623.10 560 Provide equipment, software, and all three dimensional models needed to verify layout, perform check sections, and document pay items. Train the Engineer on how to use the provided equipment and software and provide technical assistance during the duration of the Work. Upon completion of the Work, the electronic equipment, computer a nd software will remain the property of the Contractor. If using GNSS methods to construct the project and a pay item for providing electronic instrumentation is not specified, provide the Engineer with the three dimensional models in electronic format whe n requested. Provide the models at no additional expense to the Department.
623.10 Method of Measurement . Estimated quantities for replacement of
Primary Project Control Monuments, Monument Assemblies, Reference Monuments, and Right -of-Way Monuments expect ed to be destroyed that are within the project construction work limits are included in the Contract Documents. Estimated quantities for new monuments are also included in the Contract Documents. Primary project control monuments, monument assemblies, refe rence monuments, Right -of-Way monuments, and boundary monuments on or outside the project construction work limits are the Contractor’s responsibility to protect and restore as required. The Department will not pay for restoration of these items.
623.11 Basis of Payment . Payment for Construction Layout Stakes and
Surveying includes payment for Right -of-Way staking and verifying the location of existing survey monuments. The Department will consider the cost for locating new survey monuments to be included in the unit price bid for the survey monument. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 623 Lump Sum Construction Layout Stakes and Surveying 623 Lump Sum Providing Electronic Instrumentation 623 Each Primary Project Control Monument, Type A 623 Each Primary Project Control Monument, Type B 623 Each Monument Assembly 623 Each Reference Monument 623 Each Right -of-Way Monument ITEM 624 MOBILIZATION
624.01 Description
624.02 Limitation
624.03 Method of Measurement
624.04 Basis of Payment
624.01 Description. This work consists of the preparatory work and operations
including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project s ite; for the establishment of all 624.02 561 field offices, buildings, and other facilities necessary for work on the project; for all other work and operations that must be performed or costs incurred before beginning the Work on the other contract items; and for de mobilization. If Mobilization is not included as a pay item in the Contract, the Department will not pay for this work separately but will consider it incidental to the other Contract Items.
624.02 Limitation. The Department will limit the sum of the parti al payments
specified in 624.04.A and 624.04.B to the amounts shown in Table 624.02 -1 under “Maximum Total of Partial Payments”. The Department will pay the balance of the lump sum amount bid, as specified in 624.04.C. TABLE 624.02 -1 Total Contract Amount Maximum Total of Partial Payments More than Up to, inclusive ($) ($) ($) 0 50,000 0 50,000 100,000 2,000 100,000 200,000 4,000 200,000 500,000 10,000 500,000 1,000,000 20,000 1,000,000 2,000,000 40,000 2,000,000 5,000,000 100,000 5,000,000 10,000,000 200,000 10,000,000 20,000,000 400,000 20,000,000 40,000,000 800,000 40,000,000 60,000,000 1,200,000 60,000,000 80,000,000 1,600,000 80,000,000 -- 2,000,000 If the lump sum amount bid for Mobilization exceeds the total shown in Table
624.02 1 for partial payments, the Department will pay the excess upon completion
of the project.
624.03 Method of Measurement. The Department will measure Mobilization
as a unit, acceptably performed.
624.04 Basis of Payment. The Department will make part ial payments
according to 109.09 and as modified by the following schedule:
625.01 Description
625.02 Definitions
625.03 Codes
625.04 Permits
625.05 Materials
625.06 Shop Drawings
625.07 Incidentals
625.08 Luminaires
625.09 Luminaire Supports
625.10 Foundations
625.11 Junction Boxes (Handholes) & Pull Boxes (Manholes)
625.12 Raceways and Conduits
625.13 Trenching
625.14 Jacking or Boring
625.15 Power Service (Control Equipment)
625.16 Grounding
625.17 Wiring and Cabling
625.18 Connections
625.19 Testing of Installations
625.20 Plastic Caution Tape
625.21 Removal of Lighting Equipment
625.22 Method of Measurement
625.23 Basis of Payment
625.01 Description. This work consists of furnishing and installing highway
lighting equipment complete and ready for service. This work shall also include necessary excavation and backfill, disposal of discarded materials, restoration of disturbed facilities and surfaces, and testing as specified.
625.02 Definitions. Lighting terminology herein is defined in the American
National Standard Practice for Roadway Lighting.
625.03 Codes. Follow the National Electrical Code, as adopted by the State of
Ohio, The National Electrical Safety Code and local codes where applicable.
625.04 Permits. Obtain all permits required as an incidental to the construction
of the lighting installation. 625.05 563 625.05 Materials. Furnish materials conforming to: Concrete QC Misc or QC 1 ................................ .. 499, 511 Reinforcing steel ................................ ..................... 509.02 Sand ................................ ................................ ........ 703.06 Cable ................................ ................................ ....... 725.02 Unit type duct -cable systems ................................ .. 725.03 Conduit ................................ ..... 725.04, 725.051, 725.052 Pull boxes ........................ 725.06, 725.07, 725.08, 725.12 Junction boxe s ................................ ........................ 725.10 Luminaires ................................ .............................. 725.11 Lamps ................................ ................................ ..... 725.11 Cable connectors and connector kits ....................... 725.15 Cable splicing kits ................................ ................... 725.15 Ground rods ................................ ............................ 725.16 Power service components ................................ ...... 725.19 Wood service poles ................................ ................. 725.19 Multiple cell conduit ................................ ............... 725.20 Anchor bolts and nuts ................................ ............. 725.21 Light poles ................................ .............................. 725.21 Light towers ................................ ............................ 725.21 Portable power units ................................ ............... 725.21 Plastic caution tape ................................ ................. 725.22
625.06 Shop Drawings . Submit, to the Engineer prior to incorporation, two
copies of the shop drawings and catalog cuts which identify and describe each manufactured item which is being incorporated into the construction. Certify in writing that each manufactured item is in conformance with all contract requirements for that item. Ensure that the documents describing each item indicate the project number (including th e construction year) and the bid reference number under which the item is being installed and that the documentation contains all of the information needed to allow the Engineer to determine that the item to be supplied meets all applicable requirements al ong with all of the information needed by the maintaining agency to obtain an identical replacement unit from the manufacturer. When a given item is to be incorporated into the construction under multiple bid item reference numbers, furnish a separate and complete documentation package for each bid item reference number under which the item is to be installed. When multiple items are to be incorporated under a single bid reference number, submit the documentation for all such items together.
625.07 Inciden tals. Furnish and install all incidentals necessary to provide a
complete and practical working unit or system.
625.08 Luminaires . A luminaire consists of a housing with a lamp, a lamp
socket, the optical components to direct the output from that lamp, and the electrical components needed to operate the lamp. Ensure that luminaires of the same type (i.e. high mast, low mast, conventional, underpass, post top, etc) in a given installation (i.e. interchange, rest area, weigh station, etc.) are of the same bra nd. 625.09 564 Align each luminaire vertically and horizontally to the roadway as specified. Where the profile grade exceeds 4 percent and the luminaire is mounted less than 60 feet (18 m) above the roadway, adjust the luminaire to be perpendicular to the roadway rat her than gravimetric level. At the locations designated in the plans or as directed by the Engineer, furnish and install glare shields obtained from the manufacturer of the luminaire. Apply a clearly -visible, liberal coating of metal -free molybdenum disulf ide and graphite -based anti -seize compound to all fasteners used in accessing the lamp for replacement. After all other work has been completed, clean the reflector, refractor and other components of the optical assembly just prior to leaving the job.
625.09 Luminaire Supports. Luminaire supports fall into three categories:
bracket, light pole, light tower. A bracket is the attaching hardware used to mount a luminaire onto the face of a wall or pier cap, or hang a luminaire from the bottom of a deck or bea m or other similar installation. A bracket is often supplied for the luminaire by the luminaire manufacturer to facilitate the installation of the luminaire. A more complex situation will require extensive work to fabricate a bracket for the situation. A light pole is the pole with one or more fixed brackets or arms for supporting luminaires above the roadway to be lighted. A light pole also includes a lower portion of the pole which is embedded or a mounting plate, any base for housing components or wiring , and when specified a breakaway device such as a frangible base, frangible couplings or slip plates. A light tower is a shaft with a base plate, head frame, ring or similar structure on which one or more luminaires are mounted with a mechanism for lowerin g the mounting ring and luminaires for servicing and a lightning protection system. Ensure that luminaire supports of the same type (i.e. high mast, low mast, conventional, underpass, post top, etc.) in a given installation (i.e. interchange, rest area, we igh station, etc.) are of the same brand. Plumb each light pole and each light tower. When shims are used, use only shims of an approved design and installed in an approved manner. Do not install more than the minimum number needed to plumb the pole and ne ither exceed the maximum allowed total thickness of the shim pack nor the maximum number of shims permitted. When leveling nuts are used, ensure that such nuts are installed in approved locations and that both the anchor and the leveling nuts are properly tightened according to AASHTO LTS -6 (Specifications for Structural Supports for Highway Signs, Luminaires, and Traffic Signals, 2013) section C5.17.5.2. Ensure that the grounding connections for each light pole or light tower have been made and that the re sultant ground is within the earth resistance limit specified Apply a suitable lubricant to prevent seizing to each cover fastener and install all such fasteners. After erection, the Engineer shall inspect each pole for defects in the surfaces and determ ine for each defect discovered whether the defect is minor enough that the 625.10 565 Contractor may be allowed to field repair the finish or major enough that the Contractor must replace the pole. Make finish repairs and provide and install replacement poles as dire cted by the Engineer for no additional charge to the project. Label each light pole and light tower with the alpha numeric identifier. Place the identifier on the quadrant of the surface of the pole that faces oncoming traffic at approximately 7 feet (2 m eters) above the roadway surface. Apply the identifier letters and numerals when the ambient air temperature, the temperature of the labeling material and the temperature of the surface to which the labels are applied are all above 40° F (4° C). Identifica tion of the light poles or light towers and the removal of any previous such identifier in the case of light poles or light towers being reassigned shall be considered as incidental work.
625.10 Foundations. Excavate for each foundation to the dimensions g iven.
If a cave in should occur during excavation, excavating using casing, sleeving or other methods may continue with the approval of the Engineer. Where, in the opinion of the Engineer, the excavation for a foundation has revealed an unstable condition at the bottom of the excavation, drill the foundation shaft deeper, enlarge the diameter of the drilled shaft, or make other modification to the foundation as directed by the Engineer who shall initiate the appropriate arrangements to compensate the Contr actor for the addition work required. When rock is encountered, continue excavation to a minimum of 3 feet (1 meter) into rock. The Engineer may then decrease the total depth of the foundation to not less than 6 feet (2 meters) for a light pole or 10 feet (3 meters) for a light tower. Reinforce each foundation with steel as specified and such steel reinforcing shall be placed in accordance with 509. Install the anchor bolts for the light pole or light tower in each foundation using anchor bolt setting templates. Place Class QC Misc or QC 1 concrete for the foundation in accordance with 511 except that forms will not be required for portions of founda tions extending more than 6 inches (150 mm) below the ground line, unless the soil does not have sufficient stability to stay in place during the placing of the concrete. Finish the top of each foundation smooth and level. After forms have been removed, ba ckfill the excavated spaces around each foundation with suitable material placed and tamped in thin layers as directed by the Engineer.
625.11 Junctions Boxes (Handholes) & Pull Boxes (Manholes).
Furnish and install a junction box of the size and type spec ified. Furnish each junction box embedded in concrete with a drain. Lubricate each cover screw with a compound to prevent the screw from seizing and install all cover screws. Furnish and install a pull box of the size and type specified. Excavate for each pull box as nearly as practicable to the outside dimensions of the pull box. Install a 6 inch (150 mm) gravel base with a 4 inch (100 mm) underdrain to a suitable outlet below each pull box. After setting the pull box to proper grade, backfill the 625.12 566 excavate d spaces around the pull box with suitable material placed and thoroughly tamped in thin layers. When a pull box is to be installed in a paved area, remove an adequate area of the paving by saw cutting the sides of the area to be removed, or by removal of the paving back to an expansion joint as instructed by the Engineer. After setting the pull box to proper grade, backfill the excavated spaces around the pull box with suitable material placed and thoroughly tamped in thin layers, and restore the pavement base and paving to match the surround. Metal pull box lids shall be bonded by attachment of the equipment grounding conductor to the frame diagonal and a braided strap.
625.12 Raceways and Conduits. Furnish and install conduit of the sizes and
types specified. When the location, type or size of a conduit has not been indicated, submit to the Engineer working drawings showing the location and size and type of each such conduit along with the number an d size of wires contained in each such conduit and secure the approval of the Engineer prior to installing the conduit. Use of consuit material shall comply with the NEC. When not otherwise specified, all conduit and fittings on an individual run of condui t shall be of the same material except for approved manufactured transition fittings required at end of the run when the item into which the conduit terminates is not of the same material as the conduit. HDPE conduit shall not be used where exposed, or wit hin buildings. Install each conduit with a minimum amount of bending and ensure that the total bending between adjacent access points (junction boxes, pull boxes, light poles, control equipment enclosures, etc.) does not exceed 270 degrees. Do not bend any conduit to a bend radius of less than 12 times the internal diameter of the conduit. Bend each conduit in such a manner as to avoid damage to the conduit and any protective coating and such that the internal diameter of the conduit will not be reduced. Use watertight hubs for all conduit penetrations of outdoor electrical enclosures. Do not make such penetrations using locknuts onto threaded conduit ends. Remove the rough edges from the cut end of each conduit. In addition, ream the cut end of each metal lic conduit. Bush each end of each conduit to further protect the wire insulation and cable jackets from damage. Where threads have been cut onto ferrous metallic conduit after galvanizing, paint the threaded area with a UL -Listed anti -corrosion compound i n such a manner that there will be no unprotected surfaces. Make each conduit joint tight to provide structural integrity in all conduits and to electrically bond the jointed sections of metallic conduit. Provide an equipment grounding conductor that is no t in a jacketed cable assembly in metallic conduits when not otherwise available and bond the conduit to this grounding conductor. Securely fasten onto or build into the structure each conduit. 625.13 567 Install the appropriate expansion or deflection joint in each conduit at all locations where movement must be accommodated (such as expansion joints on structures) and install suitable bonding to assure electrical continuity of the grounding system. Bond all metallic items enclosing electrical conductors together and to good earth ground. Furnish each enclosure, junction box, pull box and conduit with a drain. When the low point of a conduit does not occur at a drained access point, install a T coupling at the low point of the run and route the side outlet to drain. Where underground conduits are to be encased in concrete, use Class QC Misc or QC 1 concrete and furnish a minimum of 3 inches (75 mm) of concrete on all sides using spacers. After installation of the conduit and prior to installing the cables, run a mandre l whose diameter is at least 90% of the interior diameter of the conduit through the conduit. If the new conduit contains cabling, install a flat woven polyester pulling tape, rated for 600 pound minimum, in the conduit. If the new conduit is to remain emp ty, install an HDPE insulated copper tracer wire, 12 AWG minimum, in the conduit. Allow for 10 feet of slack in each adjacent pull box. Temporarily seal the ends of a conduit immediately after placement of conduit when the conductors or cable cannot be ins talled promptly. After installing the wire or cable and conduit bushings, seal all open conduit ends. Use polymer -based, mineral -filled reusable non -drying elastic duct sealing putty identified for use with the cable insulation, shield or other components. Do not use expanding foams or foam of any kind.
625.13 Trenching. Follow the routing shown on the plan. Keep the trench
within 6 inches (150 mm) of the designated line where the trench is adjacent to and parallel with a curb or pavement. In unpaved areas, a plow may be used in lieu of trenching with the approval of the Engineer. Use a machine that can install the duct uniformly at the specified depth without stretching or abrading the duct and which leaves a narrow self closing slit which presents no signi ficant hazard during the self closing period. In unpaved areas, make the trench a minimum of 2 feet (0.6 m) deep and not more than 12 inches (300 mm) in width. Backfill the trench in layers not more than 6 inches ( 150 mm) in loose depth and compact each layer with a mechanical tamper or other approved method as directed by the Engineer. Use suitable soil to backfill a trench in earth. Use granular material to backfill a trench in an aggregate or in chemically stabilized subgrade . Ensure that the bac kfill material around and in the first 4 inches (100 mm) above the top of unit type duct cable not encased in concrete is sand or earth with no stones larger than 1/2 inch (13 mm). In paved areas, either make a slit or T type trench. Cut the pavement along existing joints or grooves where possible. Mark the pavement with cut lines and secure the Engineer’s approval of the location of the cut before cutting the pavement. 625.14 568 625.14 Jacking and Boring. In addition to the requirements of 625.12 to furnish and install conduit, use jacking or horizontal boring when the plan calls for such methods to be used. Use these methods in lieu of trenching only with the approval of the Engineer. Jack only rigid galv anized steel conduit. Use only a machine designed for jacking conduit not the bucket or blade of a machine designed for earthwork. Horizontal boring may be used to install any conduit or duct which has the adequate strength, flexibility and joints to withs tand the process. Make the diameter of the bore no more than 20 percent larger than the outside diameter of the conduit or duct being installed.
625.15 Power Service. Furnish and install all equipment necessary to provide a
complete electrical service to the roadway lighting facilities. Follow the National Electrical Code (NEC) Article 400 for enclosures, in the construction of all enclosures for power service and lighting control centers. The power service equipment includes, but is not necessarily limite d to: poles or other support structure for the mounting of the equipment, hardware for dead ending an overhead service drop or trench and conduit for receiving an underground service line, NEC Article 285 Type 1 (Surge Arrestor) surge protector device (SPD ), meter base, customer service disconnect, magnetically held lighting contactor, photoelectric cell and Hand -Off-Automatic switch for control of contactor, overcurrent protection devices for each individual lighting circuit, enclosures, conduits, fittings , cables and connectors. Assure all control equipment included in the power service is capable of operating within the provided enclosure(s) over appropriate temperature and humidity conditions. Assure that power service equipment that includes daytime li ghting controls shall operate continuously with the enclosure placed in a location fully exposed to sunlight and daytime temperature of 100°F ambient. Construct the lighting electrical system to provide selective coordination of overcurrent devices per NEC 240.12(1). Overload indications per NEC 240.12(2) are allowed but not required as part of a standard ODOT lighting control system. Provide to the Engineer: A. individual catalog sheets and device time -current curves and/or tables and B. combined graphic al overlays that document acceptable installed overcurrent device coordination. Provide this documentation for all installed overcurrent devices, including the service disconnect fuses, the lighting control center branch circuit breakers, and tower circuit breakers/ pole fuses (if present). Tabular data, if used, shall include the following time points as a minimum: 0.01, 0.02, 0.05, 0.1, 0.2, 0.5,1, 10, 100, and 300 seconds and additional points as needed to clearly show the overcurrent device operating ch aracteristics. Include minimum melt time and maximum clearing time for fuses; include minimum and maximum clearing time for circuit breakers. Provide documentation of the utility -installed transformer ANSI fuse link type (e.g., K or T) and fuse rating (if available). Provide documentation of the utility -installed power service size (in kVA). 625.16 569 Provide to the Engineer a compiled list or catalog sheets showing the Short - Circuit Current Rating (SCCR) of all fuses and fuse holders, circuit breakers, switches and contactors, pursuant of the requirements in NEC Article 110.10 If the power service has multiple enclosures, mark each enclosure in white letters engraved on a black plastic placard with the function of the equipment contained therein such as “SERVICE DISC ONNECT”, “LIGHTING CONTACTOR”, “LIGHTING PANEL”, or other appropriate designation. Apply a durable, weatherproof adhesive arc and shock hazard warning label to the outside of each electrical enclosure that contains applicable voltage and/or arc hazard leve ls. When an apparatus enclosure contains circuits above the 600 volt class, mark the enclosure in white letters on a red plastic placard with the warning “DANGER - HIGH VOLTAGE” on each enclosure door. Install each photoelectric cell facing North unless the Engineer directs that a specific cell face otherwise to reduce interference from surround lighting. Bond all metallic portions of the supporting structure, equipment housings and conduits properly and to an adequate earth ground. Install a wood or plasti c wire moldings from grade to 3 feet (1 meter) above grade over any grounding cables installed on a wood pole. Coordinate and cooperate with the power company in the making of the connections to establish electrical service. Charges made by the power compa ny for establishing of the account, extension of company facilities, connection of customer equipment to the power company facilities and energy will be borne by the maintaining agency. Install a padlock per 631.06 on all external actuators. Coordinate wi th power company on installation of a second padlock conforming to their specifications. Install a dual padlock bar.
625.16 Grounding. Connect each light pole or light tower to a local earth
ground. Connect each power service to a local earth ground. Provi de continuity of grounding by bonding the metallic portions of fixtures, apparatus enclosures, supports, conduits, raceways, junction boxes and pull boxes together and connecting to earth ground. At a light pole or a light tower, install a bonding cable be tween the grounding bushing on each metal conduit and the ground lug or bolt in the pole base. At a junction box or a pull box, install a grounding bushing on each metallic conduit not bonded to the box through the conduit connector, and install a bonding cable between the grounding bushings on the conduits and the ground lug or bolt in the box. For a light pole, light tower, power service or other such item mounted independently, install one or more grounding electrodes. For a luminaire, light pole, light tower, switch enclosure, or other such item mounted in or on major highway structures (i.e. bridges), connect the item to the structure grounding system. 625.17 570 For a lighting contactor, lighting circuit panel or other such item mounted in a building (i.e. motori sts services building, weigh station scale house, etc.), connect the item to the grounding system provided for the building. For each bridge, wall, or other structure having electrical elements contained therein or attached thereto, furnish all materials n ecessary including grounding electrodes and install a complete structure grounding system to bond all exposed metallic portions of the structure (i.e. beams, railings, etc.) electrically together and connect those items to good earth ground. In the case wh ere structures are separate but adjacent, connect the multiple structures together to avoid any difference in earth potential between the structures. Make the permanent connection between the each ground rod and the grounding conductor by exothermic weldin g. If the earth resistance measurement exceeds 10 ohms for a ground for a traffic signal controller or a light tower or 25 ohms for any other ground, install a second ground rod at least 10 feet (3 meters) from the first and temporarily connect the second rod to the first. If the earth resistance still exceeds the above specified values, permanently connect the first two rods using the same type of cable used for the grounding conductor and continue to add rods one at a time as directed by the Engineer. Whe re rock does not permit the driving of ground rods, develop an earth connection by constructing a grid from the partially driven rods supplemented by buried bare cable as directed by the Engineer.
625.17 Wiring and Cabling. Furnish and install electrical wires and cables of
the types and sizes required with no in -line splices between terminations at devices unless specifically called for by the plan or directed by the Engineer. Install wire mesh cable grips on vertical runs of wire or cable in poles and at tach said grips to the “J” hook at the tops of the poles in such a manner as to prevent the weight of the vertical run from abrading the wire insulation or cable jacket where the wire or cable passes into or from the pole. Identify all wires and cables, ex cept bare ground bonding cables, as to circuit and function with tags or bands in the base of each light pole or light tower, each junction box or pull box, each apparatus cabinet, and other similar locations. Pay out each wire, cable and duct cable by “un winding” it from the shipping reel, spool or coils and not allow the wire cable or duct -cable to “spiral” from off the side of the spool reel or coil. In addition when wire cable or duct cable is being placed in trench, move the reel spool or coil along the side of the trench to allow the wire or cable to pay out into the trench as directly as practical. Seal the ends of each run of duct cable in the same manner as conduit as each run is installed. Do not install duct cable when the temperature of the du ct-cable cannot be kept above 32 °F (0 °C) except with the permission of the Engineer. If the end of a wire or cable or duct must stand exposed to the elements or construction activities, protect said exposed end by enclosing it in a plastic bag or wrappin g it with tape until the termination or connection can be made. 625.18 571 625.18 Connections. Make each wire and cable connection above grade (i.e. bases of light poles or light towers, junction boxes on structure or in concrete barrier medians, etc.) with an approv ed cable connector kit. Use quick disconnect type kits in the base of each light pole with a fused type in each line or phase conductor. Plug unused line side wire opening in each connector kit installed in the base of the light pole at the outer end of a circuit. Make each cable connection below grade (i.e. pull boxes, junction boxes in retaining walls, etc.) with a cable splicing kit. Protect partially assembled connections from damage and the elements.
625.19 Testing of Installations. Furnish equipmen t and personnel to perform
each test as an incidental to the construction of the lighting installation. The Engineer shall witness each test and judge the results.
625.20 Plastic Caution Tape. Install tape approximately 6 to 10 inches (150 to
250 mm) below the final finished grade. Place with the printed side up and parallel 625.21 573 with the finished surface. Insure that the tape is not pulled, distorted or otherwise misplaced in completing the trench b ackfill.
625.21 Removal of Lighting Equipment.
625.22 Method of Measurement. Bracket arms will be included with the light
pole, light tower or combination support on which they are mounted for payment. However, when a bracket arm is to be mounted onto an existing support or a support 625.22 574 provided by another aspect of the project, it may be a separate item for the purpose of payment in which case payment will be made for each bracket arm. Transformer bases will be included with the light pole, light tower or combination support o n which they are mounted for payment. However, when a transformer base is to be fitted to an existing light pole, it may be a separate item for the purpose of payment in which case payment will be made for each transformer base. Light pole anchor bolts wil l be furnished with the light pole and the setting of the anchor bolts included with the foundation. However, in the case of a light pole mounted onto structures such as bridges and retaining walls where the bolts normally furnished with the light pole are not of the proper length and shape and/or the setting of the bolts must be done when the structure is constructed rather than being at the time of construction of the light pole foundation, the bolts shall be a separate item for payment in which case paym ent will be for each bolt with the count being the number of bolt ends projecting for the anchoring of the light pole. Separate payment shall also be made when the bolts are being set in a normal light pole or light tower foundation but the light pole or l ight tower is not being furnished by the Contractor or by others to the Contractor. Foundations for light poles or light towers include excavation, dewatering, sleeving, casing, reinforcing steel, raceways, concrete, backfilling, and when required the 8 fo ot or 10 foot foundation section of concrete barrier, and the disposal of surplus excavation. For light poles or light towers mounted on median barrier or retaining walls, the junction box at the point where the stub conduit to the light pole or tower join s the main lighting circuit raceway and the stub conduit from the junction box to the light pole or light tower are also included. Anchor bolts, conduit ells and surface restoration not included elsewhere are also included with the foundation. Junction box es include the drain. Pull boxes include the aggregate for base. Power service includes the control equipment, the support and foundations on which the equipment is mounted, the pull boxes with underdrain for gathering the lighting circuits into the contro l equipment at the power service location, ground rods and incidentals required for a completed power service. Also included are any poles, conduits, wire and cable to be provided by the owner to receive the incoming power from the power company. Structure grounding system includes any ground rods or ground grids required as part of the system. Ground grids include any ground rods required as part of the grid and includes the associated grounding conductor and connections from the resultant grid to the first point (or points) of connection. Ground grids that result from the addition of ground rods as a result of earth ground resistance measurements will be the sum of each ground rod installed such sum will also include all connecting cable and trenching. A ground rod includes the associated grounding conductor and connections from the rod to the first point of connection. 625.22 575 Trench will be measured to the center of a light pole foundation, the center of a light tower foundation, the center of a pull box, the ce nter of the pole of an embedded pole mounted power service, the center of the foundation for a power service with a foundation, or the wall of the building when the power service for the lighting in, on or within the building with no allowance for elevatio n change. The payment for trench includes all excavation, granular and other backfill material, compaction, disposal of surplus materials and restoration to match surrounding surface including any seeding, sodding or other plantings which were disturbed an d the replacement of any minor items such as guardrail or fence panels, and return to former position and mounting of items such as trash containers, planter boxes or parking meters and small signs which were temporarily moved to facilitate the trenching. The payment for trench in paved areas includes the aforementioned and in addition sawing and removal of pavement, along with the repaving over the trench. Trench in paved areas shall be separated for payment into Type A for pavements or sidewalks less than 6 inches (150 mm) thick and Type B for pavements 6 inches (150 mm) or greater. Conduit will be measured to the center of a light pole foundation, the center of a light tower foundation, the center of a pull box, the center of the pole of an embedded pole mounted power service, the center of the foundation for a power service with a foundation, or the wall of the building when the power service for the lighting in, on or within the building with no allowance for elevation change. The payment for conduit inc ludes couplings (plain, expansion, and alignment), bends, hubs, bushings, condulets and other such appurtenances but not junction boxes and pull boxes. Conduit to be encased in concrete or installed by jacking or boring will be paid separately from conduit to be traditionally installed. Concrete and other materials for encasement or the jacking or boring are included with such conduit where specified. Distribution cable will be measured to the center of foundation, pull box, junction box or power service, plus an allowance of 5 feet (1.5 meters) at each pull box and terminating points for slack and connections end except for a power service where the allowance will be 10 feet (3 meters) to allow for slack and connections with the sum multiplied by the numbe r of conductors required. Pole and bracket cable will be measured as the light pole support height plus the designated arm length with the sum multiplied by the number of conductors required. For twin arm poles the sum shall be increased by the length of t he second arm plus the length of the first arm. Duct cable will be measured to the center of foundation, pull box, junction box or power service, plus an allowance of 5 feet (1.5 meters) on each end except for a power service where the allowance will be 10 feet (3 meters) to allow for slack and connections with no multiplier for the number of conductors. Duct -cable includes the cable(s) and being a factory assembly is differentiated by the number and size of the conductors in each assembly. Plastic caution tape will be measured to the center of a light pole foundation, the center of a light tower foundation, the center of a pull box, the center of the pole of an embedded pole mounted power service, the center of the foundation for a power service with a foun dation, or the wall of the building when the power service for the lighting in, on or within the building with no allowance for elevation change. 625.23 576 625.23 Basis of Payment. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 625 Each Luminaire, (Functional Type), (Housing Size if Conventional), (Light Distribution), (Lamp Wattage), (Light Source), (Voltage) 625 Each Glare Shield 625 Each Light Pole, (Pole Style),(Design Number) 625 Each Light Tower,(Design Number) 625 Each Light Pole Anchor Bolts 625 Each Light Pole Foundation 625 Each Light Tower Foundation 625 Each Junction Box, (Length × Height × Depth) 625 Each Pull Box, (Material Type), (Length × Height × Depth) 625 Foot (Meter) Condui t, (Material Type), (Nominal Diameter) 625 Foot (Meter) Trench 625 Foot (Meter) Trench in Paved Area,(Type) 625 Foot (Meter) Conduit Jacked or Drilled,(Material Type), (Nominal Diameter) 625 Each Power Service 625 Each Ground Rod 625 Each Ground Grid 625 Each Structure Grounding System 625 Foot (Meter) Pole and Bracket Cable, (Size of Conductors in AWG), (Voltage Rating) 625 Foot (Meter) Distribution Cable, (Size of Conductors in AWG), (Voltage Rating) 625 Foot (Meter) Duct Cable, (Duct Diame ter) with (Number of Conductors), (Size of Conductors in AWG), (Voltage Rating) Conductors 625 Each Connection 625 Each Service to Underpass Lighting 625 Each Portable Winch Drive Power Unit 625 Each Luminaire Removed 625 Each Luminaire Suppor t Removed 625 Each Luminaire Support Foundation Removed 625 Each Pull Box Removed 625 Each Disconnect Circuit 625 Each Power Service Removed 625 Foot (Meter) Plastic Caution Tape