h.Handling, Storing, and Erecting: Units shall be adequately separated in storage immediately following removal from beds to make inspection of finished surfaces possible and to facilitate repair of surface blemishes.405.05 485Care shall be taken in handling and storing units to avoid damage to concrete. Concrete must have attained the minimum 28-day design compressive strength before structural units are shipped to the project site. Piles shall not be driven until at least 7 days after the date concrete is cast and has attained the minimum design compressive strength. Lifting and support points for all units shall be as shown on the Plans. If the Plans do not indicate lift - ing and support points, the Contractor shall lift and support units at locations not less than 6 inches or more than the depth of the unit from the end of the unit. The Contractor shall be responsible for the design and safety of the lifting device used. Piles shall be supported at lift points as shown on the Plans. Requests by the Contractor to use lifting or support points other than those indicated must be accompanied by computations showing that stresses are within the allowable range using 50 percent of the dead load as an impact factor. Units that have been damaged in handling shall be repaired to the satisfaction of the Engineer. Units that have been damaged to such an extent that they are not repairable shall be replaced at no expense to the Department. Recesses at ends of transverse ties, holes for anchor bars, and other recesses shown on the plans shall be filled with mortar conforming to Section 218. Mortar shall be applied in one continuous operation for each span. Where waterproofing material is to be applied to tops of units in the field, longitudinal joints shall be sufficiently smoothed to prevent damage to the material. Shear keys required between adjacent units shall be constructed using the material shown on the Plans. Struts and diaphragms between spread units may be cast separately or monolithically with the deck slab. If the Contractor casts struts and diaphragms separately from the slab, deck slab concrete shall not be placed until concrete in the struts or diaphragms has attained 80 percent concrete strength (f’c). If the Contractor casts struts and diaphragms monolithically with the slab, each prestressed concrete beam shall be placed and restrained in such a manner that the beam will not be canted during construction of the struts, diaphragms, and slab. The Contractor’ s method for maintaining acceptable vertical alignment of beams shall be subject to the approval of the Engineer. Bearing surfaces of units shall be parallel to the bottom surface of the unit or as specified on the plans. Attached bearing assemblies shall be fabricated so that their bottom bearing surfaces shall lie in truly horizontal planes in their erected position. Metal bearing plates or bottoms of precast beams that are to bear on elastomeric pads shall be coated with epoxy, Type EP-2, EP-4, or EP-5, and then surfaced with a No. 36 to No. 46 silicon carbide or aluminum oxide grit. Ends of beams, at ends of spans, and diaphragms shall be vertical. Continuity diaphragms for prestressed beams shall not be cast until at least 90 days after the strands in the beams have been detensioned. Units shall be stored on dunnage placed at the support points shown on the Plans and at least 4 inches above the ground. If supports points are not provided on the Plans, the Contractor may locate the dunnage at the lifting points or bearings. If units are stacked, they shall be so arranged that the weight of upper members does not introduce shear or bending effects onto members below. The Contractor shall make all units accessible for inspection by the Engineer upon request.405.05 486Once beams, girders, or slabs have been placed on temporary supports for storage, camber measure - ments shall be taken at midspan, at release and at 2 week intervals thereafter up to 120 days after detensioning. These measurements shall be recorded in the morning to reduce the effects of solar radiation for each unit and shall include the date, time, weather conditions, and measurements taken. Piles or other elements supported at more than two points shall have their camber measured at the midpoint of each supported span. Camber shall be measured and recorded in a bound log book and made available to the Inspector. Camber measurements that fall outside the tolerances below shall be reported in writing to the Engineer and will be cause for rejection if not corrected to the satisfaction of the Engineer. Each measurement shall include the date of casting, the date of the measurement, the time of day, the temperature and other weather conditions (as directed by the Engineer) along with the measurement. The Contractor shall submit a camber management plan to the Engineer prior to fabrication indi - cating the method for controlling camber. Units shall not be loaded before the 28-day compressive strength is achieved and no earlier than 7 days. The Engineer will review the plan, and once found to be acceptable, the Contractor shall implement the plan if any of the thresholds below are exceeded: • 75 percent of the design camber at erection on the Plans • 75 percent of the allowable limit between adjacent beams, girders or slabs • 3/4 inch difference between the high and low units in the same span (for slabs or box beams) The Contractor shall implement the camber management plan for any beams, girders or slabs that will be erected 120 days or more after detensioning. Where a change in construction schedule occurs which will result in erection 120 days or more after detensioning, the Contractor shall implement the camber management plan. When a camber management plan is implemented, camber measurements shall be taken after loading the units. Subsequent camber measurements can be taken in the loaded state. Camber shall be measured within 3 days prior to shipping in an unloaded state. The Contractor may submit a request to delay the implementation of the camber management plan to the next scheduled camber measurement if documentation is submitted showing the camber growth is following an established camber development path that will not exceed the camber tolerance at erection under the current construction schedule. If accepted by the Engineer, the Contractor shall implement the camber management plan at the next scheduled camber measure - ment unless a subsequent request is made and approved by the Engineer. No beam, girder or slab exceeding the camber tolerance at erection shall be shipped to the jobsite unless approved by the Engineer. All field welding, such as field welding of sole plates or other metallic components, shall be performed in accordance with Section 407. Coatings shall be repaired in accordance with Sections 233 and 411 as applicable. Payment for field welding, inspection, and coating shall be included in the price bid for other items.405.05 487405.06—Tolerances The limits of tolerance do not necessarily represent fully acceptable construction; they are the limits at which construction may become unacceptable. In general, workmanship shall be at a level of quality that will be well within the tolerance limits.
a.Precast Prestressed Concrete I-Beams and T-Beams: Characteristic Values Depth (overall) ±1/4 inch Width (flanges and fillets) ±1/4 inch Width (web) ±1/4 inch Length of beam ±1/8 inch/10 ft or 1/2 inch, whichever is greater Exposed beam ends (deviation from square Horizontal ±1/4 inch, vetical or designated skew) ±1/8 inch/ft of beam height Side inserts (spacing between centers of inserts ±1/2 inch and from centers of inserts to ends of beams) Bearing plate (spacing from centers of bearing ±1/2 inch plates to ends of beams) Stirrup bars (projection above top of beam) ±3/4 inch Stirrup bars (longitudinal spacing) ±1 inch Horizontal alignment (deviation from straight Max. 1/8 inch/10 ft line parallel to centerline of beam) Camber differential between adjacent beams 1/8 inch/10 ft or max. 1/2 inch of same type and strand pattern (at time of erection) Camber differential from design camber +30% to -50% at erection on plans (at time of erection) Center of gravity of strand group ±1/4 inch Center of gravity of depressed strand group ±1/4 inch at end of beam Position of hold-down points for depressed strands ±6 inches Position of handling devices ±6 inches
b.Precast Prestressed Concrete Box Beams and Flat Slabs: Characteristic Values Depth (top slab) +1/2 to –1/4 inch Depth (bottom slab) 0 to +1/2 inch Depth (overall) ±1/4 inch Width of web or thickness of sidewalls ±3/8 inch Width (overall) +1/8 to –1/4 inch Length ±1/8 inch/10 ft or 1/2 inch, whichever is greater V oid position (longitudinal) from Plan locations ±1/2 inch ±1 inch adjacent to end block Square ends (deviation from square) ±1/4 inch Skew ends (deviation from designated skew) Skew angle equal to or less than 30° ±1/4 inch Skew angle greater than 30° ±1/2 inch405.06 488Horizontal alignment (deviation from straight Max. 1/8 inch/10 ft line parallel to centerline of unit) Gap between adjacent units Max. 1/2 inch Tie rod tubes (spacing between centers of tubes ±1/4 inch and from centers of tubes to ends of units) Tie rod tubes (spacing from centers of tubes ±1/4 inch to bottom of beam) Longitudinal begin/end position of Virginia ±3 inches Adjacent Member Connection blockouts Camber differential between adjacent units Max. 1/4 inch (at time of erection) Camber differential between adjacent units with Max. 1/2 inch (at time of erection) Virginia Adjacent Member Connections Camber differential between high and low Max. 3/4 inch (at time of erection) units in same span Camber differential from design camber at +30% to -50% erection on plans (at time of erection) Side inserts (spacing between centers of inserts ±1/2 inch and from centers of inserts to ends of beams) Stirrup bars (projection above top of beam) ±3/4 inch Stirrup bars (longitudinal spacing) ±1 inch Center of gravity of strand group ±1/4 inch Center of gravity of depressed strand group ±1/4 inch at end of beam Position of hold-down points for depressed strands ±6 inches Position of handling devices ±6 inches