New Hampshire Department of Transportation Standard Specifications – 2016
Description
1.1This work shall consist of clearing and grubbing within the limits shown on the plans or as ordered, except objects designated
to be removed in accordance with other sections of these Specifications. Vegetation and objects designated or ordered to remain shall be preserved from injury or damage.
1.2This work shall also consist of clearing and grubbing areas of brush within the project limits, but outside the limits of clearing
and grubbing shown on the plans
1.3The items of removing trees, pruning trees, removing stumps, roadside clean up, and selective clearing and thinning will be
used for work performed outside of the areas designated under 1.1 and 1.2.
1.4Definitions:
above the average ground. Construction Requirements
3.1Clearing and Grubbing.
3.1.1 No trees shall be cut until designated by the Engineer. Particular reference is made to fruit, ornamental or shade trees or plants at the edge of the roadside slopes. Cut or scarred surfaces of trees or shrubs selected for retention shall be pai nted with an approved wound dressing or treated according to other accepted arboricultural practices. 3.1.1.1 The Contractor may be required to file an intent to cut and shall pay all charges, fees, and taxes as may be required under Chapter 79 of the RSA. 3.1.2 All trees ordered to be cut shall become the property of and shall be disposed o f by the Contractor, except as provided hereinafter. In the interest of energy and material conservation, the Contractor shall salvage wood from cut trees in accordance with standard commercial logging practices. 3.1.3 Unless otherwise shown on the plans, clearing and grubbing shall extend 10 ft. beyond areas of excavation and 5 ft. beyond embankment slopes. 3.1.4 The Contractor shall perform the work of clearing and grubbing to include the removal of only the materials specified herein. In order to conserve topsoil, rake teeth on bulldozers shall be used when removing stumps and brush unless other equipment is permitted. 3.1.5 Except in areas designated to be excavated, any excavation caused by the grubbing operations shall be filled with suitable material and compacted to conform to the surrounding ground. 3.1.6 All stumps and large roots within the limits of the roadbed shall be completely rem oved to a depth of 3 ft. below subgrade unless a greater or lesser depth is specified on the plans. Stumps wit hin the limits of the roadbed below such depth and stumps under embankments or outside the roadbed shall be cut off within 6” of the existing ground surface except in the area to be rounded at the top of backslopes, where stumps are to be cut off flush wit h the surface of the final slope line or removed at the Contractor’s option. 3.1.6.1 When stumps are designated to be removed by grinding, the Contractor shall use an approved stump -grinding machine such that no damage occurs to surrounding structures. 3.1.7 All stumps, roots, branches, brush, weeds, and other perishable material resulting from the clearing and grubbing operations shall be disposed of by an approved method. The Contractor 's attention is directed to RSA 149- M regarding the fact that stumps and roots from grubbing operations are classified as solid waste. As such, these stumps shall be disposed of in permitted sites, through firms having facilities to convert the stumps to marketable products, or by grinding or chipping. Permits for sites are obtained from the New Hampshire Department of Environmental Services, Division of Waste Management. It is the responsibility of the person disposing of the stumps to obtain all the necessary permits and to comply with the New Hampshire Solid Waste Rules and Design Standards in effect at the time of disposal.
New Hampshire Department of Transportation Standard Specifications – 2016 3.1.7.1 All wood less than 5” in diameter and not cut into 4 ft. lengths for firewood shall be chipped. Burying of brush will not be permitted. Stumps, roots, and rotten wood may be buried at approved sites on or off the project. Approved sites shall have a minimum of 24” of cover material and shall be graded and shaped as directed by the Engineer. If burial is to be on private land, the agreements as to how the area is to be left shall be set fo rth on the Disposal Agreement form provided by the Department in accordance with 106.10. Three signed copies of the Disposal Agreement shall be furnished to the Engineer. Approval of the proposed disposal area will be contingent upon agreement by the Contractor and the property owner to leave the area in such shape that it blends with the surrounding terrain and that erosion is kept to a minimum. Without special permission, slopes shall not be left steeper than 3:1 (horizontal to vertical). No disposal area shall be left in such condition that erosion, after completion of the work, might result in water pollution by silt or other deleterious substances. Areas shall be left in such shape and condition that material does not wash and block or obstruct drainage ways. If holes caused by settlement appear, they shall be filled as directed. A release from the property owner is required prior to final project acceptance. 3.1.7.2 Except in the case where wood is piled neatly for future use, storage locations should be outside the limits of view from the project, other highways, and residences. 3.1.7.3 When ordered, available chipped material shall be stockpiled in the quantity directed to be used for erosion control. The Contractor may market any remaining chips or dispose of them by other approved methods. 3.1.7.4 Unless otherwise ordered, disposal areas shall be covered with material capable of supporting vegetation and either fertilized and seeded with grass seed or planted with seedlings. Seedlings shall be set out in accordance with accepted horticultural practices as directed in the agreement. 3.1.7.5 Unless permission is given to preserve access roads to disposal areas adjacent to highways, such access roads shall be obliterated. 3.1.8 When fence lines go through wooded areas, a strip 3 ft. wide shall be cleared for the fence line.
3.2Roadside Cleanup.
3.2.1 Roadside cleanup of leaning, dead, unsound, and unsightly trees, branches, stubs, refuse, and slash (material remaining after logging operations), generally to a limit of approximately 15 ft. outside the limits specified in 3.1.3 above, shall be performed where and as directed. The material shall be disposed of as provided in 3.1. This work will not ordinarily be required outside of the right-of-way lines, but the Engineer may order that portions of medians or entire medians be cleaned up under this Section. All tree trimming in connection with roadside cleanup shall be done in accordance with accepted tree surgery practices.
3.3Trimming of Trees.
3.3.1 On trees or shrubs designated to remain, low hanging, unsound, or unsightly branches shall be removed as directed. Branches of trees extending over the roadbed shall be trimmed to g ive a clear height of 20 ft. above the roadbed surface. All trimming shall be done in accordance with accepted tree surgery practices.
3.4Invasive Species.
3.4.1 Statutory authority of RSA 430:55, the NH Department of Agriculture, Markets, and Foods prohibits the spread of invasive plants listed in Table 3800.1 of Part AGR 3800. Follow best management practices (BMPs) to avoid spreading these plants to new sites. The NHDOT manual “ Best Management Practices for Roadside Invasive P lants” is available on line at the Department’s Website or through the NHDOT Records Section (603) 271-1601. Method of Measurement
4.1Clearing, grubbing, and clearing and grubbing will not be measured , but shall be the acre final pay quantity in accordance
with 109.11 for the area(s) shown on the plans. 4.1.1 Clearing for fence lines will not be measured, but shall be the acre final pay quantity in accordance with 109.11 for the area(s) shown on the plans.
4.2Trees will be measured by the number of trees of each size removed or pruned.
4.3Stumps will be measured by the number of stumps removed measuring more than 12” in circumference at the cutoff. Stumps
of trees cut by the Contractor will not be measured.
4.4Roadside cleanup will be measured by the acre, to the nearest 0.01 acre.
4.5Selective clearing and thinning will not be measured , but shall be the acre final pay quantity in accordance with 109.11 for
the area(s) shown on the plans.
New Hampshire Department of Transportation Standard Specifications – 2016 Basis of Payment
5.1Clearing, grubbing, and clearing and grubbing are final pay quantity items and will be paid for at the Contract unit prices per
acre in accordance with 109.11. 5.1.1 When no quantity for clearing and grubbing is included in the Contract, the work will be subsidiary. 5.1.2 Clearing for fence lines is a final pay quantity item and will be paid for at the Contract unit price per acre in accordance with 109.11. 5.1.3 When no quantity for clearing for fence lines is included in the Contract, the work will be subsidiary. 5.1.4 Clearing and grubbing in areas of brush within the project limits, but outside the limits shown on the plans will be subsidiary.
5.2The accepted quantities of removed trees and their stumps will be paid for at the Contract unit price per each of the size of
tree specified. 5.2.1 When an item for removing trees but no item for removing stumps appears in the Contract, each stump shown on the plans as a tree and removed as ordered will be paid for at one-half the Item Bid Price of a tree of the respective size shown. 5.2.2 This item will not include trees and stumps removed from areas paid for under clearing and grubbing, roadside cleanup, or trees or stumps previously disposed of. 5.2.3 When there is no item for removing small trees and there is an item for large trees, small trees shall be paid for at one- half the Item Bid Price of large trees; conversely large trees shall be paid for at two times the Item Bid Price for small trees. 5.2.4 When no quantity for large trees and their stumps is included in the Contract, the removal of large trees and their stumps will be paid for as provided in 109.04. 5.2.4.1 When no quantity for small trees and their stumps is included in the Contract, the removal of small trees and their stumps will be subsidiary.
5.3The accepted quantity of stumps will be paid for at the Contract unit price per each.
5.3.1 When no quantity of stumps is included in the Contract, the removal of stumps will be subsidiary.
5.4The accepted quantity of roadside cleanup will be paid for at the Contract unit price per acre.
5.4.1 When no quantity of roadside cleanup is included in the Contract, work ordered of such nature will be paid for as provided for in 109.04.
5.5Trimming of trees where directed outside of the areas measured under the item of roadside cleanup will be paid for as provided
for in 109.04.
5.6Selective clearing and thinning is a final pay quantity item and will be paid at the Contract unit price per acre in accordance
with 109.11. Pay items and units:
201.01Clearing (F) Acre
201.02Grubbing (F) Acre
201.1Clearing and Grubbing (F) Acre
201.21Removing Small Trees Each
201.22Removing Large Trees Each
201.31Tree Pruning, Small Trees Each
201.32Tree Pruning, Large Trees Each
201.4Removing Stumps Each
201.51Roadside Cleanup Acre
201.6Clearing for Fence Lines (F) Acre
201.7Selective Clearing and Thinning (F) Acre
201.89Fertilizing Individual Trees Ton
----- Trimming of Trees Extra Work
New Hampshire Department of Transportation Standard Specifications – 2016
Description
This works hall consist of the demolition, removal and satisfactory disposal of buildings, including contents, foundations,
above ground fuel storage tanks in and adjunct to buildings, decommissioning of septic systems and wells, and other obstructions pertaining thereto, as designated on the plans or in the Contract.
The work shall also consist of the removal and salvage, satisfactory disposal of pipes or filling abandoned pipes with flowable
fill, and other items as designated on the plans or ordered.
When the item of demolishing buildings is shown as “ subject to prior removal”, the Department reserves the right to arrange
for the removal or demolition of the building or buildings that have been designated on the plans to be removed by others pri or to a specified date. If the buildings have not been completely removed by others prior to that date, the work to be done shall be th at described in 1.1 and 1.4.
Salvaging of designated materials; removing or breaking up, as ordered, of septic tanks; backfilli ng any resultant spaces,
trenches, holes, or pits including dug wells and cesspools; furnishing and erecting temporary barricades; and the final grading and cleaning up of the site shall be included under this work unless such work is included under other items in the Contract. Material Requirements
2.1Backfill material shall conform to AASHTO M 57 using the definitions given in AASHTO M 146, except the density
requirements shall conform to 203.3.8.
2.2Flowable fill for filling abandoned pipes shall consist of materials conforming to Section 520 .
Portland Cement (Type II) 20 lb. Ground Granulated Blast Furnace Slag 100 lb. Sand 2,830 lb. Water 40 - 50 gal Air Entrainment 10 - 15 percent Construction Requirements
General.
3.1.1 The Contractor's attention is directed to 104.04 . The Contractor must also comply with all Federal, State, and local laws and regulations for removal, transportation, and disposal of structures and obstructions. As ordered, the Contractor shall raze, remove, and dispose of all buildings and foundations, structures, guardrail, fences, and other obstructions any portions of w hich are on the right -of-way except utilities and those obstructions for which other provisions have been made for removal. All designated salvageable material shall be removed without unnecessary damage in sections or pieces that are readily transportable, and shall be stored by the Contractor at specified places within the project limits. Unusable perishable material shall be destroyed. Nonperishable material not designated for salvage shall be buried as directed or, with written permission of the property owner, may be disposed of off the project prov ided that the material remains outside the limits of view from the project, other highways, and residences. Copies of all such agreements with property owners shall be furnished to the Engineer. If disposal is by burial on private land, it must be in accordance with 106.10. 3.1.2 Blasting or other operations necessary for the removal of an existing structure or obstruction, which may damage new construction, shall be completed prior to placing the new work. 3.1.3 Foundations and holes resulting from operations, except within the limits of subsequent excavation, shall be backfilled in accordance with the provisions of Section 203. If caving has occurred, the caved material shall be r emoved before backfilling is undertaken. All excavated material shall be used or disposed of in accordance with the provisions of Section 203.
Demolishing Buildings.
3.2.1 In the case of buildings to be demolished, the Engineer will notify the Contractor when any building becomes available. Upon notification of availability, ownership of the building or buildings, including all equipment, fixtures, building materials, and debris remaining on the lot, except facilities belonging to a public or private utility company, shall transfer from the State to the Contractor. 3.2.2 The Contractor shall ascertain whether any water, sewer, gas, electric, cable TV, or telep hone services are still connected to the building; if so, the Contractor shall disconnect and terminate all services in compliance with the requirements of the controlling municipality or company and then proceed with the demolition of the building. 3.2.3 The Contractor shall protect all openings resulting from demolition or removal by use of temporary barricades as necessary for the protection and safety of the public. All barricades and obstructions shall be illuminated at night when or dered.