect of Heat and Air on Asphalt Materials,

Thin-Film Oven Test ............................................ AASHTO T 179

(r)Effect of Heat and Air on a Moving Film of 200

Asphalt, Rolling Thin Film Oven Test ................. AASHTO T 240

(s)Testing Asphalt Emulsions ................................... AASHTO T 59

The following exceptions to AASHTO T 59 shall apply:

1.For the Residue by Distillation test, the specified aluminum

alloy still shall be the referee still.

2.When tests on the residue are not required, the % of residue for 210

emulsion grades RS-2 and AE-90 only, may be determined by the Residue by Evaporation test of AASHTO T 59. The % of residue shall be determined by the Residue of Distillation test in all cases of failure or dispute.

3.The stone coating test shall be performed as follows on a

mixture of 465 ±1 g of reference stone and 35.0 ±0.1 g of asphalt emulsion:

a.For AE-90 the mixture of stone and asphalt shall be mixed 220

vigorously for 5 minutes. At the end of the mixing period, the mix shall be rinsed by running sufficient tap water at the side of the container to completely immerse the mix. The 902.02

994 tap water shall then be poured off and the rinsing step repeated as necessary until the rinse water pours off essentially clear. The stone sh all remain a minimum of 90% coated.

b.For AE-150 the mixture of stone and asphalt shall be mixed

vigorously for 5 minutes and then allowed to stand for 3 h. 230 At the end of this time, the mixture shall again be mixed vigorously for 5 minutes. At the end of the second mixing period, the mix shall be rinsed by running sufficient tap water at the side of the container to completely immerse the mix. The tap water shall then be poured off and the rinsing step repeated as necessary until the rinse water pours off essentially clear. The stone sh all remain a minimum of 90% coated.

4.For the Demulsibility test, normally only one test will be 240

required. In case of failure or dispute, the specified procedure in AASHTO T 59 will be followed.

5.For oil portion from Residue by Distillation, report the number

of milliliters of oil per 100 g of emulsion.

(t)Stripping tests for HMA mixtures using binder materials, with or

without additives, shall be performed as follows:

1.Test 1. A sample of produced mixture, 500 g, minimum, shall 250

be obtained for testing. The size of test specimen and the amount of distilled water shall be:

Approximate Size of Aggregate Minimum Weight of Test Specimen Amount of Distilled Water Sand 100 g 400 mL 12 100 g 400 mL 11 150 g 600 mL 9 200 g 600 mL

Place the specimen in the boiling distilled water and stir with a glass rod at the rate of one revolution per second for 3 minutes. The aggregate shall retain a mini mum of 90% of its asphalt film compared with the remainder of the sample, upon completion of this procedure. 260 2 . Test 2 . Approximately 500 g of produced mixture shall be heated to 250°F in a laboratory oven for 2 h, stirred, and cooled to 200°F. A portion of the mix shall then be placed in boiling 902.02

995 distilled water, quantity of mix and quantity of boiling water shall be as specified in Test 1, and stirred with a glass rod at the rate of one revolution per second for 3 minutes. The aggregate shall retain a minimum of 90% of its asphalt film compared with the remainder of the sample, upon completion of this procedure. 270 Note: The purpose of these tests is to determine the relative compatibility of the aggregate and asphalt, and to detect tendency of Asphalt Emulsions to re-emulsify. If Test 1 returns unsatisfactory results, Test 2 may be performed as a method of determining whether compatibility can be achieved.

(u)Penetrating Ability of AE-PL.
1.Apparatus and Equipment: 280
a.Sand mixture:
(1)Dry Ottawa Sand (AASHTO T 106) ............ 90 parts
(2)Dry Reference Limestone Dust, portion

passing No. 50 (300 mm) sieve only. Reference Limestone Dust used by the Department is Limestone Calcium Carbonate manufactured by France 290 Stone Co. The Department will furnish approximately 5 lb of Reference Limestone Dust upon request .................... 10 parts

(3)Water ............................................................ 3 parts
b.Container, 6 oz ointment tin. c. Ruler or other measuring device.

300

d.Timing device readable in seconds.
e.Compacting Device. Rimac Spring Tester or other device

suitable for compacting sand by applying a 20 psi load. The compacting device shall include an adapter consisting of two metal discs slightly smaller in diameter than a 6 oz ointment tin separated by a spacer 1 to 2 in. The 2.54 in. diameter discs used in determining weight of coating in AASHTO T 65 or ASTM A90 are satisfactory. 902.02

996 310

f.Small, square ended spatula or putty knife.
2.Procedure:

Thoroughly mix Standard Ottawa Sand, Reference Limestone Dust, and water. Weigh 190 ±1 g of sand mixture into a 6 oz ointment tin. Level surface of sa nd with a spatula. Place the compacting adapter on the sand surface and slowly, over a period of about 5 s, compact the sand until the 20 psi load is achieved, which is approximately 100 lb on the Rimac Spring Tester. Remove the compacting device, avoiding disturbance to 320 the sand surface. Quickly pour 12 g of the emulsion from a height of about 4 in. onto top of sand mixture. Start timer at start of pour. Stop timer when all emulsion penetrates into sand mixture. Delay 2 minutes then remove sand and mixture from one side of ointment tin, about 1/2 of mixture. Measure to determine average depth of penetration into sand mixture. Penetration time shall be 100 s or less; penetration depth shall be 6.0 mm or more.

(v)Flow Test for Asphalt for Coating 330

Corrugated Metal Pipe .......................................... AASHTO M 190

(w)Shock Test for Asphalt for Coating

Corrugated Metal Pipe .......................................... AASHTO M 190

(x)Viscosity Determinations of Asphalt

Binder Using Rotational Viscometer .................... AASHTO T 316 (y) Determining the Rheological Properties of Asphalt Binder Using a Dynamic Shear 340 Rheometer............................................................. AASHTO T 315

(z)Accelerated Aging of Asphalt Binder

Using a Pressurized Aging Vessel ........................ AASHTO R 28

(aa)Determining the Flexural Creep Stiffness of

Asphalt Binder Using the Bending Beam Rheometer............................................................. AASHTO T 313 902.03 Application Temperatures 350 Binder materials for the several applications indicated in the specifications shall be applied at temperatures not to exceed those shown in the following: 902.03

997 Type and Grade of Material Application Temperature, °F, max. Spray Mix SC-800-3000, SCA-800-3000 .... All Penetration and Viscosity, 225 250 275 200 225 250 160

350 (see Note) 200 225 250

225 250 180

325 (see Note) Note: In accordance with manufacturer’s recommendations.

Source: Indiana Standard Specifications, 2024 Edition. Pages 10091014 of 1,248.