- 154 - SECTION 302 -- SUBGRADE PREPARATION, SHOULDER SUBGRADE PREPARATION, AND PREPARATION OF INTERSECTIONS AND DRIVEWAYS
302.01Description
"Subgrade Preparation" or “Preparation of Intersections and Driveways” bid item:
contract.
conditions are met:
an existing grade.
minimum free haul distance specified in Section 209.
ends, railroad crossings, or any other physical features designated by the Engineer.
or the free haul distance.
the soils as necessary to conform to the contract.
Contractor shall complete, the adjustmen t of the shoulder elevations and the construction of the earth portion of the shoulder outside the surfaced shoulder width to conform to the typical cross sections shown in the contract, in addition to the above requirements for "Subgrade Preparation".
302.02Material Requirements
302.03Construction Methods
sections shown in the contract. In t he event the subgrade width is less than the width shown on the typical cross sections, the widening shall be accomplished by either:
the shoulder slopes to provide the minimum width will be allowed only if the existing slope is 1 vertical to 4 horizontal or flatter.
shall be no steeper than the slope shown in the contract. Subgrade Preparation, Shoulder Subgrade Preparation, and Preparation of Intersections and Driveways 302.03
- 155 - 3. After stepping and shaping the slopes, the Contractor shall scarify the upper 6 inches (150 mm) of the s ubgrade in all areas to be surfaced.
horizontally to ensure a uniform material throughout the area to be surfaced.
to be surfaced shall be shaped and compacted. The upper 6 inches (150 mm) of the subgrade in these sections shall conform to the cross section requirements shown in the contract.
thoroughly mixed, sections of the subgrade are too sandy to provide a firm and stable foundation for the subseq uent construction operations, these sections shall be stabilized, in accordance with the requirements of
salvaging, stockpiling, and reapplying the salvaged aggregate beyond the surfaced area.
shoulder slopes, flattening embankment slopes, or temporarily stored for use in shoulder construction. Material st ored for shoulder construction shall be placed so that it will always be adequ ately drained. Ditch drainage in cut sections shall be maintained.
subgrade and then place the surface mate rial with a shoulder widener which rides on the traveled way.
compacted.
electronically controlled machine. The machine must provide accurate vertical and horizontal control. Pr ofiling is done before placement of:
the specified line, grade, and crossse ction information. The Contractor shall dispose of excess material removed in profiling.
reference line shall be located along both outer edges of the section being profiled. The reference line shall be ma intained until the specified tolerances have been attained, except when stringless profiling is used.
for profiling shoulders and medians.
when profiling shoulders. Subgrade Preparation, Shoulder Subgrade Preparation, and
Preparation of Intersections and Driveways
- 156 - (3) When the traveled way does receive an overlay or an entirely new surface, then at least one lift of the surface course shall be placed and used as the reference for profiling the shoulder.
for profiling driveways, intersections and irregular areas.
intersections, driveways, irregular areas, narrow areas or roadway grading of 1/2 mile (0.8 km) or less.
±0.05 foot (15 mm) for each point, and the distance between any two points when measured perpendicular to the plan profile shall not exceed 0.05 foot (15 mm).
302.04Method of Measurement
number of overlying square yards (square meters) of rigid or flexible pavement, including intersections and driveways.
and "Shoulder Subgrade Preparation" are measured as follows:
centerline between the beginning and ending points.
intersections and driveways, will not be measured for payment but shall be considered subsidiary to "Subgrade Preparation" or "Shoulder Subgrade Preparation".
100 feet (100 m) without regard to wi dth. Stations will be measured horizontally along the project center line between the beginning and ending points. Areas where no shoulder is required are deducted from the total measured length of shoulder.
compacting the subgrade and adjusting grade lines for intersections and driveways, will be measured by the square yard (square meter) for the areas outside the surfaced traveled way roadbed.
aggregate surfacing on intersections and driveways will not be measured for payment but will be considered subsid iary to “Preparation of Intersections and Driveways". Subgrade Preparation, Shoulder Subgrade Preparation, and Preparation of Intersections and Driveways 302.05
- 157 - 4. Water will be measured by the gallon (liter), applied in increments of 1,000 gallons (MGAL) [Kiloliter]. Excess or wasted water will be estimated by the Engineer and deducted from the volume applied.
302.05Basis of Payment
Subgrade Preparation Station (Sta) [StaM] Subgrade Preparation Square Yard (SY) [Square Meter (m2)] Preparation of Intersections and Driveways Square Yard (SY) [Square Meter (m2)] Shoulder Subgrade Preparation Station (Sta) [StaM] Shoulder Subgrade Preparation Square Yard (SY) [Square Meter (m 2)] Water 1,000 Gallons (MGAL) [ K i l o l i t e r ( k L ) ]
contract, furnishing cohesive soil for subgrade stabilization will be considered "extra work".
constructing the earth portion of the shoulders will not be paid for directly but shall be considered to be subsidiary to shoulder subgrade preparation.
work" when the following conditions exist:
free haul distance specified in Section 209.
and under existing approach slabs, the work of correcting faulty subgrade conditions below 6 inches (150 mm) in depth will be done as "extra work" unless such conditions are caused by the Contractor's operations.
- 158 - SECTION 303 -- SUBGRADE STABILIZATION
303.01Description
"Subgrade Stabilization" bid item:
ends, railroad crossings, or any other physical features.
necessary to conform to the contract.
303.02Material Requirements
Subsection 205.02.
303.03Construction Methods
quantities and distribution of the materials delivered. A copy of the report shall be given to the Engineer at the end of each day when hauling materials.
quantity of soil binder the Contractor shall provide to stabilize subgrade sand.
pass a 1/2 inch (12.5 mm) sieve and at least 60% will pass a No. 10 (2 mm) sieve. The binder shall be pulverized be fore it is mixed with the subgrade sand.
subgrade sand, the upper 6 inches (150 mm) of the subgrade shall be compacted to the optimal stiffness as defined by a deflection target value established by the Engineer. Moisture may be added as necessary to obtain proper compaction. The moisture target value for granular materials shall be established in the field by the Contractor during the compaction process and may be adjusted at the discretion of the Engineer. Once established the target moisture shall not vary by more than +2%.
subgrade shall be profiled in accordance with the requirements of Subsection 302.03. .
contract, correcting faulty subgrade conditions below the 6 inch (150 mm) depth will be performed as "extra work " unless such conditions are caused by the Contractor's operations.
303.04Method of Measurement
Get an email when 302 changes
Nebraska revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.