4-1 Division 4
MAJOR STRUCTURES
400-1 Description
Furnish any design calculations and drawings required; furnish members and deck materials for structures and any other materials necessary; erect, maintain, remove and dispose of temporary structures required for the maintenance of pedestrian, highway and other traffic. Construct temporary structures in accordance with the contract.
400-2 Materials
Use materials for temporary structures that conform to Division 10 or previous ly used materials conforming to the contract . Obtain approval for the use of salvaged materials and materials not covered by Division 10 before their use. Unless otherwise specified, untreated timber is allowed.
400-3 Plans
400-4 Construction Methods
Construct and maintain temporary structures to adequately and safely carry traffic during the entire period for which they are required. Remove and dispose of the temporary structures after they are no longer required in accordance with Article 402 -2. Upon removal of the temporary structure, all material furnished by the Contractor for use in this structure shall remain the property of the Contractor unless otherwise provided in the contract. Unless otherwise specified in the contract, remove temporary piling to the streambed level or to one foot below existing ground.