3-10 Section 350
350-1 Description
Clean out silt accumulations and other debris from existing drainage pipes at locations shown in the plans and as directed by the Engineer .
350-2 Construction Methods
Use a pipe clean out method that does not damage the existing pipe.
350-3 Measurement and Payment
Pipe Clean Out will be measured and paid as the actual number of existing pipes, structure to structure, cleaned out and accepted by the Engineer , except where the work of cleaning out the pipe was made necessary by the Contractor’s negligence in taking appropriate erosion control measures. Such price and payment will be full compensation for cleaning out existing pipe and disposing of all silt and debris. Payment will be made under : Pay Item Pay Unit Pipe Clean Out Each
Source: North Carolina Standard Specifications for Roads and Structures, 2024 Edition. Pages 136–136 of 857.