619.01Description. This work consists of furnishing, placing, maintaining or replacing
as necessary, removing when no longer applicable and installation at other locations all traffic control devices including pavement marking materials (paint, tape, markers, etc.) in accordance with contract provisions and as directed by the Engineer.
619.02Materials. Certification of traffic control devices shall be in accordance with the
provisions of Subsection 619.02.13.
.1--Painted Traffic Stripe . Painted traffic stripe shall meet the applicable
requirements of Sections 710 and 720. The temporary traffic paint can be waterborne paint or fast dry solvent traffic paint meeting the requirements set out in Section 710. When using fast dry solvent traffic stripe, no paint can be sprayed or placed on the ground during set-up or clean-up.
.2--Pavement Marking Tape . Preformed pavement marking materials must be
listed on the Department's APL and meet the requirements of Subsection 720.05.
.3--Reflective Raised Pavement Markers. Raised pavement markers must be on
the Department's APL and shall meet the applicable requirements of Subsection 720.03.
.4--Construction Signs. Construction signs shall meet the applicable requirements
of Sections 618 and 721 and the following: Sign supports may be steel beams, structural steel pipe, steel U-section posts, 4-inch x 4- inch wood posts, portable easels, or barric ades as required for installation. Breakaway bases shall be provided for all steel beams and pipe posts. Portable sign supports may be used for daylight operations, moving work areas, or other short-term activities. Standards for height of construction signs shall be those shown for roadside signs in Chapter 6F of the MUTCD. Signs mounted on portable supports or barricades may be at lower heights but the bottom of the sign shall be no less than one foot above the traveled way. Unless specified otherwise, fluorescent orange reflective sheeting, meeting the requirements of Subsection 721.06, shall be used on all construction signs regardless of whether used during daytime or nighttime hours. Unless otherwise specified on the plans, the material on which the reflective sheeting is to be applied shall be as a minimum, 16-gauge steel, 0.080-inch aluminum, or 5/8-inch high density overlaid plywood. Ungalvanized st eel, exterior grade plyw ood and lumber shall have a minimum of two coats of paint on front, back, and edges. High density overlaid plywood shall have the edges painted. The material to which reflective sheeting is to be applied shall be prepared in accordance with the recommendations of the sheeting 450 Section 619 Section 619 manufacturer. For new signs, the Contractor shall furnish the Engineer with three certified copies of a statement or test report from the producer indicating that th e signs meet the requirements of the specifications. Previously used signs will be accepted on the basis of reflectivity and legibility. Reflectivity for these signs may be tested by the Engineer in accordance with the procedures set out below or by the Central Laboratory. If tested by the Central Laboratory, the reflective sheeting shall have at least 50 percent of the reflectivity specified for new sheeting. Tests performed in the Central Laboratory will be for reflectance only, and the Contractor shall pay the testing charges. Legi bility in all cases will be determined by the Engineer. The determination for reflectivity and legibility by the Engineer will be made from the driver’s seat of an automobile with the headlamps on low beam between the hours of one hour after sunset and one hour before sunrise at the distance specified below. The signs shall be mounted at the specified height for each type sign as it is being tested. Should the Contractor elect to have the signs tested in place, each sign not meeting the requirements of these specifications shall be immediatel y removed and replaced. The Engineer will certify by letter to the State Materials Engineer that the signs have been tested and accepted under this procedure. A sign will be considered as meeting the reflectivity requirements of this specification when the shape and color of the sign can be unquestionably identified at a distance of 1500 feet from the sign. In cases where grade or alignment will not permit a sight distance of 1500 feet, the distance for specification compliance shall be the furthermost point at which the complete sign becomes visible. If there is a question as to a sign being acceptable, the sign may be sent to the Central Laboratory for verification. Testing charges will be borne by the State when the verification test determines that the sign is acceptable. Legibility will be acceptable when the sign letters and numerals are capable of being read at a distance determined by the following formula: D = 50 H D = Distance in Feet H = Letter/numeral height in inches
.5--Advance Warning Flashing Arrow Panels. Flashing arrow panels shall meet
the requirements of Section 6F.61 of the MUTCD.
.6--Median Barrier and Delineators. New precast concrete median barrier shall
meet the requirements of the plans, contract documents, and Section 615 except the surface may be a Class 1 ordinary surface finish unl ess designated otherwise. When precast concrete median barriers are no longer needed at one location, as determined by the Engineer, the barriers shall be removed and reset at other designated locations. When barriers have to be stored until needed at another location, payment for removing and resetting will not be made until they are reset at their designated location. The Contractor shall furnish the storage area. 451 Section 619 Section 619 The Engineer may allow the installation of used barriers for temporary traffic control upon an inspection and determination that the barrier units are structurally adequate for their intended purpose and they meet the requirements of this Section. Barriers with small chips or fractures not affecting their integrity may be accepted. Precast concrete barriers used on constructi on projects purchased or manufactured after October 1, 2002 must meet the requirements of NCHRP Report 350 or MASH. Precast median barriers purchased or manufactured prior to October 1, 2002 may be used until they complete their normal service life. Certification of precast concrete barriers shall be as required in Subsection 619.02.13. Portable median barrier shall be a highly portable, crashworthy barrier especially designed and used as a temporary barrier on highway construction projects. The barriers shall be designed so that it can be filled with water when in use and be easily drained for moving and transporting. The barrier shall be NCHRP Report 350 or MASH approved for the speed rating indicated on the plans or in the contract documents. The Contractor shall furnish the Engineer th ree copies of the manufacturer's certification stating that the portable median barriers furnished meets the requirements of this Section. Delineators shall be listed on the Department's APL and meet the requirements of the plans and Section 6F.68 of the MUTCD.
.7--Channelization Devices, Barricades, and Warning Lights . Channelization
devices, vertical panels, tubular markers, cones, drums, barricades and temporary raised islands shall meet the requirements of the pl ans and Sections 6F.63 through 6F.75 of the MUTCD. Drums shall be constructed of li ghtweight, deformable material capable of retaining reflective sheeting. Reflective sheeting for drums shall be Type III meeting the requirements of Subsection 721.06. Warning lights shall meet the requirements of Section 6F.83 of the MUTCD. The use of 2-inch nominal thickness timber for rails on Type III barricades has not been approved by NCHRP or MASH as a crashworthy device. Therefore, the use of 2-inch nominal thickness timbers will not be allowed for rails on Type III Barricades. Timber rails for Type III Barricades shall be as follows. • For barricades up to four feet (4’) wide, the maximum thickness of timber rails shall be one inch (1”) and the material shall be pine timber or ¾-inch ACX plywood. • For barricades more than four feet (4’) wide, timber rails shall be constructed of ¾- inch ACX plywood. A list of crashworthy Type III Barricades can be found at the following FHWA website. http://safety.fhwa.dot.gov/roadway_dept/policy_guide/road_hardware/wzd/
.8--Traffic Signals and Flashers . Traffic signals and flashers shall meet the
requirements of the plans and Section 6F.84 & 6F.81 of the MUTCD.
.8.1--Portable Traffic Signals. Portable traffic signals shall be trailer mounted
452 Section 619 Section 619 units that provide for easy transportation and quick setup and deployment. Each unit shall be self-contained. The types of portable traffic signals are as follows. • Type 1 portable traffic signal shall include one signal head that is mounted on the vertical upright of the trailer. • Type 2 portable traffic signal shall include two signal heads per trailer with one signal head mounted on an overhead mast arm that can be extended over the travel lane, and the other signal head shall be mounted on the vertical upright of the trailer. • Type 3 portable traffic signal shall be the same as Type 2 mentioned above but with enhanced capabilities as mentioned in each applicable section below. The portable traffic signals shall be MUTCD Compliant and utilize standard ITE signal heads, and adhere to the ITE Specifications and Standards for Vehicle Traffic Control Signal Heads, Light Emitting Diode (LED) Circular Signal Supplement. The units shall be solar powered and be able to communicate with other portable signals via wireless communications. The unit shall include all the major components listed below or be able to perform the functions of these components. The major components of the unit shall include but are not limited to the trailer, telescoping mast arm (on Type 2), signal head(s) and back plates, traffic signal controller with operating software, solar charging system with batteries, input and output devices, flasher units, conflict monitor, relays, communications system and other equipment required for the safe operation and installation of the unit.
.8.1.1--Signal Heads . The signal heads and all applicable components of the
portable traffic signal shall meet the physical display and operational requirements of conventional traffic signals as specific in the Manual on Uniform Traffic Control Devices (MUTCD). The signal heads shall meet the requirement laid out in the Mississippi Standard Specification for traffic signa l heads and associated MDOT material specifications for traffic signal heads. For Type 1, Type 2 and Type 3 signals, the signal heads shall have the ability to be rotated 180 degrees to face in the opposite direction and shall have the ability to rotate and lock in approximately 10 degree increments to position the signal head for the optimum visibility to motorists. For Type 1 signals, the signal head shall be mounted to the vertical upright of the trailer at a minimum height of eight feet (8') from th e bottom of the signal head unit to the road surface. For Type 2 signals, each unit shall contain two signal heads with one signal head mounted on an overhead mast arm that can be exte nded over the travel lane with a minimum clearance of 17 feet measured from the bottom of the signal head unit to the road surface. The lower signal head shall be mounted to the vertical upright of the trailer at a minimum height of eight feet (8') from the bottom of the signal head unit to the road surface. For Type 3 signals, each unit shall be the same as Type 2 mentioned above but with
enhanced capabilities as mentioned below.
.8.1.2--Controller and Operating Requirements. The portable traffic signal
(Types 1, 2, and 3) shall include a controller that is in compliance with NEMA TS 1
Performance Standard. The controller shall have an easy to read front panel indicator
453
Section 619 Section 619
display for showing and programming the configuration settings and controller status. The
controller shall be capable of operating the portable traffic signal system in a fixed time,
traffic actuated or manual control mode. Each portable traffic signal in a connected system
shall have the capability to serve as either the master or remote signal. Each portable traffic
signal shall include a Conflict Monitor Unit (CMU), or Malfunction Management Unit
For Type 1 and Type 2 signals, a minimum of five (5) automatic time-of-day timing plans
within a 24-hour period should be available in fixed time mode. The operating system
should have the ability to control a minimum of four (4) traffic phases with programmable
cycle time adjustments and user adjustable red, amber, minimum green and maximum
green times. The operating system shall also have the capability of facilitating standby
modes of red, red flash and yellow flash.
For Type 3 signals, a minimum of ten (10) automatic time-of-day timing plans within a 24-
hour period should be available in fixed time mode. The operating system should have the
ability to control a minimum of 16 traffic phases with programmable cycle time
adjustments and user adjustable red, amber, minimum green and maximum green times.
The operating system shall also have the capability of facilitating standby modes of red,
red flash and yellow flash.
The system shall also have the ability to operate in vehicle actuation mode when vehicle
detectors are used. The operating system shall have the capability to allow the Portable
Traffic Signal to be connected to and controlled by a standard NEMA controller.
The system shall have the capability to be configured and controlled remotely using a
flagger radio remote control at a distance up to ¼ mile from the master.
The system shall have the capability of remote monitoring for reporting, at a minimum,
signal location and status, battery voltage and system defaults. The remote monitoring
shall have capability to alert designated individuals if a fault condition occurs.
The operating system shall include password protection to prevent unauthorized
programming.
.8.1.3--Wireless Communications. The portable traffic signals shall communicate
with other portable traffic signals in the system via license-free wireless 900 MHZ radio
link communications as specified in Subsection 662.02.2 of the radio Interconnect System
specification. The radio units shall maintain communications at a minimum distance of
one (1) mile. The radio system shall conform to the applicable Federal Communications
Commission requirements and all applicable state and local requirements.
The portable traffic signals shall be in direct communication at all times either by wireless
or hardwire connection to provide for the required conflict monitor.
.8.1.4--Power Requirements. The portable traffic signal shall be equipped with a
solar power array, charging unit and battery system. The number and size of batteries shall
be sufficient to operate the Type 1 and Type 2 signals for a minimum of 21 days and Type
3 signals for minimum of 30 days without additional charging or assist from the solar array.
An on-board battery charger shall be compatible with both the solar array and with a 120V
AC power source.
454
Section 619 Section 619
For Type 1 and Type 2 signals, the solar panel array shall provide for a minimum of 440
watts of solar collection capability.
For Type 3 signals, the solar panel array shall provide for a minimum of 480 watts of solar
collection capability and shall include a tilt and rotate system to optimally position the
panels.
All instrumentation for the electrical system and battery compartment shall be mounted in
a lockable weatherproof enclosure. Solar panels shall be secured to the mounting brackets
for theft prevention.
.8.1.5--Trailer and Lift System. For Type 1 and Type 2 signals, the trailer and all
mounted components shall conform to the wind loading requirements of 80 mph minimum
as described in the AASHTO Standard Specifications for Highway Signs, Luminaries and
Traffic Signals. For Type 3 signals, the trailer and all mounted components shall conform
to the wind loading requirements 90 mph minimum as described in the AASHTO Standard
Specifications for Highway Signs, Luminaries and Traffic Signals. The trailer shall be
made of structural steel and shall include four (4) leveling/stabilizer jacks capable of lifting
the trailer a minimum of six inches (6”).
The trailer shall be equipped with a hydraulic or electric lift system sufficient for one
person to be able to raise and lower the vertical upright and/or horizontal mast arm to and
from the operating position.
For Type 2 and Type 3 signals, the trailer shall be equipped to provide legal and safe
transport on the public highway system at speeds up to 55 mph.
All exterior metal surfaces, except signal heads and back plates, shall be powder-coat
painted highway safety orange.
.9--Impact Attenuators. Impact attenuators must be listed on the Department's
“Approved Sources of Materials”.
Approved impact attenuator systems shall meet standardized testing defined in NCHRP
Report 350 or MASH. In addition, documentation from FHWA must accompany the
devices, indicating that the devices meet the appropriate crash test criteria and can be used
on the National Highway System (NHS). Prior to installation, the Contractor shall provide
two copies of the manufacturer’s installation details to the Project Engineer. The Project
Engineer shall keep one copy in the project file and provide one copy to District
Maintenance Engineer. The installation details shall be engineering drawings, a minimum
of 11"x17" in size. Reflective adhesive sheeting with alternating black and yellow stripes
(sloping downward at an angle of 45 degrees in the direction traffic is to pass) shall be
required on the end of the attenuator section. The type of system installed shall be written
on the device with a Permanent Marking Stick or some other means of permanent
identification.
When an impact attenuator is no longer needed at one location, as determined by the
Engineer, the attenuator shall be removed. When the contract documents contain
provisions for the removal and resetting of impact attenuators, the attenuator shall be
removed and reset at other designated locations. When an impact attenuator is stored until
455
Section 619 Section 619
needed at another location, payment for removing and resetting will not be made until the
attenuator is reset at the designated location. The Contractor shall furnish the storage area.
Replacement Packages. Replacement packages shall consist of spare parts of the expected
type and number needed to repair one hit for every three attenuators in place.
.10--Temporary Guardrail. Temporary guardrail shall meet the requirements of
the plans and the applicable requirements of Sections 606 and 712.
.11--Snap-Back Delineators. Snap-back delineators shall be selected from the list
of surface mounted flexible delineator posts as shown on the Department's "Approved
Sources of Materials".
.12--Terminal End Section. Terminal end sections, installed as per manufacturer’s
recommendations, must meet the requirements of NCHRP Report 350 or MASH. When
specified in the plans, the terminal end sections shall be the type specified, unless otherwise
approved by the Engineer.
Terminal end sections shall be Flared or Non-Flared and shall be one listed on the
Department’s APL. The end sections shall be installed in accordance with the
manufacturer’s recommendation. Prior to installation, the Contractor shall provide two
copies of the manufacturer’s installation details to the Project Engineer. The Project
Engineer will keep one copy in the project file and provide one copy to the District
Maintenance Engineer. The installation details shall be engineering drawings, a minimum
of 11” X 17” in size. Reflective adhesive sheeting with alternating black and yellow stripes
(sloping downward at an angle of 45 degrees in the direction traffic is to pass) shall be
required on the end of the terminal section. The type of terminal section installed shall be
written on the device with a Permanent Marking Stick or some other means of permanent
identification.
.13--Certification of Traffic Control Devices. The Contractor will be required to
certify that the traffic control devices used on the project meets certain requirements. The
traffic control devices shall be certified in accordance with the following requirements:
Category 1 Traffic Control Devices. Category 1 traffic control devices are defined as low-
mass, single-piece traffic cones, tubular markers, single-piece drums with or without lights
and hardware, and delineators.
The Contractor shall certify to the Project Engineer by a letter ONLY stating that the
Category 1 traffic control devices, furnished and used, meet the requirements of NCHRP
Report 350 or MASH.
All documentation supporting the certification is to be kept on file by the Contractor subject
to review by the Department at any time. Support documentation shall be kept on file for
two years after the completion of the project.
The Contractor may self-certify Category 1 Traffic Control Devices. In order to make the
self-certification, the Contractor shall have as a minimum the following support
documentation regarding the certification:
456
Section 619 Section 619
pages and the total number of pages;
of NCHRP Report 350 or MASH. This basis as crash test experience with similar
devices or years of demonstrably safe operational performance;
responsibility for the content of the certification, however produced, and the date
of issue;
All documentation supporting the self-certification is to be kept on file by the Contractor
subject to review by the Department at any time. Support documentation shall be kept on
file for two years after the completion of the project.
The Contractor's letter to the Project Engineer shall state that all Category 1 traffic control
devices, furnished and used, meet the requirements of NCHRP Report 350 or MASH.
Category 2 Traffic Control Devices. Category 2 traffic control devices are defined as
barricades with or without lights and signs, intrusion detectors, vertical panel assemblies,
portable sign supports, drums with warning lights, and cones with warning lights not
meeting Category 1.
The Contractor shall certify to the Project Engineer by a letter ONLY stating that the
Category 2 traffic control devices, furnished and used, meet the requirements of NCHRP
Report 350 or MASH. The Contractor's letter shall state that all Category 2 traffic control
devices, furnished and used, meet the requirements of NCHRP Report 350 or MASH.
Category 3 Traffic Control Devices. Category 3 Traffic Control Devices are items similar
to Category 2 but weigh more than 100 pounds. Category 3 Traffic Control Devices
include concrete barrier, portable barriers, truck mounted attenuators (TMAs), work zone
crash cushions, and fixed sign supports.
Category 3 traffic control devices, furnished and used, must meet the requirements of
NCHRP Report 350 or MASH. The Contractor shall furnish a letter ONLY certifying that
the Category 3 traffic control devices meet the requirements of NCHRP Report 350 or
MASH.
.14--Changeable Message Sign. This work shall consist of furnishing, testing, and
maintaining a trailer-mounted electronic Portable Changeable Message Sign (PCMS)
assembly. The sign display shall be a LED, full matrix sign. If more than one portable
changeable message sign is required for this project, they shall all be of the same model
and from the same manufacturer. All parts and materials used to construct the portable
changeable message signs shall be interchangeable.
The PCMS shall be a trailer-mounted, solar powered, portable changeable message sign.
457
Section 619 Section 619
Each PCMS shall include the following main components:
The LED display shall be a full matrix sign with a minimum of 28-pixel rows x 50-pixel
columns. The pixel spacing shall be such that three (3) lines of text (5 columns x 7 rows,
8 characters) shall each have a nominal height of 18 inches.
The PCMS shall include a remote communications interface as specified herein. The
PCMS shall be provided with a local serial and USB connection within the sign control
cabinet so that a laptop computer using the remote software can communicate directly with
the sign CPU.
This subsection incorporates normative references to other standards as outlined in Section
1 of the NEMA TS-4 standard and as listed below.
NEMA TS4-2004, Hardware Standards for Dynamic Message Signs (DMS) with NTCIP
Requirements. All NEMA TS-4 requirements that are applicable to portable signs shall
be used.
NTCIP Standards.
If a conflict exists between the standards referenced and this Specification, this
Specification shall govern.
The definitions of the terms used within this Specification are as defined in Section 1 of
the NEMA TS-4 standard.
If required in the contract, the PCMS shall include a speed radar unit as specified herein.
.14.1--Mechanical Construction. Each PCMS shall meet the following minimum
requirements.
Weather-Tight Enclosure. The entire sign and trailer assembly, including each component
/ equipment exposed to weather, shall be fully protected. It shall withstand the effects of
sand, dirt, dust, moisture, hose-directed water, ice, snow and UV radiation (UVA and
UVB). It shall withstand the effects of high wind loading and blowing rain as specified
herein with all outriggers and/or leveling jacks in place. The sign and all components shall
be watertight. Space shall be provided for manuals to be stored in a weatherproof
environment.
Wind Loading. Wind loading requirements for the portable sign housing and trailer
assembly shall be as specified in Section 3.3.2.1.2 of the NEMA TS-4 standard.
458
Section 619 Section 619
Welding. All welding on all major structural components (aluminum or steel) shall be
performed by certified welders and in accordance with SAE/AWS D8.8 American Welding
Society.
Protective Coatings. Protective coatings or processes, such as anodizing, e-coating,
powder coat painting, plating, etc., shall be incorporated to protect all sign, cabinet, and
trailer metal surfaces from corrosion. Any non-protected metallic fasteners shall be made
of stainless steel or aluminum. All components shall be of similar material, or be isolated
to reduce galvanic reactions.
Temperature and Humidity. Each PCMS shall be designed to operate continuously in
extreme ambient temperature ranges and at high humidity levels.
Operating ambient temperature range of the portable sign and trailer assembly shall be -
29°F to +165°F. Storage temperature range shall be from -40°F to +185°F. The portable
sign shall be capable of continued operation within the operating temperature ranges
specified without the need for active systems (i.e., fans). Operating relative humidity level
of the portable sign shall be up to 95% non-condensing.
Sign Face. Sign face material shall be protected by a non-glaring polycarbonate material
of at least ¼-inch thickness. It shall be replaceable and manufactured of material rated for
outside use and resistant to UV degradation (exposure to the sun).
All electronics and pixels shall be protected from damage due to moisture.
Sign Housing Construction. The portable sign housing, including its front face panels,
shall be designed to conform to the requirements of minimum NEMA Type 3R, as
described in the latest edition of NEMA 250.
It shall comply with the latest structural AASHTO requirements.
It shall be constructed of aluminum sheeting that shall not be less than 1/8-inch thick with
all seams continuously welded by the inert gas process.
The front of the sign housing shall have a flat black matte finish.
Weep holes shall be provided in the housing to allow moisture from condensation to
escape.
The sign housing and cabinets shall be designed to keep insects out.
The sign housing shall be constructed in such a manner as to prohibit stray light from
reducing legibility.
All sides of the sign housing shall have a maintenance-free finish.
Alignment of the sign housing shall be capable of being horizontally adjusted to position
the sign a full 360 degrees. It shall be capable of rotating and locking at any selected
horizontal angle up to 360 degrees. A sight alignment tube/device shall be mounted to
459
Section 619 Section 619
horizontally position the sign display. A positive brake assembly with lockable control
arm shall be provided to position the sign display in the desired position.
It shall allow easy access to all components contained within the display housing without
the removal of any external parts. Door locks shall be rigidly mounted. Gasketing shall
be provided on all door openings and shall be dust-tight, permanently bonded to the door
metal, and shall not stick to the mating metal surface. A gasket channel shall be provided
to support the gasket on the door.
Trailer. Each PCMS trailer shall meet all requirements for trailers as outlined in Section
3.3.3 of the latest NEMA TS-4 standard as well as the following minimum requirements.
transport safety including, but not limited to the use of brakes, safety chains,
coupling device, and lights. PCMS manufacturer shall provide instructions stating
procedures necessary to ensure safe transport.
load of the trailer corresponding to the axle and tire ratings in accordance with
FMVSS, Part 571.
steel wheels with five lug bolts per wheel. Each trailer wheel shall be equipped with
one locking lug nut. A minimum of four keys for the locking lug nuts shall be
supplied for each trailer.
One outrigger or leveling jack shall be mounted near each corner of the trailer. The
length of the leveling jacks shall be such that when the trailer is level, all four jacks
and the tongue jack can be lowered into the vertical position. The jacks shall be
screw type jacks with a minimum 25-inch lift. Each jack shall include a swivel
mechanism that allows the jacks to swing up to a horizontal position for towing.
The swivel mechanism shall secure the jack in both vertical and horizontal positions
through a lock pin.
trailer. The stand shall be corrosion resistant. It shall include a 6-inch wheel that
allows horizontal positioning of the trailer. The stand shall be welded, not bolted,
to the tongue of the trailer.
mounting bracket. The trailer shall be supplied with an electrical harness assembly
for connection to the tow vehicle and shall be terminated in a connector type to be
specified by the Engineer.
accordance with SAE J684 and interchangeable with a 2½-inch Pintle coupler / ring
meeting SAE J847.
shall be electric, hydraulic lift, or combination of both with manual backup lift. The
lift shall be capable of lifting the display a minimum of seven feet (7’) above the
roadway surface. A mast safety pin shall be provided to prevent the sign display
from falling in the event of an electric or hydraulic system failure.
system along with a breakaway latch.
460
Section 619 Section 619
change the sign controller data in darkness.
Photovoltaic (Solar) Panel System. Each PCMS shall include solar panels. A solar bank
shall be assembled using multiple solar panels. All photovoltaic panels shall be listed in
accordance with UL 1703, or equivalent. The solar cell bank shall have a minimum
capacity of 240 watts. The solar cell bank shall be mounted on a frame capable of being
tilted at a minimum of one direction up to 61 degrees with zero degrees being horizontal.
Solar cells shall be laminated between ethylene vinyl acetate and tempered glass. The solar
panel shall incorporate an extruded aluminum frame. The solar battery charge controller
shall include the following three state charger modes:
• Bulk
• Absorption
• Float
Battery Requirements. Each PCMS shall include batteries for primary energy storage on
trailers. The battery bank capacity shall be a minimum of 900 amp/hours at 12VDC at a
20-hour rate of discharge. The batteries shall be heavy duty deep cycle type rated for 80%
discharge. A battery power disconnect shall be provided.
Battery enclosures shall be vented to prevent the accumulation of explosive gases. The
battery cabinets must be lockable with a standard padlock.
AC Charging System. Each PCMS shall have an AC battery charging sub-system. The
system shall be UL listed and operate from a standard 120VAC generator meeting all NEC
requirements for portable equipment.
The solar battery charger shall include the following three state charger modes:
• Bulk
• Absorption
• Float
The AC battery charger shall have sufficient capacity to charge the battery bank from 80%
discharged to fully charged in 24-hours, and operate the sign simultaneously. The AC
battery charger shall be equipped with a male plug-in and a 50-foot long extension cord
constructed of a minimum 12-guage wire for this purpose.
.14.2--Controller to Sign Interface. Each PCMS shall meet all applicable
controller to sign interface requirements as outline in Section 4 of the NEMA TS-4
standard.
.14.3--Display Properties. Each PCMS shall have a cone of vision (viewing angle)
from the center (reference axis) shall be a minimum 15 degrees with the half-power
viewing angle defined such that at a given distance from the LED, luminous intensity
measured at any point at an angle of 7.5 degrees from the LED's center axis is no less than
half the luminous intensity measured directly on the LED's center axis.
461
Section 619 Section 619
The minimum word legibility requirements shall be 1232 feet or greater under daytime
light conditions and within the cone of visions as specified. Legibility is defined as the
ability to discern the content of a display using a “word message.” The minimum word
legibility requirement shall be documented either by a Department approved independent
testing laboratory or by participation in the NTPEP test program.
The minimum visibility requirements shall be 3000 feet or greater under daytime light
conditions and within the cone of vision as specified. Visibility is defined as the ability to
recognize that a display exists. The minimum visibility requirement shall be documented
either by a MDOT approved independent testing laboratory or by participation in the
NTPEP test program.
The PCMS shall be capable of displaying standard fonts and font alphabets as specified in
Sections 5.6.1 and 5.6.2.3 of the NEMA TS-4 standard and adhere to NTCIP 1203. The
PCMS shall also support moving arrows.
Any NTPEP test results shall be for the PCMS model being used and shall be within the
last three completed test cycles.
.14.4--Optical Components. The pixels for the PCMS shall be manufactured using
Light Emitting Diodes (LED). Changes to displays shall be performed by turning the LEDs
in a pixel either on or off. The discrete LED shall be an untinted, non-diffused, solid-state
lamp that uses Aluminum Indium Gallium Phosphide (AlInGap) technology manufactured
by Avago Technologies (formerly Agilent Technologies), Toshiba Corporation, Nichia
Corporation, or functional equivalent. Horizontal and vertical spacing between modules
shall be such that the horizontal and vertical pitch between all pixels is equal. A failure of
one pixel shall not affect the operation of any other pixel.
All LEDs used to create a display in a single portable sign shall have a nominally rated
LED life of 100,000 hours of operation under field conditions. This shall include operating
temperatures between -29°F to +165°F. LED life shall be defined as the time it takes for
the LED light output to degrade to half of the LED's initial light output. The current
through an LED shall be limited to the manufacturer’s recommendation under any
conditions. Each LED character module shall be rated for use over the environmental range
specified herein, including heat absorption due to sunlight. The LEDs shall be protected
from the outside environmental conditions, including moisture, snow, ice, wind, dust, dirt,
and UV rays (UVA and UVB). All LEDs shall be mounted so that they present a uniform
and legible display.
Pixels shall be replaceable in modular groupings (modules). All modules within a sign
shall be the same size and interchangeable. The replacement of any module shall be
possible with no more than simple non-vendor-specific hand tools, such as screw drivers
or wrenches, without any physical modification to the module.
.14.5--PCMS Controller and Storage Cabinets. All PCMS controller and storage
cabinets shall be a minimum of NEMA 3R rated and be completely encased and lockable
with a standard padlock as specified herein. A separate lockable storage cabinet shall be
provided to house various accessories. The controller cabinet shall be manufactured to
withstand all types of adverse weather conditions and shall be designed and installed to
keep insects out. All components inside the controller cabinet shall be accessible without
disconnecting any unassociated wires or components. The controller cabinet shall be
462
Section 619 Section 619
illumination. The keyboard terminal and control panel shall be housed. Lighted keys and
terminal displays are acceptable.
All controls in the controller cabinet shall be labeled. The cabinet shall have a voltmeter
gauge to indicate the current battery charge status. It shall have an amp gauge to indicate
the current/charging status. It will be acceptable to have a display via digital readout on a
control console or panel.
.14.6--Electronics and Electrical. Each PCMS shall meet all applicable electronics
and electrical requirements as outlined in Section 8 of the NEMA TS-4 standard.
Sign Controller. The PCMS shall include a local sign controller with firmware. The local
control interface shall have a keyboard capable of allowing full programming and control
of the PCMS locally. It shall have a separate serial RS-232 or USB connection to allow a
laptop computer using the remote control software to communicate directly with the sign
controller.
Local and remote interfaces shall be password protected to safeguard against unauthorized
use.
It shall perform and report the following minimum sign diagnostics both through the local
interface and Remote Control Subsystem.
• LED brightness controls
• Sign status
• Communications status
• Battery voltage
• Photocell ambient light level.
It shall automatically report a low battery alarm to a remote user through the Remote
Control Subsystem. It shall have an alarm for the controller door open and over
temperature.
It shall store and display both textual and graphical symbols. It shall store a minimum of
20 pre-programmed messages and graphics. It shall display preprogrammed (by
manufacturer) MUTCD symbolic messages and standard arrows. It shall schedule
predetermined sequences of messages based on a programmed time and date. Each
sequence shall display up to four (4) programmed messages (text and/or graphics). It shall
display conventional one, two, or three-line messages for display with a choice of a
minimum of three font sizes. Character width shall be proportional to the letter type. The
one line message font size shall be capable of displaying messages in full size to utilize the
maximum area of display.
It shall allow for automatic and manual controls to adjust the brightness of the LEDs.
Automatic control shall be capable of varying the LED brightness by sensing the ambient
light level using photocells. Manual brightness control shall be password protected to
safeguard against unauthorized use.
It shall display a preprogrammed default message or no message at all, after a power
recovery from a power failure. The sign shall shut down its LED display if internal cabinet
temperatures reach a level that is determined unsafe by the manufacturer.
463
Section 619 Section 619
All communications and power cabling shall be either shielded or routed within conduit to
minimize potential EMI/RFI effects.
Remote Control Subsystem. The PCMS shall be supplied with all the hardware and
software necessary to control the PCMS from a remote central station.
It shall have a cellular phone and/or modem capable of communication using the
Department’s provided cellular service provider. The Contractor shall coordinate with the
Department for a cellular service provider. The Contractor shall be responsible for
establishing cellular service and providing activated phone number(s) as directed and
approved by the Department. The Contractor shall pay for cellular service for this project
until the Final Maintenance Release as documented by the State Construction Engineer at
which time it will be turned over to the Department.
The cellular service type shall be CDMA/1xRTT or GSM/GPRS, as directed by the
Department.
It shall be capable of supporting connection and remote control, programming and
diagnostics via the Internet.
The subsystem shall have all necessary hardware such as external antenna,
communications cables, and controller interface and NTCIP Sign controller software. The
central station software must meet the following minimum requirements:
1) Windows XP compatible
2) Capable of running on any desktop or laptop.
3) Capable of controlling all PCMS functions through windows and GUIs (Graphical
User Interface)
4) NTCIP compatible as specified herein.
Communications. In addition to any protocols that may be available from the PCMS
Manufacturer, each sign controller shall support NTCIP as follows:
• NTCIP Protocol and Command Sets. This specification references several standards
through their NTCIP designated names and numbers. Each NTCIP Component
covered by these specifications shall implement the most recent version of the
standard that is available as of project advertisement date, including any and all
prepared amendments to the standards as of the same date.
Profile Implementation Conformance Specifications (PICS) for each NTCIP
standard required shall be submitted for review and approval to the Department.
• RS-232 Interface. Communication interfaces using RS-232 shall conform with the
following minimum requirements:
1101 – NTCIP Simple Transportation Management Framework (STMF)
1203 - NTCIP Object Definition for Portable Dynamic Message Signs
2301 - NTCIP AP-STMF
2201 - NTCIP TP-Transportation Transport Profile
2103 – NTCIP SPPPP/RS232
2104 - NTCIP SP-PMPP/RS232
464
Section 619 Section 619
• Subnet Level. For each communication interface, the NTCIP Components may
support additional Subnet Profiles at the manufacturer’s option. At any time, only
one Subnet Profile shall be active on a given communication interface. The NTCIP
Component shall be configurable to allow the field technician to activate the desired
Subnet Profile.
• Transport Level. For each communication interface, the communication interface
may support additional Transport Profiles at the manufacturer's option. Response
data-grams shall use the same Transport Profile used in the request. Each
communication interface shall support the receipt of data-grams conforming to any
of the identified Transport Profiles at any time.
• Application Level. For each communication interface, all interfaces shall comply
with NTCIP 1101 and shall meet the requirements for Conformance Level 1 (NOTE
-See Amendment to standard). Optionally, the NTCIP Component may support
SNMP traps. A communication interface may support additional Application
Profiles at the manufacturer's option. Responses shall use the same Application
Profile used by the request. Each communication interface shall support the receipt
of Application data packets at any time allowed by the subject standards.
• Information Level. For all communication interfaces, the information level protocol
shall provide Full, Standardized Object Range Support of all objects required by
these specifications unless otherwise indicated below. The maximum Response
Time for any object or group of objects shall be 200 milliseconds. All
communication interfaces shall implement all mandatory objects of all mandatory
Conformance Groups as defined in NTCIP 1203 and its respective amendments.
Table 1 indicates the modified object requirements for these mandatory objects.
Table 2 shows the required minimum support of messages that are to be stored in
permanent memory. The sign shall blank if a command to display a message
contains an invalid Message CRC value for the desired message. Table 3 specifies
the support of the required MULTI tags and itsranges.
The protocol shall also implement all mandatory objects of the following optional
conformance groups of NTCIP 1201.
o Time Management Conformal Group
o Report Conformal Group. Table 4 indicates the modified object
requirements.
o Implement all objects of the Font Configuration Conformance Group, as
defined in NTCIP 1203. Table 5 indicates the modified object requirements
for this conformance group.
o Implement all objects of the PCMS Configuration Conformance Group, as
defined in NTCIP 1203.
o Implement all objects of the Multi Configuration Conformance Group, as
defined in NTCIP 1203. Table 6 indicates the modified object requirements
for this conformance group.
o Implement all objects of the Multi Error Configuration, as defined in NTCIP
1203.
o Implement all objects of the Illumination/Brightness.
o Sign Status, as defined in NTCIP 1203.
465
Section 619 Section 619
o Status Error, as defined in NTCIP 1203.
o Pixel Error Status, as defined in NTCIP 1203.
o The sign display shall be capable of displaying preprogrammed MUTCD)
symbolic messages and standard arrows. Since the display of graphics is
currently not defined within the NTCIP Standards or its amendments, the
vendor shall propose and provide detailed documentation (i.e., interface
protocol description level) concerning the display of the specified graphical
shapes.
o Implement the optional objects listed in Table 7.
Table 1
Modified Object Ranges for Mandatory Objects
Object Reference Project Requirement
ModuleTableEntry NTCIP 1201
Clause 2.2.3
Shall contain at least one row
with moduleType equal to 3
(software). The moduleMake
shall specify the name of the
manufacturer, the
moduleModel shall specify
the manufacturer's name of
the component and the
modelVersion shall indicate
the model version number of
the component.
MaxGroupAddresses NTCIP 1201
Clause 2.7.1
Shall be at least 1
CommunityNamesMax NTCIP 1201
Clause 2.8.2
Shall be at least 3
PCMSNumPermanentMsg NTCIP 1203
Clause 2.6.1.1.1.1
Shall be at least 20*
PCMSMaxChangeableMsg NTCIP 1203
Clause 2.6.1.1.1.3
Shall be at least 50. Each
message shall support at least
4 pages per message.
PCMSFreeChangeableMemory NTCIP 1203
Clause 2.6.1.1.1.4
Shall be at least 70 when no
messages are stored.
PCMSMessageMultiString NTCIP 1203
Clause
2.6.1.1.1.8.3
The PCMS shall support any
valid MULTI string
containing any subset of those
MULTI tags listed in Table 4.
PCMSControlMode NTCIP 1203
Clause 2.7.1.1.1.1
Shall support at least the
following modes:
local
external
central
centralOverride
466
Section 619 Section 619
Table 2
Content of Permanent Messages
Perm. Msg. Num. Section 12 Description
1 Permanent Message #1 shall blank the display (i.e., command
the sign to use PCMSMessageType 7). It shall have a run-time
priority of 50.
Table 3
Required MULTI Tags
Code Feature
f1 Field 1 - time (12hr)
f2 Field 2 - time (24hr)
f8 Field 8 - day of month
f9 Field 9 – month
f10 Field 10 - 2 digit year
f11 Field 11 - 4 digit year
Fl (and /fl) flashing text on a line by line basis with flash rates controllable in 0.5
second increments.
Fo Font
J12 justification - line – left
J13 justification - line – center
J14 justification - line – right
J15 justification - line – full
Jp2 justification - page – top
Jp3 justification - page - middle
Jp4 justification - page - bottom
Nl New line
Np New page, up to 2 instances in a message (i.e., up to 4 pages/frames
in a message counting first page)
Pt page times controllable in 0.5 second increments.
Table 4
Modified Object Ranges for the Report Conformance Group
Object Reference Project Requirement
maxEventLogConfigs NTCIP 1201 Clause 2.5.1 Shall be at least 50
eventConfigurationMode NTCIP 1201 Clause
2.4.3.1
The NTCIP Component
shall support the following
Event Configuration Modes:
onChange
greaterThanValue
smallerThanValue
maxEventLogSize NTCIP 1201 Clause 2.5.3 Shall be at least 200
maxEventClasses NTCIP 1201 Clause 2.5.5 Shall be at least 16
467
Section 619 Section 619
Table 5
Modified Object Ranges for the Font Configuration Conformance Group
Object Reference Project Requirement
numfont NTCIP 1203 Clause
2.4.1.1.1.1
Shall be at least 3*
maxFontCharacters NTCIP 1203 Clause
2.4.1.1.1.3
Shall be at least 127**
* Upon delivery, the first font shall be a standard 18-inch font. The second font shall
be a double-stroke 18-inch font. The third font shall be a 28-inch font.
** Upon delivery, the first three font sets shall be configured in accordance with the
ASCII character set for the following characters:
"A" thru "Z" - All upper case letters.
"a" thru "z" - All lower case letters.
"0" thru "9" - All decimal digits.
Space (i.e., ASCII code 0x20).
Punctuation marks shown in brackets [. , ! ? - ‘ ’ “ ” / ( )]
Special characters shown in brackets [# & * + < >]
Table 6
Modified Object Ranges for the MULTI Configuration Conformance Group
Object Reference Project Requirement
defaultBackgroundColor NTCIP 1203 Clause
2.5.1.1.1.1
The PCMS shall support
the following background
colors:
black
defaultForegroundColor NTCIP 1203 Clause
2.5.1.1.1.2
The PCMS shall support
the following foreground
colors:
amber
orange
defaultJustificationLine NTCIP 1203 Clause
2.5.1.1.1.6
The PCMS shall support
the following line
justification:
Left
Center
Right
Full
defaultJustificationPage NTCIP 1203 Clause
2.5.1.1.1.7
The PCMS shall support
the following forms of
page justification:
Top
Middle
Bottom
468
Section 619 Section 619
defaultPageOnTime NTCIP 1203 Clause
2.5.1.1.1.8
The PCMS shall support
the full range of these
objects with step sizes no
larger than 0.5 seconds
defaultPageOffTime NTCIP 1203 Clause
2.5.1.1.1.9
The PCMS shall support
the full range of these
objects with step sizes no
larger than 0.5 seconds
defaultCharacterSet NTCIP 1203 Clause
2.5.1.1.1.10
The PCMS shall support
the following character
sets:
eightBit
Table 7
Optional Object Requirements
Object Reference Project Requirement
globalSetIDParameter NTCIP 1201
Clause 2.2.1
eventConfigLogOID NTCIP 1201
Clause 2.5.2.7
eventConfigAction NTCIP 1201
Clause 2.5.2.8
eventClassDescription NTCIP 1201
Clause 2.5.6.4
defaultFlashOn NTCIP 1203
Clause
2.5.1.1.1.3
The PCMS shall support the
full range of these objects
with step sizes no larger
than 0.5 seconds
defaultFlashOff NTCIP 1203
Clause
2.5.1.1.1.4
The PCMS shall support the
full range of these objects
with step sizes no larger
than 0.5 seconds
PCMSSWReset NTCIP 1203
Clause
2.7.1.1.1.2
PCMSMessageTimeRemaining NTCIP 1203
Clause
2.7.1.1.1.4
PCMSShortPowerRecoveryMessage NTCIP 1203
Clause
2.7.1.1.1.8
PCMSLongPowerRecoveryMessage NTCIP 1203
Clause
2.7.1.1.1.9
PCMSShortPowerLossTime NTCIP 1203
Clause
2.7.1.1.1.10
469
Section 619 Section 619
PCMSResetMessage NTCIP 1203
Clause
2.7.1.1.1.11
PCMSCommunicationsLossMessage NTCIP 1203
Clause
2.7.1.1.1.12
PCMSTimeCommLoss NTCIP 1203
Clause
2.7.1.1.1.13
PCMSEndDurationMessage NTCIP 1203
Clause
2.7.1.1.1.15
PCMSMemoryMgmt NTCIP 1203
Clause
2.7.1.1.1.16
The PCMS shall support
the following Memory
management Modes:
normal
clearChangeableMessage
clearVolatileMessages
PCMSMultiOtherErrorDescription NTCIP 1203
Clause
2.7.1.1.1.20
If the vendor implements
any vendor-specific MULTI
tags, the PCMS shall be
provided with
documentation that includes
meaningful error messages
within this object whenever
one of these tags generates
an error.
PCMSIllumLightOutputStatus NTCIP 1203
Clause
2.8.1.1.1.9
watchdogFailureCount NTCIP 1203
Clause
2.11.1.1.1.5
PCMSStatDoorOpen NTCIP 1203
Clause
2.11.1.1.1.6
fanFailure NTCIP 1203
Clause
2.11.2.1.1.8
fanTestActivation NTCIP 1203
Clause
2.11.2.1.1.9
tempMinCtrlCabinet NTCIP 1203
Clause
2.11.4.1.1.1
tempMaxCtrlCabinet NTCIP 1203
Clause
2.11.4.1.1.2
470
Section 619 Section 619
tempMinSignHousing NTCIP 1203
Clause
2.11.4.1.1.5
tempMaxSignHousing NTCIP 1203
Clause
2.11.4.1.1.6
NTCIP Compliance Documentation. Software shall be supplied with full documentation,
including a CD-ROM containing ASCII versions of the following Management
Information Base (MIB) files in Abstract Syntax Notation 1 (ASN.1) format.
functionality shall be included. If the device does not support the full range of any
given object within a Standard MIB Module, a manufacturer specific version of the
official Standard MIB Module with the supported range indicated in ASN.1 format
in the SYNTAX and/or DESCRIPTION fields of the associated OBJECT TYPE
macro shall be provided. The filename of this file shall be identical to the standard
MIB Module, except that it will have the extension ".man".
supported by the device with accurate and meaningful DESCRIPTION fields and
supported ranges indicated in the SYNTAX field of the OBJECT-TYPE macros shall
be provided. This includes a MIB containing any other objects supported by the
device.
the NTCIP compliance of both, the data dictionaries (NTCIP 1201, 1203, and their
amendments) and the communications protocols have been tested. The manufacturer
shall allow the use of any and all of this documentation by any party authorized by
the Department for systems integration purposes at any time initially or in the future,
regardless of what parties are involved in the systems integration effort.
.14.7--Operational Security. The Contractor shall change the manufacturer’s
default passwords for all levels of access. The passwords for each level of access shall be
different. The individual passwords shall be at least eight (8) characters in length, contain
both upper and lowercase alphabetic characters (A-Z, a-z), have at least one (1) numerical
character (0-9), and have at least one (1) special character (~!@#$%^&*()_-+=). The
passwords shall not 1) spell a word or series of words that can be found in a standard
dictionary, 2) spell a word with a number added to the beginning and the end, or 3) be
based on any personal information such as user id, family name, pet, birthday, etc. The
Contractor shall provide the Project Engineer will a listing of all passwords for each PCMS
prior to the PCMS being placed on the project. If multiple PCMS are used on a project,
they shall each have distinct passwords.
.14.8--Additional Equipment Requirements. When the contract requires the
PCMS to include a speed radar unit, the radar shall operate in the "K" band, in an "approach
only" mode. In conjunction with the radar, the sign shall be capable of displaying the
vehicle speeds. The unit shall be programmable to allow the interruption of user-defined
messages by the vehicle speed display and/or alternate messages whenever a settable speed
threshold is exceeded. The radar unit shall be encased in an aluminum enclosure with a
polycarbonate lens, and the metal portion shall receive the same protective coating,
priming, and painting as the rest of the sign.
471
Section 619 Section 619
.14.9--System Documentation. For each PCMS, the Contractor shall provide two
functions, software required to operate the sign on site and remotely, all wiring diagrams,
a parts lists, the sign specifications, warranty information, maintenance information and
schedule, and a trouble shooting table.
Each copy shall be bound and shall contain laminated sheets.
.15--Glare Paddles. Glare paddles shall be those listed on the Department's APL"
619.03Construction Requirements
.1--General. Traffic control devices shall be furnished and utilized in accordance
with the Traffic Control Plan (TCP) as referenced in Section 618. Upon failure of the
Contractor to adequately maintain traffic control devices and safe movement of traffic
through the construction zones, the provisions of Subsection 105.15 will be invoked.
.2--Temporary Stripe. Temporary stripes are pavement markings, temporary in
nature, that are used to direct traffic from its customary path, to be removed from the
pavement course under use for further temporary traffic control, to be covered by the next
pavement course and/or to be replaced by permanent stripes. Temporary stripes shall be
4-inch paint or preformed tape as designated on the plans or when not designated, the use
of paint or tape will be at the Contractor's option. Temporary stripes on surface treatments
shall be paint.
All temporary stripe shall be placed in accordance with the plans and the requirements set
out in Section 625, except that alignment of temporary stripe placed on underlying courses
shall have a tolerance of four inches in fifty (50) feet from true alignment for skip stripes
and edge lines and one inch in fifty (50) feet from true alignment for no-passing stripes and
lane lines. When preformed tape is used on the final pavement course for temporary traffic
markings, it shall be removed at no additional cost to the State.
Temporary paint stripe requiring removal shall be removed by carefully controlled blast
cleaning, approved grinding or other approved methods in such a manner that the surface
to which the stripe is applied will not be unnecessarily marred or damaged. Preformed tape
is to be removed in accordance with the manufacturer's recommendations.
Temporary paint stripe placed on the final pavement course may be left in place and
covered with permanent stripe of the same color provided the temporary stripe has been
satisfactorily placed in the proper location. Under this condition, any remaining temporary
paint stripe not covered by the permanent stripe shall be removed at no additional cost to
the State.
Painted traffic stripe removed from the final asphalt pavement surface shall be sealed with
an approved sealant. The Engineer may wave the sealant requirement when the area to be
sealed is insignificant. This sealing operation shall be performed at no additional costs to
the State.
All temporary pavement markings placed and measured for payment under this section
472
Section 619 Section 619
shall include any required removal. Removal of all temporary stripe will not be measured
for separate payment.
Existing pavement markings conflicting with temporary markings shall be removed.
Removal of such materials (paint, tape, marker, etc.) will be measured and payment made
under Section 202. When measuring removal of pavement markings for payment, the skips
will not be included in the measurement.
.3--Portable Traffic Signals
.3.1--Installation. The Contractor shall be responsible for placing the portable
traffic signal(s) in the appropriate location based as shown in the plans and meeting the
MUTCD and ITE standards for visibility to motorists and for safe operation.
The Contractor shall be responsible for providing all hardware, software, communications
equipment and licenses to operate a complete system. All equipment shall be installed
according to the manufacturer's recommendations.
The Contractor shall be responsible for transport, setup, configuration, operation and
monitoring of the portable traffic signals throughout the entire project. The Engineer shall
approve all timing and settings that are used for operation of the signal.
It may be necessary to relocate the portable traffic signals during the project. The cost of
the relocation shall be included in the lump sum price bid.
.3.2--Conformance / Testing. Each portable traffic signal shall undergo testing to
verify conformance with this specification. The Contractor shall conduct a Project Testing
Program as required below. All costs associated with the Project Testing Program shall be
included in overall contract prices; no separate payment will be made for any testing.
.3.2.1--General Requirements. This work shall meet the following general
requirements.
1) The Contractor is responsible for planning, coordinating, conducting and
documenting all aspects of the Project Testing Program. The Project Engineer
and/or their designee(s) are only responsible for attending and observing each test,
and reviewing and approving the Contractor's test results documentation. The
Project Engineer and/or their designee(s) reserve the right to attend and observe all
tests.
2) Each test shall fully demonstrate that the equipment being tested is clearly and
definitely in full compliance with all project requirements.
3) Test procedures shall be submitted and approved for each test as part of the project
submittals. Test procedures shall include every action necessary to fully
demonstrate that the equipment being tested is clearly and definitively in full
compliance with all project requirements. Test procedures shall cross-reference to
these specifications or the project plans. Test procedures shall contain
documentation regarding the equipment configurations and programming.
4) No testing shall be scheduled until approval of all project submittals and approval
of the test procedures for the given test.
5) The Contractor shall provide all ancillary equipment and materials as required in the
approved test procedures.
473
Section 619 Section 619
6) The Contractor shall request in writing the Project Engineer’s approval for each test
occurrence a minimum of 14 days prior to the requested test date. Test requests
shall include the test to be performed and the equipment to be tested. The Project
Engineer reserves the right to reschedule test request if needed.
7) All tests shall be documented in writing by the Contractor in accordance with the
test procedure and submitted to the Project Engineer within seven (7) days of the
test. Any given test session shall be considered incomplete until the Project
Engineer has approved the documentation for that test session.
8) All tests deemed by the Project Engineer to be unsatisfactorily completed shall be
repeated by the Contractor. In the written request for each test occurrence that is a
repeat of a previous test, the Contractor shall summarize the diagnosis and
correction of each aspect of the previous test. The test procedures for a repeated test
occurrence shall meet all the requirements of the original test procedures, including
review and approval by the Project Engineer.
9) The satisfactory completion of any test shall not relieve the Contractor of
responsibility to provide a completely acceptable and operating system that meets
all requirements of this project.
.3.2.2--Portable Traffic Signal Pre-Installation Test (PIT). The Contractor shall
perform PIT on the portable traffic signals units as they arrive from the factory. The goal
of the PIT is to verify that the portable traffic signals were not damaged during shipping
and that all components are working.
.3.2.3--Portable Traffic Signal Stand Alone Test (SAT). The Contractor's
comprehensive SATs for the portable traffic signals shall be completed once the signal has
been location on the site where it will be utilized. The SAT shall be sufficient to
demonstrate compliance with all requirements specified herein.
.3.3--System Maintenance and Support. The portable traffic signal(s) shall be
maintained and supported by the Contractor throughout the duration of the project. The
Contractor shall provide MDOT with a 24/7 contact to respond to any issues and shall be
required to respond within two (2) hours to any call from the Engineer or designated
representative concerning any request for correcting any deficiency in the signal system.
Equipment damaged or otherwise not functioning shall be repaired or replaced immediately
upon notification by MDOT. Sufficient spare parts to repair common components of the
portable traffic signal such as heads, controller, load switch, relays, etc. shall be available
on site. All equipment installation, service, repair, relocation and removal are the
responsibility of the Contractor.
.3.4--System Documentation. For each type signal, the Contractor shall provide
the Engineer with a user manual. The user manual shall include description and samples
for all operational functions, software required to operate the signal on site and remotely
(if applicable), all wiring diagrams, a parts lists, the signal specifications, maintenance
information and schedule, and a trouble-shooting guide.
.4--Reflective Pavement Markers. Reflective pavement markers for construction
zones shall be secured to the pavement by an approved adhesive. The portion of the
highway surface to which the marker is to be bonded shall be free of dirt, grease, oil,
moisture, loose or unsound layers and any other material that would adversely affect the
bond of the adhesive. Clean pavement need not be blast-cleaned unless the surface contains
an abnormal amount of asphalt or the surface is contaminated with dirt, grease, oil, or any
474
Section 619 Section 619
other material that would adversely affect the bond of the adhesive. Necessary cleaning
shall be performed by blast cleaning.
When a pressure-sensitive pad is used, a primer shall be applied directly to the road surface
with a brush or sprayer but is not to be applied when the ambient temperature is lower than
50°F. No marker shall be installed when the relative humidity of the air is greater than 80
percent or when the pavement is not surface dry. Traffic shall not be permitted to run over
the primed area until after the markers have been installed. After priming, allow one
minute for the primer to dry, then peel the release paper from the pressure-sensitive pad
and immediately place the marker in the correct position on the primed road surface and
apply light pressure. Drive slowly over the located marker with one wheel of a truck to
help set it in place. Traffic may be allowed immediately.
All markers shall be installed in a uniform line, with controls established by the Engineer.
The Engineer will establish controls for each line of markers by setting control points at
not less than approximately 600-foot intervals on tangents and 50-foot intervals in curves.
All additional work necessary to establish intermediate control points and individual
marker points shall be performed by the Contractor. On curves, the line of markers on lane
lines and edge lines shall follow the normal curvature of the curve and placement on chords
or other variations from the normal curvature will not be permitted, unless specifically
shown on the plans or ordered by the Engineer.
Reflective markers shall be installed in such a manner that the reflective face of the marker
is perpendicular to a line parallel to the roadway centerline. No markers shall be installed
over longitudinal or transverse joints of the pavement surface.
All markers placed out of alignment shall be removed and replaced by a new marker.
.5--Impact Attenuators. Impact attenuators shall be installed and maintained by
experienced workmen familiar with the installation of impact attenuators. Installation shall
be in accordance with the recommendations of the manufacturer. Each impact attenuator
shall also include one replacement package. A replacement package shall consist of the
quantity of materials necessary to repair one hit for every three attenuators in place. The
Contractor shall use these parts to maintain the attenuator during the construction period.
When it becomes necessary to install a replacement package, the Contractor shall order an
additional replacement package to have available for future use. All unused parts and the
attenuators shall become the property of the Contractor upon completion of the project.
.6--Temporary Guardrail. Temporary guardrail shall be installed in accordance
with the plans and the applicable provisions of Section 606.
The sites where temporary guardrail has been removed shall be restored to their original
condition or as provided in the contract documents.
Salvage of temporary guardrail designated to become the property of the Department shall
be in accordance with Subsection 202.03.
.7--Maintenance of Traffic Signs. All signs, whether placed new or previously
used, shall meet the requirements of this specification on each inspection. Signs failing to
comply with these requirements shall be replaced at no additional cost to the State.
475
Section 619 Section 619
.8--Snap-Back Delineators. Snap-back delineators shall be installed in accordance
with the manufacturer's recommendations and at the locations shown on the plans or
directed by the Engineer. Delineators that are damaged by traffic to the extent that they
are non-functional shall be replaced as quickly as possible.
.9--Portable Median Barrier. Portable median barriers shall be installed in
accordance with the manufacturer’s recommendations. The barriers shall be installed at
the locations shown on the plans, or as directed by the Engineer.
.10--Changeable Message Sign. Each changeable message sign shall be installed
and continuously operated at the location selected by the Engineer on State right-of-way.
The Contractor is advised that selected locations may be outside the planned limits of the
project. The Contractor shall perform all work necessary for preparation of the site selected
and approved by the Engineer, to ensure maximum safety and sign visibility for the
traveling public and may be required to remove any temporary work at a later date as
directed by the Engineer. The Contractor will also place a minimum of two plastic drums
in advance of the sign and one beside the sign as long as it is in use. The Contractor shall
be required to move the sign to a new location if directed by the Engineer.
The Contractor may be permitted to bring electric power from outside the normal right-of-
way for operation of the equipment if the Department determines that the installation
operation will not be hazardous to the traveling public. The Contractor will be required to
secure a permit from the Department prior to any work by the power company on the right-
of-way. The entire cost of providing electrical service, power to operate the equipment,
and removal of the power source from the right-of-way shall be borne by the Contractor.
The changeable message sign(s) will remain the property of the Contractor after the
Engineer determines that there is no further need for the sign(s) on the project.
.11--Glare Paddles. Glare paddle installation shall consist of furnishing, installing,
maintaining, removing and relocating glare paddles as required. Glare paddles shall be
placed atop precast median barriers, or other devices, at locations shown in the plans, or as
directed by the Engineer.
The paddles shall be six to nine inches (6" to 9") in width, 24 to 36 inches in height, and
spaced a maximum of 24 inches apart. The paddles shall be attached to the top of the
devices in accordance with manufacturer’s recommendations at a 22 degree angle. A
yellow high-intensity reflective strip shall be attached vertically to each side of one of the
paddles such that the spacing is 10 feet apart. Unless otherwise directed, these strips shall
be placed on the edge of the paddle adjacent to traffic. These reflective strips shall be made
of 2-inch by 12-inch material conforming to the requirements of Subsection 721.06 of the
Standard Specifications.
All glare paddles shall be properly maintained. Maintenance will include replacement of
damaged or missing blades, improper reflectorization, and any other portions of the
installation that may fail, for the entire length of time that the paddles are in place. Cleaning
of the reflective material shall be accomplished by any means that does not damage the
paddles and in a manner that is not hazardous to traffic. Cleaning shall be accomplished
on an as-needed basis or as ordered by the Engineer.
476
Section 619 Section 619
The Contractor shall relocate the glare paddles as required during construction at no
additional cost to the State.
After completion of the work, glare paddles and attachments shall remain the property of
the Contractor.
619.04Method of Measurement. Traffic control devices will be measured one time only
by the units indicated. When moved from the original location to other locations, as
required by the contract or as directed by the Engineer, traffic control devices will not be
measured for additional payment except when the contract includes the pay item, "Remove
and Reset". The total pay quantity for each traffic control device excluding traffic stripe
shall not exceed the maximum number of installations in place at any given time during
the life of the contract. Unless otherwise provided, replacement of devices will not be
measured for payment.
Temporary stripe, completed and removed in accordance with the requirements of this
Section, will be measured by the mile or by the linear foot, as indicated, from end-to-end
of individual stripes. In the case of skip lines, the measurement will include skips. The
length used to measure centerline, lane lines and edge stripes will be the horizontal length
computed along the stationed control line. Detail traffic stripe will be measured by the
linear foot from end-to-end of individual stripes. Measurement will be made along the
surface of each stripe and will exclude nominal skip intervals where specified. Stripes
more than four inches in width will be converted to equivalent lengths of four-inch stripe.
Legend, which is to include railroad markings, pedestrian crosswalks and stop lines, will
be measured by the square foot or linear foot. Pay areas of individual letters and symbols
will usually be shown on the plans and measured by the square foot. Transverse railroad
bands, pedestrian crosswalks and stop lines will generally be measured by the linear foot,
and stripes more than four inches in width will be converted to equivalent lengths of four-
inch widths.
Each impact attenuator installation, including one replacement package, will be measured
per each installation as shown on the plans. Replacement packages, excluding the package
included with the initial attenuator, will be measured per each in accordance with these
specifications.
Initial snap-back delineators will be measured per each. Replacement will be measured as
follows:
Changeable message signs, as described above, will be measured per each. When directed,
separate measurements will be made for items included in the contract and required for
temporary site preparation for the sign as referenced in Subsection 619.03.10. Materials
for which no pay items are included in the contract will not be measured for separate
payment. Separate measurements will not be made for moving the changeable message
sign to a new location, but materials used for which pay items are included in the contract
and are necessary for repositioning the sign as directed by the Engineer will be measured
477
Section 619 Section 619
for separate payment. Removal of materials used for site preparation for changeable
message signs will not be measured for separate payment.
Portable traffic signals of the type specified will be measured per each.
The lengths of median barrier, including remove and reset median barrier, will be measured
per linear foot by multiplying the number of commercial lengths installed by the nominal
length of the barrier.
619.05Basis of Payment. Traffic control devices will be paid for at the contract unit
price for the units specified. Devices that have been measured for payment and
subsequently require repair or replacement will be dropped from payment on future
estimates unless satisfactorily repaired or replaced.
Payment for devices for which no pay items are contained in the contract will be included
in the unit prices of contract items and/or in the lump sum contract price for Maintenance
of Traffic.
Payment for items required by the Engineer for temporary location of the changeable
message sign, and for which pay items are included in the contract, will be made by the
individual pay item. No additional payment will be made for working outside the planned
indicated project limits.
Payment for removal of materials used for site preparation at changeable message sign
locations shall be included in the contract price for Maintenance of Traffic.
Portable traffic signals of the type specified will be paid for at the contract unit price per
each, which price shall be full compensation for furnishing, installing, testing, operating,
relocating a complete portable traffic signal as required, integration, configuration, and all
other materials, equipment, labor, tools and incidentals necessary to complete the work.
The prices thus paid shall be full compensation for completing the work.
Payment will be made under:
619-A1: Temporary Traffic Stripe, Continuous White,
Description * - per linear foot or mile
619-A2: Temporary Traffic Stripe, Continuous Yellow,
Description * - per linear foot or mile
619-A3: Temporary Traffic Stripe, Skip White,
Description* - per linear foot or mile
619-A4: Temporary Traffic Stripe, Skip Yellow,
Description* - per linear foot or mile
619-A5: Temporary Traffic Stripe, Detail, Description* - per linear foot
619-A6: Temporary Traffic Stripe, Legend, Description* - per square foot
or linear foot
478
Section 619 Section 619
619-B: Blank
619-C1: Red-Clear Reflective Raised Pavement Marker - per each
619-C2: Two-Way Yellow Reflective Raised Pavement Marker - per each
619-C3: One-Way Clear Reflective Raised Pavement Marker - per each
619-C4: One-Way Yellow Reflective Raised Pavement Marker - per each
619-C5: Yellow Clear Reflective Raised Pavement Marker - per each
619-C6: Red-Clear Reflective High Performance Raised Marker - per each
619-C7: Two-Way Yellow Reflective High Performance Raised
Marker - per each
619-C8: One-Way Clear Reflective High Performance Raised
Marker - per each
619-C9: One-Way Yellow Reflective High Performance Raised
Marker - per each
619-C10: Yellow Clear Reflective High Performance Raised Marker - per each
619-D1: Standard Roadside Construction Signs, Less than
10 Square Feet - per square foot
619-D2: Standard Roadside Construction Signs,
10 Square Feet or More - per square foot
619-D3: Remove and Reset Signs, All Sizes - per each
619-D4: Directional Signs - per square foot
619-D5: Directional Signs, Overhead, Location - lump sum
619-E1: Flashing Arrow Panel, Type____ - per each
619-E2: Sequencing Chevron Panel, Size - per each
619-E3: Changeable Message Sign ***** - per each
619-F1: ** Median Barrier, *** - per linear foot
619-F2: Remove and Reset ** Median Barrier, *** - per linear foot
619-F3: Delineators, Mounting, Description - per each
619-F4: Snap-Back Delineator - per each
479
Section 619 Section 619
619-F5: Snap-Back Delineator, Replacement - per each
619-G1: Blank
619-G2: Barricades, Type I - per each
619-G3: Barricades, Type II - per each
619-G4: Barricades, Type III, **** - per linear foot
619-G5: Free Standing Plastic Drums - per each
619-G6: Warning Lights, Type A - per each
619-G7: Warning Lights, Type B - per each
619-G8: Warning Lights, Type C - per each
619-H1: Traffic Signal, Location - lump sum
619-H2: Traffic Signal, Portable, Type ___ - per each
619-H3: Hazard Identification Beacons - lump sum
619-J1: Impact Attenuator, Speed Rating - per each
619-J2: Impact Attenuator, Speed Rating, Replacement Package - per each
619-J3: Remove and Reset Impact Attenuator ***** - per each
619-K1: Installation and Removal of Guardrail, Type____,
Class____ - per linear foot
619-K2: Installation and Removal of Guardrail, Type____
Bridge End Section - per each
619-K3: Installation and Removal of Guardrail, Type____
Cable Anchorage - per each
619-K4: Installation and Removal of Guardrail, Terminal
End Section - per each
619-L: Glare Paddles - per linear foot
* The description for temporary traffic stripe will be shown as "paint" or "tape.”
In the case of "tape" the type will also be designated. When the description is
not designated, the use of "paint" or "tape" will be at the Contractor's option.
** Indicate Concrete or Portable
*** Indicate Speed Rating, Color, etc. if applicable
**** Indicate if barricade is to remain with “Permanent”
***** Indicate when options are required 480
Get an email when 619 changes
Mississippi revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.