209Project Cleanup

MI · 2020 Standard Specifications✓ Full text on BuildSpecBook pages 175–175 Save this section

Ask about Section 209

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

2-49 Section 209. Project Cleanup

209.01 Description

This work consists of removing and disposing of debris including fences, fallen timber, logs, guardrail sections and posts, rocks, boulders, and other rubbish from the Contractor’s operations within the project limits in accordance with section 201 and section 205.

209.02 Materials

None specified.

209.03 Construction

Provide project cleanup as an ongoing operation. Perform project cleanup within the right -of-way but over an area no greater than 50 feet beyond the limits of earth disturbance for the length of the project. Fill holes and ruts resulting from construction operations with Department -approved material. Compact and level filler materials and restore ruts and holes to the surrounding contour in accordance with section 816 or as directed by the Engineer. Clean existing culverts, sewer s, or drainage structures that contain sediment or debris from the construction operation.

209.04 Measurement and Payment

Pay Item Pay Unit Project Cleanup ............................................................................... Lump Sum The Department will pay for Project Cleanup upon completion of the cleanup operation. If the contr act does not include a pay item for Project Cleanup , the Department will consider the cost of this work to be included in the contract unit prices for other relevant pay items.

Sections that cite this one

Get an email when 209 changes

Michigan revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Michigan Standard Specifications for Construction, 2020 Edition. Pages 175–175 of 1,146. View official source ↗

Ask about this section

Scoped to Michigan 2020 Standard Specifications for Construction, Section 209 — Project Cleanup. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.