SECTION 412 - PRE-GRINDING

412.01 Description. This work shall consist of grinding existing pavement surfaces to

substantially eliminate bumps/knots in the existing pavement which results will improve riding characteristics of the finished paveme nt surface. The work shall be accomplished in accordance with these specifications and in reasonably close conformity to any details on the plans or in the contact documents. Pre-grinding will be allowed, and paid for, on certain projects in which a pay item for pre-grinding is included in the bid items. Pre-grinding will be allowed at the Contractor’s option on all other projects, but at no cost to the State. The Contractor may elect to pre- grind bumps in the existing pavement surface to improve riding characteristics prior to placement of the new asphalt pavement. It is the intent of this specification to remove bumps which cannot be eliminated during the paving operation but not to pre-grind areas that can be corrected with the asphalt overlay.

412.02 Blank.

412.03 Construction Requirements. Prior to any paving operations, the Contractor

shall run a profile of the existing pavement as required in Subsection 403.03.2.1. This profile shall be used to determine if and wher e any areas are located with a short interval MRI value of 160 inches per mile or more. With approval of the Engineer, these areas may be ground prior to placement of the asphalt overlay. Equipment for pre-grinding shall meet the requirements set forth in Section 406 of the Standard Specifications, or other equipment approved by the Engineer. The Contractor shall establish positive means for removal of grinding residue. Solid residue shall be removed from pavement surf aces before it is blown by traffic action or wind. Residue shall not be permitted to flow across lanes used by public traffic or into gutters or drainage facilities, but may be allowed to flow into adjacent ditches.

412.04 Method of Measurement. When a pay item is included in the contract, Pre-

Grinding of existing pavement will be measur ed by the square foot of area approved by the Engineer.

412.05 Basis of Payment. Pre-Grinding, measured as prescribed above, will be paid for

at the contract fixed price per square foot, which price shall be full compensation for all

Referenced in this section

Get an email when 412 changes

Mississippi revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction, 2017 Edition. Pages 343–343 of 1,113. View official source ↗

Ask about this section

Scoped to Mississippi 2017 Standard Specifications for Road & Bridge Construction, Section 412 — Pre-Grinding. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.