7-6 Section 704. Steel Sheet Piling and Cofferdams
704.01. Description This work consists of the following:
7-7 3. Assumptions and references for the design calculations;
7-8 Do not install or remove steel sheet piling within 25 feet of newly placed
concrete until the concrete attains at least 70% of the required minimum 28-day flexural or compressive strength.
7-9 704.04. Measurement and Payment
Pay Item Pay Unit Steel Sheet Piling, Permanent ....................................................... Square Foot Steel Sheet Piling, Temp ............................................................... Square Foot Steel Sheet Piling, Temp, Left in Place .......................................... Square Foot Cofferdams (Structure Identification) ............................................... Lump Sum Cofferdams, Left in Place (Structure Identification) .......................... Lump Sum All cost s associated with shop or field welder endorsement to MDOT ’s Welder Qualification Program testing including, but not limited to, providing the specimen test plates, completing performance testing, and submittal of qualification specimen will be at the Contractor ’s expense.
7-10 installing, m aintaining, and cutting off the sheet piling, bracing, tie
backs, deadm en, walers, related material, and equipment required to maintain support of the sheeting and adjacent embankment.