Instrumentation and Evaluation
829.01 DESCRIPTION . Furnish and install instrumentation, provide power and
backup power systems, access for installation and removal of instrumentation, and loadings for structural evaluation as specified. Also, provide instrumentation consultant engineering services when specified.
829.02 MATERIALS. Comply with the following sections and subsect ions.
Electrical Systems Secti on 822 Metals Section 1013 Carbon Steel Bolts, Nuts, and Washers 1013.08 High Strength Bolts, Nuts, Washers, and Direct Te nsion Indicators (DTIs) 1013.08 Provide mechanically g alvanize d bolts, nuts, washers , and DTIs in accordance with Section 811 . Provide stainless steel m achine screws and washers for fastening . Instrumentation shall be as shown on the plans or when specified, as designed by the contractor’s consultant .
829.03 Construction Requirements .
829.03.1 Submittals : When the Bridge Instrumentation and Evaluation Plan
is not provided, su bmit to the Bridge Engineer for review a “Bridge Instrumentation and Evaluation Plan” in accordance with 801.05 . Submit the plan no later than 30 calendar days pr ior to commencing the work. The engineer will evaluate the plan for conformance with the plans and specifications. Allow 21 calendar days for review. Resubmit any parts of the submittal returned for correction and allow an additional 14 calendar days fo r review of each resubmittal. No changes in the Bridge Instrumentation and Evaluation Plan shall be made after final acceptance without the concurrence of the engineer. Provide at least the following information in the Bridge Instrumentation and Evaluation Plan: • Name and address of supplier and manufacturer of component and associate information and cut sheet. Instrumentation and Evaluation
829.01 DESCRIPTION . Furnish and install instrumentation, provide power and
backup power systems, access for installation and removal of instrumentation, and loadings for structural evaluation as specified. Also, provide instrumentation consultant engineering services when specified.
829.02 MATERIALS. Comply with the following sections and subsect ions.
Electrical Systems Secti on 822 Metals Section 1013 Carbon Steel Bolts, Nuts, and Washers 1013.08 High Strength Bolts, Nuts, Washers, and Direct Te nsion Indicators (DTIs) 1013.08 Provide mechanically g alvanize d bolts, nuts, washers , and DTIs in accordance with Section 811 . Provide stainless steel m achine screws and washers for fastening . Instrumentation shall be as shown on the plans or when specified, as designed by the contractor’s consultant .
829.03 Construction Requirements .
829.03.1 Submittals : When the Bridge Instrumentation and Evaluation Plan
is not provided, su bmit to the Bridge Engineer for review a “Bridge Instrumentation and Evaluation Plan” in accordance with 801.05 . Submit the plan no later than 30 calendar days pr ior to commencing the work. The engineer will evaluate the plan for conformance with the plans and specifications. Allow 21 calendar days for review. Resubmit any parts of the submittal returned for correction and allow an additional 14 calendar days fo r review of each resubmittal. No changes in the Bridge Instrumentation and Evaluation Plan shall be made after final acceptance without the concurrence of the engineer. Provide at least the following information in the Bridge Instrumentation and Evaluation Plan: • Name and address of supplier and manufacturer of component and associate information and cut sheet. Instrumentation and Evaluation
829.01 DESCRIPTION . Furnish and install instrumentation, provide power and
backup power systems, access for installation and removal of instrumentation, and loadings for structural evaluation as specified. Also, provide instrumentation consultant engineering services when specified.
829.02 MATERIALS. Comply with the following sections and subsect ions.
Electrical Systems Secti on 822 Metals Section 1013 Carbon Steel Bolts, Nuts, and Washers 1013.08 High Strength Bolts, Nuts, Washers, and Direct Te nsion Indicators (DTIs) 1013.08 Provide mechanically g alvanize d bolts, nuts, washers , and DTIs in accordance with Section 811 . Provide stainless steel m achine screws and washers for fastening . Instrumentation shall be as shown on the plans or when specified, as designed by the contractor’s consultant .
829.03 Construction Requirements .
829.03.1 Submittals : When the Bridge Instrumentation and Evaluation Plan
is not provided, su bmit to the Bridge Engineer for review a “Bridge Instrumentation and Evaluation Plan” in accordance with 801.05 . Submit the plan no later than 30 calendar days pr ior to commencing the work. The engineer will evaluate the plan for conformance with the plans and specifications. Allow 21 calendar days for review. Resubmit any parts of the submittal returned for correction and allow an additional 14 calendar days fo r review of each resubmittal. No changes in the Bridge Instrumentation and Evaluation Plan shall be made after final acceptance without the concurrence of the engineer. Provide at least the following information in the Bridge Instrumentation and Evaluation Plan: • Name and address of supplier and manufacturer of component and associate information and cut sheet. Instrumentation and Evaluation
829.01 DESCRIPTION . Furnish and install instrumentation, provide power and
backup power systems, access for installation and removal of instrumentation, and loadings for structural evaluation as specified. Also, provide instrumentation consultant engineering services when specified.
829.02 MATERIALS. Comply with the following sections and subsect ions.
Electrical Systems Secti on 822 Metals Section 1013 Carbon Steel Bolts, Nuts, and Washers 1013.08 High Strength Bolts, Nuts, Washers, and Direct Te nsion Indicators (DTIs) 1013.08 Provide mechanically g alvanize d bolts, nuts, washers , and DTIs in accordance with Section 811 . Provide stainless steel m achine screws and washers for fastening . Instrumentation shall be as shown on the plans or when specified, as designed by the contractor’s consultant .
829.03 Construction Requirements .
829.03.1 Submittals : When the Bridge Instrumentation and Evaluation Plan
is not provided, su bmit to the Bridge Engineer for review a “Bridge Instrumentation and Evaluation Plan” in accordance with 801.05 . Submit the plan no later than 30 calendar days pr ior to commencing the work. The engineer will evaluate the plan for conformance with the plans and specifications. Allow 21 calendar days for review. Resubmit any parts of the submittal returned for correction and allow an additional 14 calendar days fo r review of each resubmittal. No changes in the Bridge Instrumentation and Evaluation Plan shall be made after final acceptance without the concurrence of the engineer. Provide at least the following information in the Bridge Instrumentation and Evaluation Plan: • Name and address of supplier and manufacturer of component and associate information and cut sheet. • Detailed drawings of placement of all sensors, method and sequence of sensor placement, and layout of wiring, conduit, and data collection system. • Details of the access system for attaching and removing instrumentation and associated equipment. • Schematic of data acquisition system. Plans for sampling frequency, data retrieval, and software to be used. Software setup including configuration of ports and flags, and IP addresses. • Instrumentation enclosure and breakaway mounting pole meeting NEMA 4X requirements. • Estimation of power consumption. Planned power and backup power system for a minimum of 7 days uptime. • Detailed plan for all test loading. • Traffic control for each operation associated with instrumentation and evaluation. • Other information shown in the plans or required by the engineer .
829.03.2 Instrumentation : Furnish instrumentation as shown on the plans.
Upon completion of instrumentation work, all instrumentation, power supply, data collection systems, data loggers, conduit and wiring, and data transmitters will become the property of the Department. Weather proof instrumentation with a rating of IP66 or higher for above water applications and a rating of IP68 for submerged applications. Shelter wiring and data collection systems from the weather.
829.03.3 Instrumentation Assistance : Provide access and assistance as
required for installation and removal of instrumentation, and access for data collecti on during the project.
829.03.4 Evaluation : Furnish test loading equipment, equipment operation,
and traffic control as required by the plans.
829.03.5 Instrumentation Services: When specified, provide consultant
services to design the Instrumentation and Evaluation Plan, install instrumentation in accordance with the plans, monitor instrumentation, and upon completion of the instrumentation and evaluation work, remove instrument ation not required for future use.
829.04 INSTRUMENTATION REMOVAL . Remove all sensors, data
acquisition systems along with all associated conduits, and instrumentation enclosure when shown on the plans. Deliver sensors and data acquisition systems to the engi neer after removal. Any unsalvageable materials shall become the • Detailed drawings of placement of all sensors, method and sequence of sensor placement, and layout of wiring, conduit, and data collection system. • Details of the access system for attaching and removing instrumentation and associated equipment. • Schematic of data acquisition system. Plans for sampling frequency, data retrieval, and software to be used. Software setup including configuration of ports and flags, and IP addresses. • Instrumentation enclosure and breakaway mounting pole meeting NEMA 4X requirements. • Estimation of power consumption. Planned power and backup power system for a minimum of 7 days uptime. • Detailed plan for all test loading. • Traffic control for each operation associated with instrumentation and evaluation. • Other information shown in the plans or required by the engineer .
829.03.2 Instrumentation : Furnish instrumentation as shown on the plans.
Upon completion of instrumentation work, all instrumentation, power supply, data collection systems, data loggers, conduit and wiring, and data transmitters will become the property of the Department. Weather proof instrumentation with a rating of IP66 or higher for above water applications and a rating of IP68 for submerged applications. Shelter wiring and data collection systems from the weather.
829.03.3 Instrumentation Assistance : Provide access and assistance as
required for installation and removal of instrumentation, and access for data collecti on during the project.
829.03.4 Evaluation : Furnish test loading equipment, equipment operation,
and traffic control as required by the plans.
829.03.5 Instrumentation Services: When specified, provide consultant
services to design the Instrumentation and Evaluation Plan, install instrumentation in accordance with the plans, monitor instrumentation, and upon completion of the instrumentation and evaluation work, remove instrument ation not required for future use.
829.04 INSTRUMENTATION REMOVAL . Remove all sensors, data
acquisition systems along with all associated conduits, and instrumentation enclosure when shown on the plans. Deliver sensors and data acquisition systems to the engi neer after removal. Any unsalvageable materials shall become the • Detailed drawings of placement of all sensors, method and sequence of sensor placement, and layout of wiring, conduit, and data collection system. • Details of the access system for attaching and removing instrumentation and associated equipment. • Schematic of data acquisition system. Plans for sampling frequency, data retrieval, and software to be used. Software setup including configuration of ports and flags, and IP addresses. • Instrumentation enclosure and breakaway mounting pole meeting NEMA 4X requirements. • Estimation of power consumption. Planned power and backup power system for a minimum of 7 days uptime. • Detailed plan for all test loading. • Traffic control for each operation associated with instrumentation and evaluation. • Other information shown in the plans or required by the engineer .
829.03.2 Instrumentation : Furnish instrumentation as shown on the plans.
Upon completion of instrumentation work, all instrumentation, power supply, data collection systems, data loggers, conduit and wiring, and data transmitters will become the property of the Department. Weather proof instrumentation with a rating of IP66 or higher for above water applications and a rating of IP68 for submerged applications. Shelter wiring and data collection systems from the weather.
829.03.3 Instrumentation Assistance : Provide access and assistance as
required for installation and removal of instrumentation, and access for data collecti on during the project.
829.03.4 Evaluation : Furnish test loading equipment, equipment operation,
and traffic control as required by the plans.
829.03.5 Instrumentation Services: When specified, provide consultant
services to design the Instrumentation and Evaluation Plan, install instrumentation in accordance with the plans, monitor instrumentation, and upon completion of the instrumentation and evaluation work, remove instrument ation not required for future use.
829.04 INSTRUMENTATION REMOVAL . Remove all sensors, data
acquisition systems along with all associated conduits, and instrumentation enclosure when shown on the plans. Deliver sensors and data acquisition systems to the engi neer after removal. Any unsalvageable materials shall become the • Detailed drawings of placement of all sensors, method and sequence of sensor placement, and layout of wiring, conduit, and data collection system. • Details of the access system for attaching and removing instrumentation and associated equipment. • Schematic of data acquisition system. Plans for sampling frequency, data retrieval, and software to be used. Software setup including configuration of ports and flags, and IP addresses. • Instrumentation enclosure and breakaway mounting pole meeting NEMA 4X requirements. • Estimation of power consumption. Planned power and backup power system for a minimum of 7 days uptime. • Detailed plan for all test loading. • Traffic control for each operation associated with instrumentation and evaluation. • Other information shown in the plans or required by the engineer .
829.03.2 Instrumentation : Furnish instrumentation as shown on the plans.
Upon completion of instrumentation work, all instrumentation, power supply, data collection systems, data loggers, conduit and wiring, and data transmitters will become the property of the Department. Weather proof instrumentation with a rating of IP66 or higher for above water applications and a rating of IP68 for submerged applications. Shelter wiring and data collection systems from the weather.
829.03.3 Instrumentation Assistance : Provide access and assistance as
required for installation and removal of instrumentation, and access for data collecti on during the project.
829.03.4 Evaluation : Furnish test loading equipment, equipment operation,
and traffic control as required by the plans.
829.03.5 Instrumentation Services: When specified, provide consultant
services to design the Instrumentation and Evaluation Plan, install instrumentation in accordance with the plans, monitor instrumentation, and upon completion of the instrumentation and evaluation work, remove instrument ation not required for future use.
829.04 INSTRUMENTATION REMOVAL . Remove all sensors, data
acquisition systems along with all associated conduits, and instrumentation enclosure when shown on the plans. Deliver sensors and data acquisition systems to the engi neer after removal. Any unsalvageable materials shall become the • Detailed drawings of placement of all sensors, method and sequence of sensor placement, and layout of wiring, conduit, and data collection system. • Details of the access system for attaching and removing instrumentation and associated equipment. • Schematic of data acquisition system. Plans for sampling frequency, data retrieval, and software to be used. Software setup including configuration of ports and flags, and IP addresses. • Instrumentation enclosure and breakaway mounting pole meeting NEMA 4X requirements. • Estimation of power consumption. Planned power and backup power system for a minimum of 7 days uptime. • Detailed plan for all test loading. • Traffic control for each operation associated with instrumentation and evaluation. • Other information shown in the plans or required by the engineer .
829.03.2 Instrumentation : Furnish instrumentation as shown on the plans.
Upon completion of instrumentation work, all instrumentation, power supply, data collection systems, data loggers, conduit and wiring, and data transmitters will become the property of the Department. Weather proof instrumentation with a rating of IP66 or higher for above water applications and a rating of IP68 for submerged applications. Shelter wiring and data collection systems from the weather.
829.03.3 Instrumentation Assistance : Provide access and assistance as
required for installation and removal of instrumentation, and access for data collecti on during the project.
829.03.4 Evaluation : Furnish test loading equipment, equipment operation,
and traffic control as required by the plans.
829.03.5 Instrumentation Services: When specified, provide consultant
services to design the Instrumentation and Evaluation Plan, install instrumentation in accordance with the plans, monitor instrumentation, and upon completion of the instrumentation and evaluation work, remove instrument ation not required for future use.
829.04 INSTRUMENTATION REMOVAL . Remove all sensors, data
acquisition systems along with all associated conduits, and instrumentation enclosure when shown on the plans. Deliver sensors and data acquisition systems to the engi neer after removal. Any unsalvageable materials shall become the • Detailed drawings of placement of all sensors, method and sequence of sensor placement, and layout of wiring, conduit, and data collection system. • Details of the access system for attaching and removing instrumentation and associated equipment. • Schematic of data acquisition system. Plans for sampling frequency, data retrieval, and software to be used. Software setup including configuration of ports and flags, and IP addresses. • Instrumentation enclosure and breakaway mounting pole meeting NEMA 4X requirements. • Estimation of power consumption. Planned power and backup power system for a minimum of 7 days uptime. • Detailed plan for all test loading. • Traffic control for each operation associated with instrumentation and evaluation. • Other information shown in the plans or required by the engineer .
829.03.2 Instrumentation : Furnish instrumentation as shown on the plans.
Upon completion of instrumentation work, all instrumentation, power supply, data collection systems, data loggers, conduit and wiring, and data transmitters will become the property of the Department. Weather proof instrumentation with a rating of IP66 or higher for above water applications and a rating of IP68 for submerged applications. Shelter wiring and data collection systems from the weather.
829.03.3 Instrumentation Assistance : Provide access and assistance as
required for installation and removal of instrumentation, and access for data collecti on during the project.
829.03.4 Evaluation : Furnish test loading equipment, equipment operation,
and traffic control as required by the plans.
829.03.5 Instrumentation Services: When specified, provide consultant
services to design the Instrumentation and Evaluation Plan, install instrumentation in accordance with the plans, monitor instrumentation, and upon completion of the instrumentation and evaluation work, remove instrument ation not required for future use.
829.04 INSTRUMENTATION REMOVAL . Remove all sensors, data
acquisition systems along with all associated conduits, and instrumentation enclosure when shown on the plans. Deliver sensors and data acquisition systems to the engi neer after removal. Any unsalvageable materials shall become the property of the contractor. Dispose of beyond the limits of the project in accordance with Section 202 .
829.05 Measurement .
829.05.1 Instrumentation: Instrumentation will be measured per lump
sum, which includes all materials, equipment, tools, and incidentals necessary to complete this item. Type and quantity of instrumentation will be shown on the plans or as specified in the Instrumentation and Evaluation Plan.
829.05.2 Instrumentation Assistance : Provide instrumentation
assistance for instrumentation items shown on the plans. Instrumentation Assistance will be measured per lump sum. Measurement includes all equ ipment, material, labor, and time necessary to complete this item. Instrumentation Assistance occurrences that are necessary because of contractor error will not be measured for payment.
829.05.3 Evaluation: Evaluation is measured per lump sum, which includes
all materials, equipment, tools, and incidentals necessary to complete this item. The type and description of the evaluation will be shown on the plans.
829.05.4 Instrumentation Services: Instrumentation services will be
measured per lump sum. Measurement will i nclude consultant services to development the Instrumentation and Evaluation Plan, install the instruments, monitoring service, data collection, data analysis, reporting, and removal of instrumentation upon completion of the work.
829.06 PAYMENT. Payment will be made under:
Item No. Pay Item Pay Unit 829-01 Instrumentation Lump Sum 829-02 Instrumentation Assistance Lump Sum 829-03 Evaluation Lump Sum 829-04 Instrumentation Services Lump Sum property of the contractor. Dispose of beyond the limits of the project in accordance with Section 202 .
829.05 Measurement .
829.05.1 Instrumentation: Instrumentation will be measured per lump
sum, which includes all materials, equipment, tools, and incidentals necessary to complete this item. Type and quantity of instrumentation will be shown on the plans or as specified in the Instrumentation and Evaluation Plan.
829.05.2 Instrumentation Assistance : Provide instrumentation
assistance for instrumentation items shown on the plans. Instrumentation Assistance will be measured per lump sum. Measurement includes all equ ipment, material, labor, and time necessary to complete this item. Instrumentation Assistance occurrences that are necessary because of contractor error will not be measured for payment.
829.05.3 Evaluation: Evaluation is measured per lump sum, which includes
all materials, equipment, tools, and incidentals necessary to complete this item. The type and description of the evaluation will be shown on the plans.
829.05.4 Instrumentation Services: Instrumentation services will be
measured per lump sum. Measurement will i nclude consultant services to development the Instrumentation and Evaluation Plan, install the instruments, monitoring service, data collection, data analysis, reporting, and removal of instrumentation upon completion of the work.
829.06 PAYMENT. Payment will be made under:
Item No. Pay Item Pay Unit 829-01 Instrumentation Lump Sum 829-02 Instrumentation Assistance Lump Sum 829-03 Evaluation Lump Sum 829-04 Instrumentation Services Lump Sum property of the contractor. Dispose of beyond the limits of the project in accordance with Section 202 .
829.05 Measurement .
829.05.1 Instrumentation: Instrumentation will be measured per lump
sum, which includes all materials, equipment, tools, and incidentals necessary to complete this item. Type and quantity of instrumentation will be shown on the plans or as specified in the Instrumentation and Evaluation Plan.
829.05.2 Instrumentation Assistance : Provide instrumentation
assistance for instrumentation items shown on the plans. Instrumentation Assistance will be measured per lump sum. Measurement includes all equ ipment, material, labor, and time necessary to complete this item. Instrumentation Assistance occurrences that are necessary because of contractor error will not be measured for payment.
829.05.3 Evaluation: Evaluation is measured per lump sum, which includes
all materials, equipment, tools, and incidentals necessary to complete this item. The type and description of the evaluation will be shown on the plans.
829.05.4 Instrumentation Services: Instrumentation services will be
measured per lump sum. Measurement will i nclude consultant services to development the Instrumentation and Evaluation Plan, install the instruments, monitoring service, data collection, data analysis, reporting, and removal of instrumentation upon completion of the work.
829.06 PAYMENT. Payment will be made under:
Item No. Pay Item Pay Unit 829-01 Instrumentation Lump Sum 829-02 Instrumentation Assistance Lump Sum 829-03 Evaluation Lump Sum 829-04 Instrumentation Services Lump Sum property of the contractor. Dispose of beyond the limits of the project in accordance with Section 202 .
829.05 Measurement .
829.05.1 Instrumentation: Instrumentation will be measured per lump
sum, which includes all materials, equipment, tools, and incidentals necessary to complete this item. Type and quantity of instrumentation will be shown on the plans or as specified in the Instrumentation and Evaluation Plan.
829.05.2 Instrumentation Assistance : Provide instrumentation
assistance for instrumentation items shown on the plans. Instrumentation Assistance will be measured per lump sum. Measurement includes all equ ipment, material, labor, and time necessary to complete this item. Instrumentation Assistance occurrences that are necessary because of contractor error will not be measured for payment.
829.05.3 Evaluation: Evaluation is measured per lump sum, which includes
all materials, equipment, tools, and incidentals necessary to complete this item. The type and description of the evaluation will be shown on the plans.
829.05.4 Instrumentation Services: Instrumentation services will be
measured per lump sum. Measurement will i nclude consultant services to development the Instrumentation and Evaluation Plan, install the instruments, monitoring service, data collection, data analysis, reporting, and removal of instrumentation upon completion of the work.
829.06 PAYMENT. Payment will be made under:
Item No. Pay Item Pay Unit 829-01 Instrumentation Lump Sum 829-02 Instrumentation Assistance Lump Sum 829-03 Evaluation Lump Sum 829-04 Instrumentation Services Lump Sum property of the contractor. Dispose of beyond the limits of the project in accordance with Section 202 .
829.05 Measurement .
829.05.1 Instrumentation: Instrumentation will be measured per lump
sum, which includes all materials, equipment, tools, and incidentals necessary to complete this item. Type and quantity of instrumentation will be shown on the plans or as specified in the Instrumentation and Evaluation Plan.
829.05.2 Instrumentation Assistance : Provide instrumentation
assistance for instrumentation items shown on the plans. Instrumentation Assistance will be measured per lump sum. Measurement includes all equ ipment, material, labor, and time necessary to complete this item. Instrumentation Assistance occurrences that are necessary because of contractor error will not be measured for payment.
829.05.3 Evaluation: Evaluation is measured per lump sum, which includes
all materials, equipment, tools, and incidentals necessary to complete this item. The type and description of the evaluation will be shown on the plans.
829.05.4 Instrumentation Services: Instrumentation services will be
measured per lump sum. Measurement will i nclude consultant services to development the Instrumentation and Evaluation Plan, install the instruments, monitoring service, data collection, data analysis, reporting, and removal of instrumentation upon completion of the work.
829.06 PAYMENT. Payment will be made under:
Item No. Pay Item Pay Unit 829-01 Instrumentation Lump Sum 829-02 Instrumentation Assistance Lump Sum 829-03 Evaluation Lump Sum 829-04 Instrumentation Services Lump Sum property of the contractor. Dispose of beyond the limits of the project in accordance with Section 202 .
829.05 Measurement .
829.05.1 Instrumentation: Instrumentation will be measured per lump
sum, which includes all materials, equipment, tools, and incidentals necessary to complete this item. Type and quantity of instrumentation will be shown on the plans or as specified in the Instrumentation and Evaluation Plan.
829.05.2 Instrumentation Assistance : Provide instrumentation
assistance for instrumentation items shown on the plans. Instrumentation Assistance will be measured per lump sum. Measurement includes all equ ipment, material, labor, and time necessary to complete this item. Instrumentation Assistance occurrences that are necessary because of contractor error will not be measured for payment.
829.05.3 Evaluation: Evaluation is measured per lump sum, which includes
all materials, equipment, tools, and incidentals necessary to complete this item. The type and description of the evaluation will be shown on the plans.
829.05.4 Instrumentation Services: Instrumentation services will be
measured per lump sum. Measurement will i nclude consultant services to development the Instrumentation and Evaluation Plan, install the instruments, monitoring service, data collection, data analysis, reporting, and removal of instrumentation upon completion of the work.
829.06 PAYMENT. Payment will be made under:
Item No. Pay Item Pay Unit 829-01 Instrumentation Lump Sum 829-02 Instrumentation Assistance Lump Sum 829-03 Evaluation Lump Sum 829-04 Instrumentation Services Lump Sum property of the contractor. Dispose of beyond the limits of the project in accordance with Section 202 .
829.05 Measurement .
829.05.1 Instrumentation: Instrumentation will be measured per lump
sum, which includes all materials, equipment, tools, and incidentals necessary to complete this item. Type and quantity of instrumentation will be shown on the plans or as specified in the Instrumentation and Evaluation Plan.
829.05.2 Instrumentation Assistance : Provide instrumentation
assistance for instrumentation items shown on the plans. Instrumentation Assistance will be measured per lump sum. Measurement includes all equ ipment, material, labor, and time necessary to complete this item. Instrumentation Assistance occurrences that are necessary because of contractor error will not be measured for payment.
829.05.3 Evaluation: Evaluation is measured per lump sum, which includes
all materials, equipment, tools, and incidentals necessary to complete this item. The type and description of the evaluation will be shown on the plans.
829.05.4 Instrumentation Services: Instrumentation services will be
measured per lump sum. Measurement will i nclude consultant services to development the Instrumentation and Evaluation Plan, install the instruments, monitoring service, data collection, data analysis, reporting, and removal of instrumentation upon completion of the work.
829.06 PAYMENT. Payment will be made under:
Item No. Pay Item Pay Unit 829-01 Instrumentation Lump Sum 829-02 Instrumentation Assistance Lump Sum 829-03 Evaluation Lump Sum 829-04 Instrumentation Services Lump Sum Section 830 Repair and Rehabilitation
830.01 DESCRIPTION. Perform structural repairs and rehabilitation as
specified.
830.02 MATERIALS. Materials shall be specific to the required actions of the
contract. Comply with the following sections and subsections: Structural Concrete 805.02 Reinforcing Steel 806.02 Structural Metals 807.02 Steel Grid Flooring 808.02 Bridge Railings, Hand Railings and Permanent Roadway Barriers 810.02 Painting and Protective Coat ings 811.03 Treated Timber 812.02 Concrete Approach Slabs 813.02 Bearings 814.02 Joints 815.02 Drainage Systems 816.02 Movable Bridges 820.04 Mechanical Systems 821.04 Electrical Systems 822.04 Facilities 823.04 Portland Cement Concrete 901.02 Epoxy Resin Adhesives Section 1017
830.02.1 Structural Concrete Patching : Conform to Table 830-1 for
structural concrete patching unless otherwise specified. An exception is made for the specific case of patching tops of decks, where rapid setting patching materials for concrete from the Approved Materials List may be used.