553.01 Description
This work is the furnishing and placing of precast, prestressed concrete beams, slabs, piling, and other structural members.
553.02 Materials
553.02.1 Concrete
Furnish concrete in accordance with Section 551.
553.02.2 Reinforcing Steel
Furnish reinforcing steel in accordance with Section 555 and Subsection 711.01.1. Obtain the Project Manager’s written approval for reinforcing steel substitutions. State on the fabrication drawings showing reinforcing steel details the following or similar words: “All dimensions are out-to-out”.
553.02.3 Steel Rods and Bolts Furnish rods used as dowels and bolts in accordance with
Subsection 711.07.
553.02.4 Prestress Steel
Furnish high tensile strength steel wire in accordance with Subsection 711.11. Furnish the typical load-elongation curves for all shipments of prestress steel to the fabrication plant. Ensure all prestress steel used in the work is free of rust, corrosion, dirt, oil, spatter from welding or flame cutting, kinks, bends, nicks, broken wires, or other defects. Prestress steel is sampled in accordance with MT 111.
553.02.5 Enclosures
Use metallic enclosures, excluding aluminum, or forms using removable cores or ducts made of rubber or other approved material. Remove cores and ducts before installing the prestress steel. Use enclosures that are mortar tight and maintain their shape when subjected to loading. Use enclosures that are ¼-inch (6 mm) larger in internal diameter than the bar, cable, strand, or group of wires being enclosed. Equip cores or ducts with pipes or other connections for grout injection when pressure grouting is specified.
553.02.6 Structural Steel
Furnish structural steel in accordance with Subsection 711.02.
553.02.7 Elastomeric Bearing Devices
Furnish elastomeric bearing devices in accordance with Subsection 711.14.
553.02.8 Fiber Reinforced Pads for Bearing Plates
Furnish fiber reinforced pads in accordance with Subsection 711.16.
553.02.9 Deck Sealer
Furnish deck sealer for precast prestressed deck sections which is listed on the QPL and in accordance with Subsection 717.02. 553 – PRESTRESSED CONCRETE MEMBERS 2020 EDITION V5.1 553-2
553.02.10 Leveling Inserts
Furnish Leveling inserts for precast prestressed deck sections designed for a minimum working tension of 5,500 lbs. (24.4 kN) and have machine threaded ferrules. Use ¾-inch (19 mm) minimum diameter structural connection type leveling inserts.
553.03 Construction Requirements
553.03.1 Fabrication
Fabricate all prestressed concrete members using a manufacturing plant currently certified by the Prestressed Concrete Institute in the category applicable to the member being fabricated. The Department will make an exemption for new manufacturing plants that are of the same ownership as an existing certified plant, provided the new manufacturing plant operates under the same quality assurance and control programs as the certified plants, modified to address any production differences, and all fabrication is performed under the direct supervision of a quality assurance and control manager provided by an existing pre-qualified plant. Direct supervision means that the quality assurance and control manager is on site during all fabrication performed in the new fabrication plant and is responsible for the quality assurance and control activities. Furnish a copy of the plant’s current certification in the applicable category along with the fabrication drawings for the elements to be fabricated. For new manufacturing plants, submit and receive approval of any proposed modifications to the parent plant’s quality assurance and control program prior to beginning production. Allow 30 business days from the date submitted for Department review and approval. New manufacturing plants may operate under the parent plant’s quality assurance and control programs for a maximum of 18 months from the date of opening. Plants currently operating under this exemption may do so only until January 1, 2016. The fabricator may prestress by pretension or post-tensioning the member, subject to the contract requirements. Obtain written approval before changing the prestressing details.
553.03.2 Fabrication Drawings
Before casting members, submit fabrication drawings and designs calculations. Show complete details of the method, materials, and equipment proposed for use in prestressing. Include in the fabrication drawings the following information:
556.03.1 and 556.03.10
; and
553.03.3 Design of Concrete Mixtures
The prestressed girder concrete must have a minimum ultimate compressive strength of 4,000 psi (27.6 MPa) at transfer of prestress and 5,000 psi (34.5 MPa) at 28 days. The actual required strengths are specified in the contract. Furnish a concrete mix design that produces concrete meeting the specified compressive strengths before use. Approved changes to the mix design may be permitted during fabrication. Use a concrete design of between 6.5 to 8.0 sacks of cement per cubic yard (350 - 450 kg/m
553.03.4 Forms
Use steel side and bottom forms. End bulkhead forms may be steel or plywood. Form joints and strand exits through bulkhead forms that are mortar tight. Check the grade and alignment of side forms before casting. Check the beam bed alignment for displacement while placing the concrete. 553 – PRESTRESSED CONCRETE MEMBERS 2020 EDITION V5.1 553-4 Construct beam bed forms to limit movement to not exceed ¼-inch (6 mm) from a straight line in any 50-foot (15.25 m) length of the bed. Use clean forms that are free from warp, bulge, and other defects. Do not exceed a maximum offset of 1⁄16-inch (2 mm) where form sections are joined. Treat the form facing with a bond breaker before each casting. Form treating materials that stain or react with concrete are not permitted. Apply form oil or other bond breaker materials without contaminating the prestress strand and reinforcing steel. Clean soiled strand or reinforcing with a non-contaminating solvent. Chamfer all exposed concrete edges, excluding the beam top, with an enclosed angle of less than 120°. Use chamfer strips having no irregularities and maintain smooth joints with the chamfer tightly fitted against abutting forms. Fit forms with a grade strip or other positive control to establish the nominal depth of the beam. Use forms that can be removed from the member without damaging the concrete. Identify production form dimensions that vary from the contract beam dimensions on the fabrication drawings.
553.03.5 Placing Reinforcing Steel
Place and secure all reinforcing steel as shown in the contract before placing concrete. Fasten all bars at all intersections with adjacent bars. Do not tack weld reinforcing steel if the reinforcing bar is a stress-carrying member. Welding non-stress reinforcing bars may be permitted with the Engineer’s approval. Reinforcing steel welds not shown on the approved tacking detail or fabrication drawings are prohibited. For convenience, additional reinforcing steel may be tied in for securing inserts, void ducts, etc., or may be secured by tack welding. Protect the tensioning strand from weld spatter using wet burlap or other protective covering. Replace all strands with weld spatter at Contractor expense. Provide the distance between the reinforcing and side forms using approved stays, ties, or chairs. Do not use precast mortar blocks, pebbles, pieces of broken stone or brick, metal pipe, or wooden blocks. Provide clearance between the beam stirrups and the beam bed using metal chair supports with stainless steel or other approved, corrosion-resistant legs. Use reinforcing steel in the ends of prestressed beams to provide clearance for the paving notch block out, void ducts, embed plates and anchorages, and inserts without interfering with the reinforcement spacing. Reinforcement in the prestressed member will be inspected in place and approved by the Inspector before the concrete is placed. Concrete placed before inspection may be rejected.
553.03.6 Prestressing Equipment
Use approved jacking equipment for prestressing. Equip hydraulic jacks with pressure gauges. Have a certified testing laboratory calibrate each jack and gauge combination as a unit with the cylinder extension in the approximate position that it will be in at the final jacking force. Have a certified calibration chart for each jack. Other types of jacks may be used with proving rings or other approved devices calibrated by a qualified testing laboratory. 2020 EDITION V5.1 PRESTRESSED CONCRETE MEMBERS – 553 553-5 Calibrate jacking equipment once each year and after each repair. Re-calibration may be required if any jack or gauge gives erratic results or if the difference between the gauge reading and elongations exceed allowable limits. Equip tensioning systems with hydraulic gauges that prevent the gauge pointer from fluctuating until the jacking load is released from the tendon. The gauge must read loads directly in pounds (Newtons) or have a chart to convert the dial reading into pounds (Newtons). Ensure the gauge readings are accurate to within ± 2%. Locate the gauges to provide the operator and Inspector a clear view of elongation measurements and gauge readings. Use gauge dials graduated in increments not exceeding 100 pounds (700 kPa) pressure. The gauge range or load cells must not use the lower 10% of the manufacturer’s rated capacity in determining the jacking stress, unless calibration data establishes accuracy within the 2% requirement at the lower range. Ensure the end anchorages and prestressed member stressing blocks can maintain the required tension in all prestressed tendons until the concrete has been placed and reached transfer strength. Equip the end anchorages and stressing blocks to detect deflection while prestressing. The Inspector will check for deflection. Provide the equipment to determine concrete compressive strengths at the location the prestressed members are manufactured. The test equipment may be mechanical or hydraulic, capable of applying and measuring the required load. Error for loads within the loading range of the test equipment may not exceed an error of ± 1.5%. Have a certified calibration diagram covering the entire use range with the equipment at all times. The indicated load of the testing equipment does not have to be corrected by calculation or by the calibration diagram to obtain values when the values are within the required variation of + 1.5%. Certify the concrete strength testing equipment every 2 years; after each repair or adjustment of the equipment; when a non-portable machine has been moved; and whenever accuracy is in question.
553.03.7 Pre-tensioning
Hold the prestressing elements in position using jacks when stressing. Keep a record of the jacking force and the elongations. Multiple units may be cast in a continuous line and stressed at one time. Leave a space between the ends of the units to permit cutting of the strands. Furnish strand in coils, reel-less packs, or on reels. Stringing may be performed by pulling single or multiple strands. Pull to gradually relieve strand rotation on coil or reel-less packs. Strand with gripped points are not permitted within the lengths to be stressed. Bring all prestress tendons to the uniform initial tension on the approved fabrication drawings. Initial tension is the minimum force required to equalize stresses and eliminate slack in the strand. Submit alternate initial loading proposals for approval. The initial load may be applied by the jack used for single strand tensioning or by any other approved method that provides a definite, uniform load. Regardless of the method used, measure the initial load within ± 100 pounds (450 N). Compute elongation measurements for initial tensioning but do not use as a measurement of the initial force. Once initial tensioning is complete, reference mark the strand as directed. The mark must provide an accurate measurement of elongation by final tensioning. Measure the induced stress by gauge and check it by elongation, load cell, or both. The results must agree within 5%. Do not permit jacking stress to exceed 75% of the specified minimum ultimate tensile strength of the prestressing steel. Measure the strand elongation to 553 – PRESTRESSED CONCRETE MEMBERS 2020 EDITION V5.1 553-6 within 1% of the theoretical elongation or ⅛-inch (3 mm), whichever is smaller. If a discrepancy between measured elongations and gauge readings exceeds 5%, check and correct the entire operation before proceeding with the work. All uplift devices, hold-down devices, and strand openings in end bulkheads must have rounded, smooth surfaces at all contact points with the strand. Take gauge readings, elongation measurements, and make calculations for elongation and include allowances for operational losses for the tensioning system used. These allowances must include losses for strand slippage, anchor movement, friction, strand rotation, and other forces acting on the strand. If the temperature difference between the strand at the time of tensioning and the concrete at the time of pouring exceeds 30 °F (16 °C), correct the computed elongation measurements for the temperature differences. Provide the elongation calculations to fabrication and inspection personnel at the beginning of production to ensure all allowances for the method of tensioning have been considered.
553.03.8 Final Tensioning
553.03.9 Placing Concrete
553.03.10 Curing
Water-cure or steam-cure prestressed concrete members in accordance with Subsection
551.03 7
. 2020 EDITION V5.1 PRESTRESSED CONCRETE MEMBERS – 553 553-9
553.03.11 Transfer of Prestress
Prestressed strands may be released when the concrete has:
553.03.12 Post-tensioning
Begin tensioning of the prestress reinforcing steel when the concrete cylinders representing the member to be prestressed reach the compressive strength shown on the approved fabrication drawings. Stress the prestress reinforcing steel, using jacks, to the specified tension with the stress transferred to the end anchorage. Measure the tension and elongation at all times. 553 – PRESTRESSED CONCRETE MEMBERS 2020 EDITION V5.1 553-10 Make a record of gauge pressures and elongation while post tensioning and submit it for review.
553.03.13 Bonding Steel
Bond post-tensioned steel to the concrete unless otherwise specified. Clean all dirt, loose rust, grease, or other deleterious material from all pre-stress reinforcing steel. Flush all conduits with water and blow them out with compressed air after post-tensioning. Remove rubber sheaths used as enclosures, then flush and blow out the voids as described above. Once cleaned, pressure-grout the conduit or void using a pressure not exceeding 100 psi (690 kPa). Continue grouting until a steady flow of grout exits from the pipe outlet. Close the outlet, then the inlet with the grout under pressure. Maintain the final grout pressure at between 50 to 100 psi (345 - 690 kPa).
553.03.14 Concrete Surface Finish
Perform the concrete finish work immediately after de-tensioning. Give the exterior surfaces of exterior members and the entire bottom flange of all girders to the juncture with the beam web an ordinary finish as specified in Subsection 552.03.11(D) . All other beam surfaces may be left with the surface created by the forms, if the surfaces are true, even, and free of stone pockets, depressions, or surface projections. Point with mortar and strike off even with the surrounding surface, all air holes in the concrete measuring ½-inch (13 mm) or more in any direction. Repair rough, uneven, and non-uniform concrete surfaces using power grinders, carborundum stones, brushhammers, or other approved equipment and then apply an ordinary finish. Match the appearance of the surface adjacent to the repair. Apply an ordinary finish to the entire adjoining surface of the member if a match is not possible. Repair rock pockets identified for repair. Chip rock pockets back to sound concrete, clean, and permit inspection before patching. Rock pockets affecting the member’s strength will be further evaluated before repair. Notify the Inspector of all members having the prestress strand exposed for 8 inches (200 mm) or more on any one strand or any exposure of multiple strands before repair. Provide an ordinary finish on beam ends not embedded in concrete. The Contractor may use approved epoxy or quick-setting grout products, provided the colors blend with the surrounding surface. Before finishing the beam ends, cut the strands back a minimum of ½-inch (13 mm) and fill the depressions with an approved epoxy. When beam ends are to be embedded in concrete, the ends may be left rough, and strands cut back to extend a maximum 1-inch (25 mm) beyond the surface of the concrete. Cut the strands in the area of the paving notch flush with the concrete surface. Screed and rough float the top surface of prestressed girders to the required depth of the member, bringing grout to the surface, and covering all aggregate. Clean all projecting reinforcing stirrups of mortar and other foreign materials before starting the cure cycle.
553.03.15 Workmanship and Tolerances
All tolerances are applied to the theoretical positions and dimensions shown in the contract and approved fabrication drawings. 2020 EDITION V5.1 PRESTRESSED CONCRETE MEMBERS – 553 553-11 The tolerances from the plan and theoretical dimensions listed in Table 553-1 are the maximum acceptable cumulative deviations. The Project Manager will verify that the girders are within the allowable tolerances when the girder’s alignment is not influenced by temporary temperature differences between the girder’s surfaces. Tolerances in other manufacturing sequences cannot accumulate to supersede any individual tolerance. Members having dimensions outside the tolerance limits may be rejected. TABLE 553-1 TOLERANCES FOR PRESTRESSED CONCRETE MEMBERS Element Tolerance Length of beam, end-to-end, measured at centerline of beam, top or bottom flange ± ¾-inch (19 mm) Centerline-to-centerline of end bearing plates ⅛-inch per 10 feet (3 mm per 3 m), but no greater than ½-inch (13 mm) Depth of flanges, fillets, and web ± ¼-inch (5 mm) Depth overall + ½ to -¼-inch (13 to 5 mm) Width of flanges, fillets, and web + ⅜ to -¼-inch (10 to 5 mm) Beam ends - deviation from square or specified skew horizontal ± ¼-inch (5 mm), vertical ⅛-inch per foot (3 mm per 300 mm) of beam height or ½-inch (13 mm), whichever is less Side insert, center-to-center and center to beam end ± ½-inch (13 mm) Horizontal alignment (deviation from a straight line parallel to centerline of the member) ⅛-inch per 10 feet (3 mm per 3 m) of beam length but not greater than 1-inch (25 mm) Camber differential between adjacent beams measured at release of prestress (to be applied only to identical members cast in same line) ⅛-inch per 10 feet (3 mm per 3 m) of span to a maximum of 1-inch (25 mm) Stirrup bars (specified projection above beam top) ± ½-inch (13 mm) Tendon position ± ¼-inch (5 mm) in center of gravity of strand group and individual tendons Position of deflection points for deflected strands ± 6-inch (150 mm) Position of handling devices along centerline of beam ± 6-inch (150 mm) Centerline of bearing plates to end of beam ± ¼-inch (5 mm) Bearing plates (deviation from a plane perpendicular to the vertical axis of the beam) ± 1⁄16-inch (2 mm) Stirrup bars (longitudinal spacing) ± 1-inch (25 mm) Position of post-tensioning ducts ± ¼-inch (5 mm) 553 – PRESTRESSED CONCRETE MEMBERS 2020 EDITION V5.1 553-12
553.03.16 Storage and Transportation
Exercise care during transporting, storing, hoisting, and handling of the precast units to prevent cracking or damage. Transport precast girders and slabs in an upright position, with the points of support and directions of the reactions with respect to the members being approximately the same during transport and storage as when the members are in the final planned position. Lift the beams using the lifting eyes. During lifts, use spreaders between slings to eliminate the horizontal component of the lifting force from being applied to the beam. A spreader is not required when the angle between the sling and the top of the beam exceeds 45°. Do not move prestressed members from the casting yard until the concrete has reached the 28 day strength and the Project Manager has been notified of the intent to transport the beams. Replace units damaged by improper storing, handling, or transporting at Contractor expense.
553.03.17 Placing
Place precast, prestressed structural members as specified. Place piling in accordance with Section 559 .
553.03.18 Bearing and Anchorage
Place masonry bearing plates in accordance with Subsection 565.03.2. Place anchor bolts in accordance with Subsection 552.03.13.
553.03.19 Precast Prestressed Deck Sections
553.04 Method of Measurement
Precast, prestressed concrete members, excluding piling, are measured by the foot (meter) for each specified type and/or size, installed and accepted. Prestress beams are measured by the foot (meter) from centerline bearing to centerline bearing along the beam centerline. Precast prestressed deck sections are measured by foot (meter) for each type installed and accepted.
553.05 Basis of Payment
Payment for the completed and accepted quantities is made under the following: Pay Item Pay Unit Precast Member Foot (m) Prestress Member Foot (m) Prestressed Beam – (Type) Foot (m)