11-1 Division 11
WORK ZONE TRAFFIC CONTROL 1101 -1 TRANSPORTATION MANAGEMENT PLAN (TMP) Maintain traffic through work zones in accordance with the se Specifications , the MUTCD, Roadway Standard Drawings , 23 CFR 630 Subparts J and K and the Transportation Management Plan (TMP) . Below is a list of the possible TMP components:
11-2 (E) Temporary Traffic Control Plan Not Ful ly Covered in the Contract
When the TTC does not cover a particular work function, notify the Engineer to allow for the development or modification of a sealed set of the Temporary Traffic Control Plans. 1101 -3 BLASTING ZONE When blasting operations are within 1, 000 f eet of a travelway , provide the appropriate traffic control as shown in the plans and/or the Roadway Standard Drawings . 1101 -4 CONSTRUCTION VEHICLE CROSSINGS Do not cross the median, ramps or loops with vehicles or equipment unless a specific location for crossing is approved and required traffic control devices are used as shown in the Roadway Standard Drawings . 1101 -5 ON-ROAD CONSTRUCTI ON VEHICLES When operating outside of a closed lane or haul road crossing in a work zone, on- road construction vehicles are subject to the Department’s Division of Motor Vehicle weight and safety regulations as commercial vehicles . Work vehicles must alwa ys use warning lights with at least 50% being amber in color attached to the vehicle as high as possible and in a manner such that they are not obscured by equipment or supplies. Vehicle hazard signals or lights may be used to supplement this requirement. This requirement applies to all work vehicles and equipment not inside lane closures or behind barriers. This requirement does not apply to dump trucks but it is encouraged. 1101 -6 EXCAVATIONS WITHIN TRAVELWAY During the process of excavating in a travelway where traffic is to be later maintained, make provisions to backfill and repair any excavated or damaged pavement before allowing traffic to proceed over the affected lanes. In low speed areas (35 mph or less) , metal plates may be used to cover excavated areas. 1101 -7 HAULING OPERATIONS Comply with the multiple and single vehicle hauling restrictions as shown in the TMP when performing hauling of equipment or materials to or from the project. Define “Multiple Vehicle Hauling ” as the hauling of equipment or materials to or from the project with delivery at intervals of less than 5 minutes o r results in more than one vehicle at a particular work site at a time. Define “Single Vehicle Hauling ” as the hauling of equipment or materials to or from the project with delivery at intervals of more than 5 minutes and results in no more than one vehicl e at a particular work site at a time. Do not conduct any hauling operations against the flow of traffic of an open travelway unless an approved temporary barrier or guardrail separates the traffic from the hauling operation. On multi- lane, controlled access roadways, haul vehicles shall not enter/exit an open travel lane at speeds more than 10 mph below the posted speed limit. Haul vehicle acceleration to within 10 mph of the posted speed limit shall only occur on paved surfaces. 1101 -8 MATERIAL AND EQUIPMENT STORAGE When work is not in progress, keep all personnel, equipment, machinery, tools, construction debris , materials and supplies away from active travel lanes that meets Table 1101 -1.
11-3 Table 1101 -1
MATERIAL AND EQUIPMENT STORAGE FROM ACTIVE TRAVEL LANES Posted Speed Limit (mph) Distance (ft) 40 or less ≥ 18
45-50 ≥ 28
55 ≥ 32 60 or higher ≥ 40 When vehicles, equipment and materials are protected by concrete barrier or guardrail, they shall be offset at least 5 f eet from the barrier or guardrail. 1101 -9 PARKING OF PERSONAL VEHICLES Provide staging areas for personal vehicle parking in accordance with Article 1101- 8 or as directed by the Engineer before use. 1101 -10 PROTECTION OF HAZARDS Mark all hazards with signs, barricades, drums or other warning devices. At each location where work is started which creates a safety hazard, continue the work until completed to the extent that the safety hazard i s eliminated. If the work is not pursued in a continuous manner the Engineer will not allow any other work on the project to be performed until the existing safety hazard is eliminated. 1101 -11 TEMPORARY LANE CLOSURES
11-4 (C) Traffic Stoppage
Limit the stoppage of traffic to times specified in the TMP . Provide time between consecutive stoppages to allo w the traffic queue to deplete. 1101 -13 TRAFFIC CONTROL SUPERVISION Provide the service of at least one qualified work zone supervisor. The work zone supervisor shall have the overall responsibility for the proper implementation of the TMP and ensure all employees working inside the NCDOT right of way have received the pr oper training appropriate to the job decisions each individual is required to make. The work zone supervisor is not required to be on site at all times but shall be available to address concerns of the Engineer. The name and contact information of the wor k zone supervisor shall be provided to the Engineer prior to or at the preconstruction conference. Qualification of work zone supervisors shall be done by an NCDOT approved training agency or other approved training provider. For a complete listing of app roved training agencies , see the Work Zone Safety Training webpage. Coordinate with and cooperate with work zone supervisors of adjacent or overlapping construction projects to ensure safe and adequate traffic control is maintained throughout the projects at all times including periods of construction inactivity in accordance with
Article 105 — 7.
All certification records for qualified work zone supervisors shall be uploaded by the approved training agency or other approved training provider to the Department’s Work Zone Education Verification App (WZ -EVA) prior to the qualified work zone supervisor performing any work zone supervisor duties on the project. For more information about WZ - EVA, see the Work Zone Safety Training webpage. 1101 -14 WORK ZONE INSTALLER Provide the service of at least one qualified work zone installer during the setup, installation, and removal of temporary traffic control within the highway right of way. The qualified work zone installer shall serve as crew leader and shall be on site and directing the installation and removal of temporary traffic control. If multiple temporary traffic control installations or removals are occurring simultaneously, then each shall have a qualified work zone installer. The work zone installer shall be qualified by an NCDOT approved training agency or other NCDOT approved training provider in the safe and competent set up of temporary traffic control. For a complete listing of approved training agencies, see the Work Zone Safety Training webpage. A work zone supervisor, in accordance with Article 1101- 13 of the Standard Specifications, may fulfill the role of the work zone installer during the setup, installa tion, and removal of temporary traffic control within the highway right of way provided they are on site and directing the installation and removal of temporary traffic control. All other individuals participating in the setup, installation, and removal of temporary traffic control within the highway right of way shall be certified as a qualified flagger in accordance with Article 1150 -3 of the Standard Specifications, even if flagging is not being performed as part of the traffic control. Provide the name and contact information of all qualified work zone installers to the Engineer prior to or at the preconstruction conference. Additionally, provide a qualification statement that all other individuals participating in the setup, installation, and removal of temporary traffic control are qualified flaggers that have been properly trained through an NCDOT approved training agency or other NCDOT approved training provider . All certification records for qualified work zone installers and flaggers shall be uploa ded by the approved training agency or other NCDOT approved training provider to the