Prosecution and Progress

1809Termination of Contract

MN · 2025 Standard Specifications✓ Full text on BuildSpecBook pages 124–0 Save this section

Ask about Section 1809

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

The Department may terminate the Contract, or any portion of the Contract, for any of the following reasons:

(1)If the Department determines that the Contractor is prevented from proceeding with or

completing the Work within a reasonable period of time for any reason including, but not limited to:

(a)Labor or Material shortage
(b)Limitations imposed by law, rule, regulation, or order of the local, State, or

Federal government

(c)Actions of the public enemy, including those related to priorities and third-

party actions

(2)If the Department determines it is in the best interest of the Department, public, State,

or Nation for any reason including, but not limited to:

(a)Lack of funding or a funding reallocation that prevents the completion of the

Work as planned

(b)Discovery of significant hazardous Material problems
(c)Right-of-way acquisition problems
(d)Utility conflicts that would cause substantial delays or expense to the Contract

If the Department terminates all or any portion of the Contract, the termination will relieve the Contractor of its obligation to perform such portions of the Contract. The termination will not relieve the Contractor of its responsibilities for the Work performed prior to termination, or relieve the Contractor’s Surety of its responsibilities for any just claims arising out of Work performed prior to termination. The Department may direct the Contractor to complete certain elements of the Work before termination of the Contract. The Department will compensate the Contractor for eliminated Contract Items in accordance with 1904, “Compensation for Contract Revisions,” and 1905, “Compensation for Eliminated Items.” Measurement and Payment

Get an email when 1809 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 124–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 1809 — Termination of Contract. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.