General Provisions (00100-00999)

300SUBGRADE PREPARATION, FOUNDATION COURSES, BASE COURSES, SHOULDER CONSTRUCTION, AND AGGREGATE SURFACING

NE · 2017 Standard SpecificationsBook pages 185186View official source ↗

- 151 - DIVISION 300 -- SUBGRADE PREPARATION, FOUNDATION COURSES, BASE COURSES, SH OULDER CONS TRUCTION, AND AGGREGATE SURFACING 301 -- GENERAL REQU IREMENTS ......................................................... 153

301.01 General ................................................................................. 153

301.02 Equipment .............................................................................. 153

302 -- SUBGRADE PREPARATION, SHOULDER SUBGRADE PREPARATION, AND PREPARATION OF INTERSECTIONS AND DRIVEWAYS ............................................................................................. 154

302.01 Description ........................................................................... 154

302.02 Material Requirements ........................................................ 154

302.03 Construction Methods ......................................................... 154

302.04 Method of Measurement ...................................................... 156

302.05 Basis of Payment .................................................................. 157

303 -- SUBGRADE STAB ILIZATION ....................................................... 158

303.01 Description ........................................................................... 158

302.02 Material Requirements ........................................................ 158

303.03 Construction Methods ......................................................... 158

303.04 Method of Measurement ...................................................... 158

303.05 Basis of Payment .................................................................. 159

304 -- EARTH SHOULDER CONSTRUCTION ......................................... 160

304.01 Description ........................................................................... 160

304.02 Material Requirements ........................................................ 160

304.03 Construction Methods ......................................................... 160

304.04 Method of Measurement ...................................................... 162

304.05 Basis of Payment .................................................................. 163

305 -- CRUSHED ROCK BASE COURSE ................................................ 164

305.01 Description ........................................................................... 164

305.02 Material Requirements ........................................................ 164

305.03 Construction Methods ......................................................... 164

305.04 Method of Measurement ...................................................... 164

305.05 Basis of Payment .................................................................. 165

306 -- GRANULAR FILL ........................................................................... 166

306.01 Description ........................................................................... 166

306.02 Material Requirements ........................................................ 166

306.03 Construction Methods ......................................................... 166

306.04 Method of Measurement ...................................................... 166

306.05 Basis of Payment .................................................................. 166

307 -- FOUNDATION COURSE ................................................................ 167

307.01 Description ........................................................................... 167

307.02 Material Requirements ........................................................ 167

307.03 Construction Methods ......................................................... 169

307.04 Method of Measurement ...................................................... 171

307.05 Basis of Payment .................................................................. 172

308 -- MEDIAN CONS TRUCTION ............................................................ 173

308.01 Description ........................................................................... 173

308.02 Material Requirements ........................................................ 173

308.03 Construction Method ........................................................... 173

308.04 Method of Measurement ...................................................... 173

308.05 Basis of Payment .................................................................. 173

309 -- CALCIUM CHLORID E TREATMEN T ............................................. 174

309.01 Description ........................................................................... 174

- 152 - 309.02 -- MATERIAL REQUIREMENTS ........................................................ 174

309.03 Construction Method ........................................................... 174

309.04 Method of Measurement ...................................................... 174

309.05 Basis of Payment .................................................................. 174

310 -- ROCK OR GRAVEL SURFACIN G ................................................. 175

310.01 Description ........................................................................... 175

310.02 Material Requirements ........................................................ 175

310.03 Construction Methods ......................................................... 175

310.04 Method of Measurement ...................................................... 175

310.05 Basis of Payment .................................................................. 175

311 -- FURNISH ROCK OR GRAVEL ...................................................... 177

311.01 Description ........................................................................... 177

311.02 Material Requirements ........................................................ 177

311.03 Construction Methods ......................................................... 177

311.04 Method of Measurement ...................................................... 177

311.05 Basis of Payment .................................................................. 177

312 -- REMOVAL AND PROCESSING OF CONCRETE PAVEMENT ..... 179

312.01 Description ........................................................................... 179

312.02 Material Requirements ........................................................ 179

312.03 Construction Methods ......................................................... 179

312.04 Method of Measurement ...................................................... 179

312.05 Basis of Payment .................................................................. 179

313 -- CRUSHED ROCK EMBEDMEN T ................................................... 180

313.01 Description ........................................................................... 180

313.02 Material Requirements ........................................................ 180

313.03 Construction Methods ......................................................... 180

313.04 Method of Measurement ...................................................... 180

313.05 Basis of Payment .................................................................. 180

- 153 - SECTION 301 -- GENERAL REQUIREMENTS

301.01 General

1.Compaction requirements are shown in the contract.
2.The Contractor shall be responsi ble for the repair and restoration of any roadbed damage, loss of stability, or rutting caused by the hauling operations.
3.Maintenance of the granular f ill, base course, foundation course, and subgrade for both roadway and shoulders shall be the responsibility of the Contractor until overlying pavement is complete and accepted by the Engineer. This maintenance shall be cons idered subsidiary to the items for which direct payment is provided.

301.02 Equipment

1.Operation:
a.All equipment shall be kept in satisfactory working condition.
b.Equipment shall be operated within the manufacturer's specifications.
c.The Contractor shall perfo rm the tests and calibrations on all equipment. In the event problems are encountered during the tests and calibrations, the Contractor shall arrange for a trained technician or company representative to make the necessa ry repairs or adjustments to the equipment. Calibrations shall be made as often as is deemed necessary by the Engineer, at no additional cost to the Department.
2.The hauling equipment shall consist of trucks equipped for dumping material into spreader boxes or in a windrow. They shall be constructed and maintained to prevent loss of materials during hauling operations.
3.Water Distributors:
a.The distributor equipment sh all provide accurate and uniform distribution of water. The control valves shall close fully to prevent leakage.
b.Water will be measured through a meter or with calibrated tanks in gallons (liters). The weight of the water can also be measured and converted to Megagallons (kiloliters).
4.The equipment used for profiling the subgrades, base courses, and foundation courses shall be capable of meeting Construction Methods.
5.Only compacting equipment and methods which will consistently produce the compaction specified thro ughout the depth of the compacted lifts shall be used. Compacting equipment which produces laminations within the compacted lifts will not be allowed.
6.Equipment used to spread the material shall be capable of distributing the material uniformly.
7.Equipment for weighing loaded trucks shall comply with requirements given in Subsection 503.03.
Source: Nebraska Standard Specifications for Highway Construction, 2017 Edition. Pages 185186 of 1,048.