ITEM 624 MOBILIZATION
624.01 Description. This work consists of the preparatory work and operations including, but
not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for the establishment of all field offices, buildings, and ot her facilities necessary for work on the project; for all other work and operations that must be performed or costs incurred before beginning the Work on the other contract items; and for demobilization. If Mobilization is not included as a pay item in the Contract, the Department will not pay for this work separately but will consider it incidental to the other Contract Items.
624.02 Limitation. The Department will limit the sum of the partial payments specified in
624.04 A and 624.04.B to 5% of the original contract amount. The Department will pay the balance of
the lump sum amount bid, as specified in 624.04.C. If the lump sum amount bid for Mobilization exceeds 5% of the original contract amount , the Department will pay the excess upon completion of the project.
624.03 Method of Measurement. The Department will measure Mobilization as a unit,
acceptably performed.
624.04 Basis of Payment. The Department will make partial payments according to 109.09 and
as modified by the following schedule:
Mobilization in other states