502Concrete Bridge End Pavement

MS · 2017 Standard SpecificationsBook pages 376376View official source ↗

Section 501 Section 501 10-foot straightedge at locations selected by the Engineer. The variation of the surface from the testing edge of the straightedge between any two contacts, longitudinal or transverse with the surface, shall not exceed 1/ 4 inch. Irregularities exceeding the specified tolerances shall be corrected, at no additional co st to the State, by the Contractor with an approved profiling device or by other means as directed by the Engineer. Following correction, the area will be retested to veri fy compliance with the specified tolerances. SECTION 502 - CONCRETE BRIDGE END PAVEMENT

502.01 Description . This work consists of bridge end pavement of concrete with

reinforcement as shown on the plans, constructed in one course on a prepared base in accordance with these specifications, and in r easonably close conformity with the lines, grades, thickness, and cross section shown on the plans or as directed. 502.02--Materials . On bituminous paving contracts, concrete for this work may be Class "B" Structural Concrete meeting the applicable requirements of Subsection 804.02. Sampling and testing of concrete for acceptance and control purposes shall be in accordance with Subs ection 804.02.3. Reinforcing steel shall meet the requirements of Subsection 711.02.

502.03 Construction Requirements .

502.03.1 General . The requirements specified for concrete pavement in Section 501,

shall apply in all respects to bridge end pave ment except where otherwise indicated in the specific requirements belo w, or on the plans. When the plans specify a certain thickness of asphalt under the bridge end pavement, the Contractor may substitute Class "B" Structural Concrete base in lieu of the asphalt. The concrete base shall be constructed in one course on a prepared base in accordance with these specifications, and in reasonably close co nformity with the lines, grades, thickness, and typical cross-sections as shown on the plans or as directed. The concrete base will be allowed to cure 24 hours prior to placement of the bridge end pavement. A one-inch premolded expansion joint will be required along the face of the paving bracket. See Section 403 for measurement and payment of substituted concrete base material.

502.03.2 Specific Requirements .

502.03.2 1--Final S creeding and Finishing . The final screeding shall be performed by

hand methods. The concrete shall be screeded longitudinally using the bridge floor for a gauge on one end, and a temporary bulkhead cu t and securely installed true to crown and grade on the other end. In the event the concrete pavement, adjacent to the bridge end pavement, has been previously poured, the end of the pavement shall be used as a gauge in lieu of the temporary bulkhead. The final finish of the bridge end pavement shall be that designated on the plans. If a finish is not designed, the finish shall be transverse tined finish.

502.03.2 2--Joints . Concrete bridge end pavement shall be constructed monolithically,

unless construction joints are speci fically indicated on the plans.

502.04 Method of Measurement . Concrete bridge end pavement, complete in place and

accepted, will be measured as sp ecified in Subsection 501.04.

502.05 Basis of Payment . Concrete bridge end pavement will be paid for at the contract

unit price per square yard in accordance with the methods as provided in Subsection 501.05, which price shall be full compensation for completing the work. Payment will be made under: 502-A: Reinforced Cement Concrete Bridge End Pavement - per square yard SECTION 503 - REPLACEMEN T OF CONCRETE PAVEMENT

503.01 Description . This work consists of replacing continuously reinforced concrete

pavement (CRCP), jointed reinforced concrete pavement (JRCP), or plain jointed concrete pavement (JCP) and the removal and replacement of base materials at locations designated on the plans or as determined by the Engi neer, all in accordan ce with the plans and specifications.

503.02 Materials. Materials shall meet the requirements of Subsection 700.01 and the

following Subsections of Division 700, Materials and Tests. Cement ........................................................................................... 701.01 and 701.02 Fine Aggregate ............................................................................... 703.01 and 703.02 Coarse Aggregate ........................................................................... 703.01 and 703.03 Concrete Admixtures ........................................................................................ 713.02 Water ................................................................................................................ 714.01 Concrete Reinforcem ent Bars ........................................................................... 711.02 Longitudinal Joint Filler ................................................................................... 707.02 Curing Material s ............................................................................................... 713.01

503.03 Construction Requirements.

503.03.1 Equipment . Equipment shall meet the requirements set out in Section 501 for

hand placement and finishing concrete paveme nt. Batching and mi xing equipment shall meet the applicable requirements of Section 804. On-site mixers or truck mixers will be permitted.

503.03.2 Removal of Existing Pavement.

503.03.2 1--General. Existing pavement shall be removed in accordance with details

shown on the plans and as specifically set out herein. Removal will be measured for payment as set forth in Section 202. The Contractor shall dispose of the concrete in accordance with Section 201. Equipment and methods used in all of the work shall not damage any of the underlying base and materials that are to remain in pl ace. All materials which are removed from the roadway shall be disposed of daily. 503.03.2.2--Jointed Reinforced Concrete Pavement (JRCP) . The removal of existing

Source: Mississippi Standard Specifications for Road and Bridge Construction, 2017 Edition. Pages 376376 of 1,113.