108.06 and 109.05. The Engineer will notify the Contractor of its determination whether or not an
adjustment to the Contract Documents is warranted. Failure of the Engineer to suspend or delay the Work in writing does not bar the Contractor from receiving a time extension or added compensation according to 108.06 or 109.05. The Department will not make an adjustment under this subsection in the event that performance is suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this Contract.
D.Significant Changes in Character of the Work. The Engineer may increase or decrease quantities and alter the Work as necessary to complete the Project. The Engineer will make appropriate adjustments according to 108.06 and 109.05, if such alterations significantly change the character of the Work. If the Contractor disagrees as to whether an alteration constitutes a significant change, use the notification procedures specified in 108.02.F. The term “significant change” is defined as follows: 1.when the character of the Work as altered differs materially in kind or nature from that involved or included in the original proposed construction; or
2.when the product of the quantity in excess of the estimated quantity of a contract item and the unit price exceeds the limits set forth in Table 104.02-1. TABLE 104.02-1 Contract Price Contract Limits Up to $1,000,000 $50,000 $1,000,001 to $2,000,000 5% of Total Contract Price Over $2,000,000 $100,000 A quantity underrun is defined as follows:
a.the estimated quantity of a contract item exceeds four units (this minimum quantity does not apply to pavement markings measured in units of miles), and
b.the decrease in quantity of any unit price Contract Item exceeds 25 percent of the estimated quantity, and
c.the total of all such adjustments for all Contract Items is more than $400. Then after the determination of final quantities according to 109.12.C, the Engineer will adjust the unit prices for the affected Contract item by multiplying the bid unit price by the factor obtained from Table 104.02-2. TABLE 104.02-2 % Decrease Factor % Decrease Factor 25 1.08 57 1.33 26 to 27 1.09 58 1.35 28 to 29 1.10 59 1.36 30 to 31 1.11 60 1.38 32 to 33 1.12 61 1.39 34 to 35 1.13 62 1.41 36 1.14 63 1.43 37 to 38 1.15 64 1.44 39 1.16 65 1.46 40 to 41 1.17 66 1.49 42 1.18 67 1.51 43 1.19 68 1.53 44 to 45 1.20 69 1.56 46 1.21 70 1.58 47 1.22 71 1.61 48 1.23 72 1.64 49 1.24 73 1.68 50 1.25 74 1.71 51 1.26 75 1.75 52 1.27 76 1.79 53 1.28 77 1.84 54 1.29 78 1.89 55 1.31 79 1.94 56 1.32 80 and over 2.00 When the increase in quantity or decrease in quantity of any unit price contract item does not exceed the limits set forth in Tables 104.02-1 and 104.02-2, the change is considered a minor change. The Department will pay for minor changes in the Work at the unit bid price. E.Eliminated Items. The Department may partially or completely eliminate contract items. The Department will only make an adjustment to compensate the Contractor for the reasonable cost incurred in preparation to perform significantly changed work as set forth in 104.02.D or work completely eliminated prior to the date of the Engineer ’s written order to significantly change or completely eliminate the Work. The adjustment will be determined according to 109.04 and 109.05. Such payment will not exceed the price of the Contract Item. The Department will not seek a savings for maintaining traffic, mobilization, and construction layout stakes items for Eliminated Items of Work, unless there is a significant change. F.Extra Work. Perform Extra Work as directed by the Engineer. The Department will pay for Extra Work as specified in 109.05. Time extensions, if warranted, will be determined according to 108.06. G.Unilateral Authority to Pay. The Department has unilateral authority to pay the Contractor sums it determines to be due to the Contractor for work performed on the project. This unilateral authority to pay by the Department does not preclude or limit the rights of the Department and the Contractor to negotiate and agree to the amounts to be paid to the Contractor.
104.03 Rights in and Use of Materials Found on the Work. Upon obtaining the Engineer ’s
approval, the Contractor may use material, such as stone, gravel, or sand, found in the plan excavation for another Contract Item. The Department will pay for both the excavation of the material under the corresponding Contract Item and for the placement of the excavated material under the Contract Item(s) for which the excavated material is used. Excavate or remove material only from within the grading limits, as indicated by the slope and grade lines. Obtain written permission from the Engineer according to 107.11.A.
104.04 Cleaning Up. Maintain the Project in a presentable condition. Remove all rubbish, layout
stakes, sediment control devices as directed by the Engineer, excess material, temporary structures, and equipment, including stream channels and banks within the Right -of-Way at drainage structures, and all borrow and waste areas, storage sites, temporary plant sites, haul roads, and other ground occupied by the Contractor in connection with the Work. Establish suitable vegetative cover in these areas by seeding and mulching according to Item 659, except for cultivated fields. Leave the Project site in an acceptable condition as determined by the Engineer. The cost of cleanup is incidental to all contract items. The Department may withhold 10 percent of the Bid amount for the mobilization contract item, if included, until performance under this section is complete. See 624.04.
Source: Construction and Material Specifications, 2023 (rev. 7/17/2026) Edition. Pages 20–24 of 892.