625Painted Traffic Markings

MS · 2017 Standard Specifications✓ Full text on BuildSpecBook pages 505–506 Save this section

Ask about Section 625

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 625 - PAINTED TRAFFIC MARKINGS

625.01 Description. This work consists of furnishing materials and applying

reflectorized painted traffic markings and high build painted traffic markings in reasonably close conformity with these specifications and the details shown on the plans or established.

625.02 Materials. Paint shall be the color specified and shall meet the applicable

requirements of Section 710. Application of permanent painted traffic markings shall require Class B (High-Visibility) glass beads. Otherwise, Class A (Standard) glass beads shall be required. Glass beads shall meet the requirements of Subsection 720.01. Blue - ADA marking material shall meet the requirements of Section 710 with the exception that the color shall be Blue - ADA.

625.03 Construction Requirements.

625.03.1 Equipment. All paint shall be applied by approved mechanical equipment

providing constant agitation of paint, traveling at controlled speeds, with one or more paint "guns" synchronized to begin and cut off paint flow automatically for skip lines, and subject to manual control for continuous lines of varying length. The machine, or a separate machine, shall be equipped with a glass bead dispenser adjusted and so synchronized with the paint applicator as to distribute the beads uniformly on the painted lines within 10 seconds. Calibration charts and devices for measurement of tanks shall be provided by the Contractor for determining the quantity being applied. All painting equipment and operations shall be under the control of an experienced technician thoroughly familiar with the equipment, materials, and marking layouts.

625.03.2 Preparation of Surface. All areas to be painted shall be thoroughly cleaned.

Cleaning may be done by hand brooms, rotary brooms, air blast, scrapers, or whatever combination of equipment is necessary to clean the pavement thoroughly without damage to the surface. Before edge striping, particular care shall be taken to remove all vegetation, loose soil, and the like from the area to be painted. Should other methods fail, the surface shall be wetted with a water jet and scrubbed as necessary to dislodge all foreign material. After washing, the surface shall be allowed to dry thoroughly, and all films of dried mud apparent after surface drying shall be removed before application of paint. Painting shall follow as closely as practicable after the surf ace has been cleaned and dried, but no paint shall be applied until the surface has been inspected and permission given to proceed. The cost for preparing the surface shall be included in the contract unit prices for the marking items. Upon request, the Engineer will establish control points for markings, by type and color, at necessary intervals not to exceed 600 feet . The Contractor shall preserve and apply markings in conformity with control points established.

625.03.3 Application. The paint shall be applied when the ambient temperature is no less

than 50oF, the pavement surface is properly prepared and the temperature of the pavement surface is no less than 50oF. For four-inch temporary traffic stripe, paint and Class A glass beads shall be uniformly applied at the rate of not less than one gallon of paint and six pounds of beads per 264 linear feet of four-inch stripe. For six-inch permanent traffic stripe, paint and Class B glass beads shall be uniformly applied at the rate of not less than one gallon of paint and twelve pounds of beads per 176 linear feet of six-inch stripe. For six-inch permanent high build traffic stripe, paint and Class B glass beads shall be uniformly applied at the rate of not less than one gallon of paint and twelve pounds of beads per 140 linear feet of six-inch stripe. The length and width of lines shall be within a tolerance of plus or minus three inches and plus or minus 1/8 inch, respectively. For skip markings, the tolerance for intervals shall not exceed the line length tolerance. Markings applied at less than minimum material rates, deviating from true alignment by more than one inch in 50 feet, exceeding stipulated length and width tolerances, and showing light spots, faulty distribution of beads, smears, or other deficiencies or irregularities shall be removed and replaced. Removal methods shall be in accordance with Subsection 619.03.2.

625.03.4 Protection. The newly painted markings shall be protected so that, insofar as

possible, paint will not be picked up by the tires of passing vehicles. Warning signs shall be placed at the beginning of a wet line and at points well in advance of the marking equipment. For the benefit of the Contractor, small flags or other similarly effective small objects may be placed near freshly applied lin es at frequent interval s to reduce crossings by traffic. Damaged portions of stripes shall be effaced and replaced by the Contractor at no additional cost to the State. Operations shall be conducted so that traffic can move without undue hindrance. When public traffic is being maintained, warning signs at the starting end shall be moved forward as sections of stripe dry sufficiently to prevent pick-up under traffic. Reference is made to Subsection 710.02.2.2 for the particular paint involved.

625.03.5 Detail Traffic Stripe. Detail traffic stripe shall be those short stripes, exclusive

of lane and edge striping of the main facility, at exit and entrance ramps, turnouts, turn bays, and other locations indicated on the plans. When shown on the plans or directed by the Engineer, detail stripe of the color, width, and length shall be placed in accordance with the provisions and requirements of this section.

625.03.6 Legend. Legend shall be applied by the use of templates cut to the dimensions

shown on the plans, or by other methods approved by the Engineer that will provide a clean cut, uniform, and workmanlike appearance. All other requirements for legend shall be in accordance with the applicable materials and construction requirements of this section. Legend that fails to have a uniform, satisfactory appearance either by day or by night shall be corrected by the Contractor or removed and replaced at no additional cost to the State.

Get an email when 625 changes

Mississippi revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction, 2017 Edition. Pages 505–506 of 1,113. View official source ↗