- 396 - SECTION 602 -- PORTLANDCE MENT CONCRETE PAVEMENT SMOOTHNESS
602.01General
concrete pavement smoothness, a nd defines defective pavement smoothness. The intent of the specification is to produce a finished Portland cement concrete pavement driving su rface with an International Roughness Index (IRI) no greater than 99 inches per mile.
section when the pay item “Portland Cement Concrete Smoothness Testing” is included in the contract.
Smoothness” is not included in the cont ract, the Contractor shall test the hardened concrete for surface irregularities with a non-contact inertial pavement profiler, a 10 foot (3 m) stra ightedge, or an approved device at the Engineers discretion. Areas showing high spots in excess of 1/8 inch (3 mm) in the 10 foot (3 m) span will be plainly marked and ground to the required profile.
602.02Equipment
the manufacturer. The profiler shall be certified by the Department that it meets the ASTM Standard E 950 requirements.
record, analyze, and print the test data. The profiler shall be equipped with a guide bar and a large footprint height sensor specifically designed for surface profile measurements on te xtured Portland cement concrete surfaces.
report. The report shall include the following information.
test section
California profilograph emulation Portland Cement Concrete Pavement Smoothness 602.04
- 397 - 602.03 -- Certification and Independent Assurance Testing
annually at a test site established by the Department.
equipment requirements, including dat a analysis system, guidance system, and overall condition.
moving it over the described path of a premeasured test distance to determine its distance calibration factor.
by performing the height measurement calibration procedure described in Section 6 of AASHTO R 056, Certification of Inertial Profiling Systems.
operating it over the described path of a premeasured pavement test section at its normal operating speed.
0.2% tolerance of the actual premeasu red test section distance. To ensure accurate distance measurement during test runs, the air pressure of the distance measurement tire must always be maintained at the same pressure.
within 10.0% tolerance of the IRI reported by a Department profiler for the same test section.
certify its acceptability for use on Department pavement construction projects.
least every 5 years. The operator may be certified by presenting certification from another state highway agency or by completing certification training conducted by the Department.
Contractor’s profilers and operators at least once per construction season. Independent Assurance testing will be conducted at a randomly selected time on an active construction project. The criteria for the test will be similar to those used for certification.
602.04Profilograph Test Procedures
specification tests with a De partment certified profiler.
all required test sections.
that end at a bridge, railroad crossing, or other designated termini.
528 feet (200 m) long test sections, in t he direction of project stationing. The last test section in a segment is usually shorter than 528 feet (200 m).
Portland Cement Concrete Pavement Smoothness
- 398 - c. If a test section is less th an 300 feet (100 m) long, it will be combined with the preceding 528 feet (2 00 m) long test section for analysis.
smoothness specification tests in the Engineer’s presence.
working hours unless otherwise approved by the Engineer.
measurements in the right-hand or left- hand wheel path of all driving lanes and shall be performed in the direction of traffic, as directed by the Engineer, including climbing and fly-by lanes. The wheel path is the path followed by the right or left wheels of a truck or car traveling in the center of a traffic lane. It is assumed to be 3 feet from the left or right lane lines. In urban areas, where inlet block-outs or manholes are in the right- or left-hand wheel path, the pavement smoothness measurements shall be made in a location determined by the Engineer.
the pavement surface befor e testing, including any extra run-in or run-out lengths required for the profiler.
wheel path of each traffic lane at a constant speed and directional path throughout the length of pavement being tested. The speed of the profiler must be within the speed range recommended by the manufacturer. Sudden changes in speed or direction during a te st run will disqualify that test, and a new test must be performed.
required test path during testing. Pavement edges, longitudinal joints or longitudinal pavement markings may be used as reference lines.
procedures of the measurement system as recommended by the manufacturer. To ensure consistent distance measurement, the profiler operator shall also check and adjust the distance recording wheel tire pressure several times a day.
stations. Stations shall be accurately noted on any printed profiles at least every 100 feet (25 m).The distance measured by the profiler shall compare within 0.2% of the actual distance tested, as determined using project stationing, for all testing and retesti ng runs. Test runs that do not compare within 0.2% will disqualify that test. New tests must be performed for all disqualified tests, following calibration of the distance measuring system
the Engineer shall sign and date any pr inted reports and profiles to verify their authenticity. The signed prints then immediately become the property of the Department. Failure to do so will disq ualify the tests. The test shall be re- run by the Contractor at no additional expense to the Department. Upon completion of the project, the data files shall be given to the Engineer in a Pro-VAL- compatible file. Portland Cement Concrete Pavement Smoothness 602.05
- 399 - 12. The Engineer will perform or schedule verification tests on at least 10% of the lane miles of pavement surf ace, with a Department profiler. This verification testing will be performed in conjunction with the Contractor’s profile testing. The Contractor’s IR I results shall be within 10% of the Departments IRI results.
observations indicate that the Contra ctor’s procedures or results are not acceptable and/or accurate, the Engineer may do any or all of the following:
tests on some or all previous projects in the current construction season.
owned by the Department, and charge th e Contractor $500.00 per lane mile for all testing done by the Department.
requirements.
curvature of less than 1,000 feet (300 m) and pavement within the superelevation transition of such curves.
separates the pavement from an approach slab to a bridge deck or existing pavement not constructed under the contract.
deceleration lanes, and interchange ramps and loops.
associated transitions.
less.
including 50 feet (15 m) on either side.
practices.
plans.
by the Contractor with a profiler or a 10 foot (3m) straight edge. If the profiler is used, the bump or surface deviation shall not exceed 0.30 inch (7.6 mm) in 25 feet. The deviation of the surface shall not exceed 1/8 inch (3 mm) if a 10 foot (3 m) straight edge is used.
602.05Evaluation
bumps and dips for each test section, record the information on the report form, and provide a copy of the report, along with the corresponding printed reports and profiles, to the Engineer.
Portland Cement Concrete Pavement Smoothness
- 400 - a. The International Roughness I ndex (IRI) shall be calculated by the profiler software using the quarter-car simulation. IRI shall be reported in units of inches per mile.
software in a summary report using th e California profilograph emulation. Bumps will appear as high points on the printed profile, and correspond to high points on the pavement surface. Correctable bumps are vertical deviations on the pavement surface that exceed 0.30 inch (7.6 mm) in height above a base line span of 25 feet (7.62 m).
software in a summary report using th e California profilograph emulation. Dips will appear as low points on the printed profile, and correspond to low points on the pavement surf ace. Correctable dips are vertical deviations on the pavement surface that exceed 0.30 inch in depth below a base line span of 25 feet.
602.06Pavement Surface Correction
surface corrective work, with the approval of and in the presence of, the Engineer. Corrective work may also be required for any combination of bumps, dips, or other roughness that, in the opinion of the Engineer, produces an objectionable ride. The Contractor may also locate and perform voluntary corrective work as described in Paragraphs 2.b. and 2.c. of this Subsection.
by removal and replacement, at no cost to the Department.
be power driven, self-propelled units specifically designed to grind and texture pavements. The cutting head shall be at least 36 inches (0.9 m) wide and consist of many diamond blades with spacers. The Engineer may approve equipment with a narrower width for irregular and confined areas which will not accommodate larger equipment and for bumps of limited number and area.
bond will not be broken.
profiler.
1.b. and 1.c., shall be corrected until t hey are at or below the 0.30 inch (7.6 mm) limit. All dips shall be corrected by diamond grinding on either or both sides of the dip.
mandatory bump and dip correction is the only corrective work allowed for that section.
may perform voluntary corrective work in that section, in addition to mandatory bump and dip correction work. Portland Cement Concrete Pavement Smoothness 602.08
- 401 - c. When the IRI of a test section exceeds 124 in/mi, mandatory corrective work shall be performed to re duce the IRI of that section to a value of 124 in/mi or less. The Contra ctor may perform voluntary corrective work in that section, in addition to mandatory work.
pavement thickness to less than the required plan thickness minus 1/4 inch.
the Contractor shall furnish the replacem ent material and construction at no cost to the Department.
for the material removed.
distance determined by the Engineer.
requirements as the removed pavement.
602.07Traffic Control
testing and corrective work at no cost to the Department.
602.08Method of Measurement
pavement in each profilograph test section shall be adjusted according to the schedule in Table 602.01, subject to the limitations in Paragraphs 2, 3, and 4 of this Subsection. Pavement sections excluded from this smoothness specification shall not qu alify for incentive pay. Table 602.01 Payment Adjustment Schedule I R I P e r c e n t o f Inches per Lane Mile Contract Prices (mm per lane Kilometer) 0 to 43 (0 to 63) 106 Greater than 43 to 56 (63 to 126) 104 Greater than 56 to 68 (126 to 189) 102 Greater than 68 to 99 (189 to 347) 100 Greater than 99 to 105 (347 to 379) 97 Greater than 105 to 111 (379 to 410) 94 Greater than 111 to 117 (410 to 442) 92 Greater than 117 to 124 (442 to 473) 90 Greater than 124 (473) Corrective work required
except that any mandator y correction work ( bumps or dips) performed in
Portland Cement Concrete Pavement Smoothness
- 402 - that section may increase the percent of pay up to the 106% level indicated in Table 602.01.
(347 mm/km), mandatory or voluntary corrective work performed in that section may increase the percent of pa y up to the 100% level indicated in Table 602.01.
(473 mm/km), mandatory an d voluntary corrective work performed in that section may increase the percent of pa y up to the 100% level indicated in Table 602.01.
602.09Basis of Payment
concrete pavement in all profile test sections shall be determined according to the formula in Table 602.02. Table 602.02 Pay Factor Formula PF = A(1.06) + B(1.04) + C(1.02) + D( 1.00) + E(0.97) + F(0.94) + G(0.92) + H(0.90) A + B + C + D + E + F + G + H Where: A = Length of pavement with an IRI of 0 to 43 inches per mile (0 to 63 mm/km) B = Length of pavement with an IRI greater than 43 to 56 inches per mile (63 to 126 mm/km) C = Length of pavement with an IRI greater than 56 to 68 inches per mile (126 to 189 mm/km) D = Length of pavement with an IRI greater than 68 to 99 inches per mile (189 to 347 mm/km) E = Length of pavement with an IRI gr eater than 99 to 105 inches per mile (347 to 379 mm/km) F = Length of pavement with an IRI greater than 105 to 111 inches per mile (379 to 410 mm/km) G = Length of pavement with an IRI greater than 111 to 117 inches per mile (410 to 442 mm/km) H = Length of pavement with an IRI greater than 117 to 124 inches per mile (442 to 473 mm/km)
contract unit price. This price shall be full compensation for all smoothness testing as set forth in this Specification.
- 403 - SECTION 603 -- CO NCRETE PAVEMENT
603.01Description
Portland cement concrete pavements, approach slabs, and headers. They are to be constructed on a prepared subgrade, modified subgrade or foundation course.
603.02Material Requirements
slabs shall be as specified in the contract.
to the requirements of the Sections shown in Table 603.01. Table 603.01 Material Requirements Applicable Materials Section Curing Materials ............................................. 101 0, 1011, 1012, 1013 Preformed Polychloroprene Elastomeric Reinforcing Steel ............................................ 1020, 1021, 1024
603.03Construction Methods
the requirements of Secti on 307 or in the contract.
subgrade or foundation course.
construction staking provided by the Department or by the Contractor if Contractor Staking is required.
that the Contractor prep ares a digital terrain model (DTM) to a system specifically designed to control the paving equipment. The Contractor shall provide elevations from the DTM at key locations selected by the Engineer,