602PORTLAND CEMENT CONCRETE PAVEMENT SMOOTHNESS

NE · 2017 Standard Specifications✓ Full text on BuildSpecBook pages 430–436 Save this section

Ask about Section 602

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

- 396 - SECTION 602 -- PORTLANDCE MENT CONCRETE PAVEMENT SMOOTHNESS

602.01General

1.This Specification establishes a standard for Portland cement

concrete pavement smoothness, a nd defines defective pavement smoothness. The intent of the specification is to produce a finished Portland cement concrete pavement driving su rface with an International Roughness Index (IRI) no greater than 99 inches per mile.

2.Pavement smoothness will be evaluated as described in this

section when the pay item “Portland Cement Concrete Smoothness Testing” is included in the contract.

3.When the pay item “Portland Cement Concrete Pavement

Smoothness” is not included in the cont ract, the Contractor shall test the hardened concrete for surface irregularities with a non-contact inertial pavement profiler, a 10 foot (3 m) stra ightedge, or an approved device at the Engineers discretion. Areas showing high spots in excess of 1/8 inch (3 mm) in the 10 foot (3 m) span will be plainly marked and ground to the required profile.

602.02Equipment

1.The Contractor shall furnish a non-contact inertial pavement profiler
(profiler)that meets the requirements of ASTM Standard E 950, certified by

the manufacturer. The profiler shall be certified by the Department that it meets the ASTM Standard E 950 requirements.

2.The profiler may be a lightweight version or a high speed version.
3.The profiler shall be equipped wi th a computerized system that will

record, analyze, and print the test data. The profiler shall be equipped with a guide bar and a large footprint height sensor specifically designed for surface profile measurements on te xtured Portland cement concrete surfaces.

4.The profiler shall produce a printed pavement profile summary

report. The report shall include the following information.

a.Project number b. Test date c. Traffic lane d. Test direction e. Test path
f.Pass number (1 for initial test; 2, 3, etc. for repeat runs)
g.Operator’s name h. Project stations i. Data filter values j. IRI values fo r each test section
k.California profilograph emulation traces (profilograms) for each

test section

l.Bump and dip locations for each test section, as determined by

California profilograph emulation Portland Cement Concrete Pavement Smoothness 602.04

- 397 - 602.03 -- Certification and Independent Assurance Testing

1.The Department will calibrate and certify the Contractor’s profiler

annually at a test site established by the Department.

a.The profiler will be inspected for compliance with general

equipment requirements, including dat a analysis system, guidance system, and overall condition.

b.The profiler will be calibrated for distance measurement by

moving it over the described path of a premeasured test distance to determine its distance calibration factor.

c.The profiler will be checked for vertical measurement accuracy

by performing the height measurement calibration procedure described in Section 6 of AASHTO R 056, Certification of Inertial Profiling Systems.

d.The profiler will be checked for overall performance by

operating it over the described path of a premeasured pavement test section at its normal operating speed.

e.Distance measurement indicated by the profiler shall be within

0.2% tolerance of the actual premeasu red test section distance. To ensure accurate distance measurement during test runs, the air pressure of the distance measurement tire must always be maintained at the same pressure.

f.The IRI reported by the profiler for the test section shall be

within 10.0% tolerance of the IRI reported by a Department profiler for the same test section.

g.A dated and signed decal will be placed on the profiler to

certify its acceptability for use on Department pavement construction projects.

2.The Department will certify the Contractor’s profiler operator at

least every 5 years. The operator may be certified by presenting certification from another state highway agency or by completing certification training conducted by the Department.

3.The Department will perform I ndependent Assurance tests for the

Contractor’s profilers and operators at least once per construction season. Independent Assurance testing will be conducted at a randomly selected time on an active construction project. The criteria for the test will be similar to those used for certification.

602.04Profilograph Test Procedures

1.The Contractor shall per form all pavement smoothness

specification tests with a De partment certified profiler.

2.The Engineer will furnish a repor t form to the Contractor identifying

all required test sections.

a.The pavement surface will be divided into lane-width segments

that end at a bridge, railroad crossing, or other designated termini.

b.The lane-width segments will be further divided into individual

528 feet (200 m) long test sections, in t he direction of project stationing. The last test section in a segment is usually shorter than 528 feet (200 m).

Portland Cement Concrete Pavement Smoothness

- 398 - c. If a test section is less th an 300 feet (100 m) long, it will be combined with the preceding 528 feet (2 00 m) long test section for analysis.

3.The Contractor’s certified profiler operator shall perform

smoothness specification tests in the Engineer’s presence.

4.Smoothness testing shall be performed during normal daylight

working hours unless otherwise approved by the Engineer.

5.The profiler operators hall perform pavement smoothness

measurements in the right-hand or left- hand wheel path of all driving lanes and shall be performed in the direction of traffic, as directed by the Engineer, including climbing and fly-by lanes. The wheel path is the path followed by the right or left wheels of a truck or car traveling in the center of a traffic lane. It is assumed to be 3 feet from the left or right lane lines. In urban areas, where inlet block-outs or manholes are in the right- or left-hand wheel path, the pavement smoothness measurements shall be made in a location determined by the Engineer.

6.The Contractor shall remove all objects and foreign material from

the pavement surface befor e testing, including any extra run-in or run-out lengths required for the profiler.

7.The profiler operator shall gui de the profiler along the specified

wheel path of each traffic lane at a constant speed and directional path throughout the length of pavement being tested. The speed of the profiler must be within the speed range recommended by the manufacturer. Sudden changes in speed or direction during a te st run will disqualify that test, and a new test must be performed.

8.A lateral location indicator shall be used to align the profiler in the

required test path during testing. Pavement edges, longitudinal joints or longitudinal pavement markings may be used as reference lines.

9.Before testing, the profiler operator shall perform routine check

procedures of the measurement system as recommended by the manufacturer. To ensure consistent distance measurement, the profiler operator shall also check and adjust the distance recording wheel tire pressure several times a day.

10.All station references on the prof iler reports shall be actual project

stations. Stations shall be accurately noted on any printed profiles at least every 100 feet (25 m).The distance measured by the profiler shall compare within 0.2% of the actual distance tested, as determined using project stationing, for all testing and retesti ng runs. Test runs that do not compare within 0.2% will disqualify that test. New tests must be performed for all disqualified tests, following calibration of the distance measuring system

11.Immediately after completion of the tests, the profiler operator and

the Engineer shall sign and date any pr inted reports and profiles to verify their authenticity. The signed prints then immediately become the property of the Department. Failure to do so will disq ualify the tests. The test shall be re- run by the Contractor at no additional expense to the Department. Upon completion of the project, the data files shall be given to the Engineer in a Pro-VAL- compatible file. Portland Cement Concrete Pavement Smoothness 602.05

- 399 - 12. The Engineer will perform or schedule verification tests on at least 10% of the lane miles of pavement surf ace, with a Department profiler. This verification testing will be performed in conjunction with the Contractor’s profile testing. The Contractor’s IR I results shall be within 10% of the Departments IRI results.

13.If the verification test, Indepen dent Assurance tests, or other

observations indicate that the Contra ctor’s procedures or results are not acceptable and/or accurate, the Engineer may do any or all of the following:

a.Require the Contractor to calibrate the profiler and re-run the

tests on some or all previous projects in the current construction season.

b.Disqualify the Contract or’s equipment or operator.
c.Perform the tests for part, or all, of the project with a profiler

owned by the Department, and charge th e Contractor $500.00 per lane mile for all testing done by the Department.

14.The following areas of pavement shall be excluded from the IRI

requirements.

a.Pavement on horizontal curves having a centerline radius of

curvature of less than 1,000 feet (300 m) and pavement within the superelevation transition of such curves.

b.Pavement within 50 feet (15 m) of a transverse joint that

separates the pavement from an approach slab to a bridge deck or existing pavement not constructed under the contract.

c.Pavement for truck weigh st ations, rest areas, acceleration/

deceleration lanes, and interchange ramps and loops.

d.Pavement within 50 feet (15 m) of railroad crossing and

associated transitions.

e.Pavement with a posted speed limit of 45 miles per hour or

less.

f.Mandated blockouts for access at intersections and driveways

including 50 feet (15 m) on either side.

g.Pavement that would require handwork by normal industry

practices.

h.Additional exceptions shown on the summary sheet in the

plans.

15.Excluded pavement sections shall be measured for bumps and dips

by the Contractor with a profiler or a 10 foot (3m) straight edge. If the profiler is used, the bump or surface deviation shall not exceed 0.30 inch (7.6 mm) in 25 feet. The deviation of the surface shall not exceed 1/8 inch (3 mm) if a 10 foot (3 m) straight edge is used.

602.05Evaluation

1.The Contractor shall determine the IRI and number of correctable

bumps and dips for each test section, record the information on the report form, and provide a copy of the report, along with the corresponding printed reports and profiles, to the Engineer.

Portland Cement Concrete Pavement Smoothness

- 400 - a. The International Roughness I ndex (IRI) shall be calculated by the profiler software using the quarter-car simulation. IRI shall be reported in units of inches per mile.

b.Correctable bumps shall be s eparately identified by the profiler

software in a summary report using th e California profilograph emulation. Bumps will appear as high points on the printed profile, and correspond to high points on the pavement surface. Correctable bumps are vertical deviations on the pavement surface that exceed 0.30 inch (7.6 mm) in height above a base line span of 25 feet (7.62 m).

c.Correctable dips shall be separately identified by the profiler

software in a summary report using th e California profilograph emulation. Dips will appear as low points on the printed profile, and correspond to low points on the pavement surf ace. Correctable dips are vertical deviations on the pavement surface that exceed 0.30 inch in depth below a base line span of 25 feet.

602.06Pavement Surface Correction

1.The Contractor shall locate and perform all required pavement

surface corrective work, with the approval of and in the presence of, the Engineer. Corrective work may also be required for any combination of bumps, dips, or other roughness that, in the opinion of the Engineer, produces an objectionable ride. The Contractor may also locate and perform voluntary corrective work as described in Paragraphs 2.b. and 2.c. of this Subsection.

a.Corrective work shall be acco mplished by diamond grinding or

by removal and replacement, at no cost to the Department.

b.Diamond grinding equipment used for surface correction shall

be power driven, self-propelled units specifically designed to grind and texture pavements. The cutting head shall be at least 36 inches (0.9 m) wide and consist of many diamond blades with spacers. The Engineer may approve equipment with a narrower width for irregular and confined areas which will not accommodate larger equipment and for bumps of limited number and area.

c.The grinding shall be perfo rmed so that the cement aggregate

bond will not be broken.

d.The Contractor shall re-test all corrected test sections with the

profiler.

2.All bumps and dips, as def ined in Subsection 602.05, Paragraph

1.b. and 1.c., shall be corrected until t hey are at or below the 0.30 inch (7.6 mm) limit. All dips shall be corrected by diamond grinding on either or both sides of the dip.

a.When the initial IRI of a te st section is 99 in/mi or less,

mandatory bump and dip correction is the only corrective work allowed for that section.

b.When the IRI of a test secti on exceeds 99 in/mi, the Contractor

may perform voluntary corrective work in that section, in addition to mandatory bump and dip correction work. Portland Cement Concrete Pavement Smoothness 602.08

- 401 - c. When the IRI of a test section exceeds 124 in/mi, mandatory corrective work shall be performed to re duce the IRI of that section to a value of 124 in/mi or less. The Contra ctor may perform voluntary corrective work in that section, in addition to mandatory work.

d.Dip correction by diamond grinding shall not reduce the

pavement thickness to less than the required plan thickness minus 1/4 inch.

3.When pavement removal and replacement is used for correction,

the Contractor shall furnish the replacem ent material and construction at no cost to the Department.

a.All replacement material shal l meet the original specifications

for the material removed.

b.Removal and replacement shall be for the full lane width for a

distance determined by the Engineer.

c.Replacement material must meet the same smoothness

requirements as the removed pavement.

602.07Traffic Control

1.The Contractor shall provide all traffic control for smoothness

testing and corrective work at no cost to the Department.

602.08Method of Measurement

1.The unit price of the accepted quantity of Portland concrete

pavement in each profilograph test section shall be adjusted according to the schedule in Table 602.01, subject to the limitations in Paragraphs 2, 3, and 4 of this Subsection. Pavement sections excluded from this smoothness specification shall not qu alify for incentive pay. Table 602.01 Payment Adjustment Schedule I R I P e r c e n t o f Inches per Lane Mile Contract Prices (mm per lane Kilometer) 0 to 43 (0 to 63) 106 Greater than 43 to 56 (63 to 126) 104 Greater than 56 to 68 (126 to 189) 102 Greater than 68 to 99 (189 to 347) 100 Greater than 99 to 105 (347 to 379) 97 Greater than 105 to 111 (379 to 410) 94 Greater than 111 to 117 (410 to 442) 92 Greater than 117 to 124 (442 to 473) 90 Greater than 124 (473) Corrective work required

2.When the initial IRI of a test section is 99 in/mi (347 mm/km) or less, that value shall determine the perc ent of incentive pay for the section,

except that any mandator y correction work ( bumps or dips) performed in

Portland Cement Concrete Pavement Smoothness

- 402 - that section may increase the percent of pay up to the 106% level indicated in Table 602.01.

3.When the initial IRI of a test section is greater than 99 in/mi

(347 mm/km), mandatory or voluntary corrective work performed in that section may increase the percent of pa y up to the 100% level indicated in Table 602.01.

4.When the initial IRI of a test section is greater than 124 in/mi

(473 mm/km), mandatory an d voluntary corrective work performed in that section may increase the percent of pa y up to the 100% level indicated in Table 602.01.

602.09Basis of Payment

1.The overall pay factor for the a ccepted quantity of Portland cement

concrete pavement in all profile test sections shall be determined according to the formula in Table 602.02. Table 602.02 Pay Factor Formula PF = A(1.06) + B(1.04) + C(1.02) + D( 1.00) + E(0.97) + F(0.94) + G(0.92) + H(0.90) A + B + C + D + E + F + G + H Where: A = Length of pavement with an IRI of 0 to 43 inches per mile (0 to 63 mm/km) B = Length of pavement with an IRI greater than 43 to 56 inches per mile (63 to 126 mm/km) C = Length of pavement with an IRI greater than 56 to 68 inches per mile (126 to 189 mm/km) D = Length of pavement with an IRI greater than 68 to 99 inches per mile (189 to 347 mm/km) E = Length of pavement with an IRI gr eater than 99 to 105 inches per mile (347 to 379 mm/km) F = Length of pavement with an IRI greater than 105 to 111 inches per mile (379 to 410 mm/km) G = Length of pavement with an IRI greater than 111 to 117 inches per mile (410 to 442 mm/km) H = Length of pavement with an IRI greater than 117 to 124 inches per mile (442 to 473 mm/km)

2.The work of smoothness testing shall be paid for at the lump sum

contract unit price. This price shall be full compensation for all smoothness testing as set forth in this Specification.

- 403 - SECTION 603 -- CO NCRETE PAVEMENT

603.01Description

1.This work shall consist of furnishing all materials and constructing

Portland cement concrete pavements, approach slabs, and headers. They are to be constructed on a prepared subgrade, modified subgrade or foundation course.

603.02Material Requirements

1.The concrete class for pavements, headers and bridge approach

slabs shall be as specified in the contract.

2.All materials shall be furnished by the Contractor and shall conform

to the requirements of the Sections shown in Table 603.01. Table 603.01 Material Requirements Applicable Materials Section Curing Materials ............................................. 101 0, 1011, 1012, 1013 Preformed Polychloroprene Elastomeric Reinforcing Steel ............................................ 1020, 1021, 1024

603.03Construction Methods

1.General Preparation:
a.The Contractor shall pre pare the subgrade as described in
b.The foundation course shall be constructed in accordance with

the requirements of Secti on 307 or in the contract.

c.In no case shall concrete be placed upon an unstable or frozen

subgrade or foundation course.

2.Slip-Form Preparation:
a.Grade control shall be maintained by the Contractor. (1) Conventional Stringline shall be installed utilizing the

construction staking provided by the Department or by the Contractor if Contractor Staking is required.

(2)Stringless machine grade control may be utilized, provided

that the Contractor prep ares a digital terrain model (DTM) to a system specifically designed to control the paving equipment. The Contractor shall provide elevations from the DTM at key locations selected by the Engineer,

Get an email when 602 changes

Nebraska revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Nebraska Standard Specifications for Highway Construction, 2017 Edition. Pages 430–436 of 1,048. View official source ↗

Ask about this section

Scoped to Nebraska Standard Specifications for Highway Construction, Section 602 — PORTLAND CEMENT CONCRETE PAVEMENT SMOOTHNESS. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.