Stone for Erosion Control, Class __ will be measured and paid for in accordance with Article 1 1610 -4. Seeding and Mulching will be measured and paid for in accordance with Article 1660 -8. Seed for Temporary Seeding will be measured and paid for in accordance with Article 1620- 6. Fertilizer for Temporary Seeding will be measured and paid for in accordance with Article 5 1620 -6. Matting for Erosion Control will be measured and paid for in accordance with Article 1631- 4. No measurement will be made for other items or for over excavation or stockpiling. Payment will be made under: Pay Item Pay Unit __" Skimmer Each Coir Fiber Mat Square Yard Low Permeability Geotextile Square Yard
WOODED AREA CLEANUP -1 DESCRIPTION Remove and satisfactorily dispose of debris and of dead, partially dead or broken vegetation from wooded areas of the right of way outside clearing limits and from other areas outside construction limits on which seeding and mulching is not to be performed. Work includes treating stumps with herbicide and repai ring any damage to vegetation. Cutover timberland, reforested areas or thickets of young native volunteer vegetation will be considered to be wooded areas. -2 MATERIALS Refer to Division 10. Item Section Herbicide 1060 -13 -3 CONSTRUCTION METHODS Remove all logs, stumps, snags, loose roots, down timber, slabs, tree laps, lumber, dead or partially dead trees, broken trees or brush, dead brush, sawdust piles, discarded fences, leaf piles, brick, tile masonry and other debris from the cleanup areas. Cut, all dead trees, stumps, snags, broken or partially dead trees and brush, flush with the ground. Remove vegetation which dies between initial cleanup and completion of the project before final acceptance. Hand raking of areas or removal of a normal leaf layer is not required unless stated in the contract. Treat partially dead stumps or broken vegetation with a herbicide immediately after cutting. Use the herbicide and the method and rate of application, specified in the contract. Follow all applicable instructions, warnings and safety precauti ons stated on the manufacturer's label, and comply with all laws and regulations governing herbicides that are in effect at the time of use. Dispose of all material cleaned up under this item in accordance with the applicable requirements of Article 200 -5 and Article 802- 2. -4 DAMAGE TO REMAINING VEGETATION Conduct operations so as to prevent injury to trees, shrubs or other types of vegetation that are to remain growi ng and to prevent damage to adjacent property.