623.01 Description. This work consists of furnishing the accurate horizontal and vertical
locations for the construction of the Work shown in the contract documents. Acceptable methods include, placing, and maintaining construction layout stakes, real time layout utilizing survey equipment (GPS, Total Station, Level) and automated machine control and guidance. This work also includes verification, placement, protection, and any necessary restoration of project control monuments, monument assemblies, reference monuments, rig ht-of-way monuments, property line/boundary monuments and other survey monuments. Use Geodetic and/or Primary Project Control monuments as the basis for all construction layout staking and verification, placement, protection, and restoration of survey monuments. Ensure that all work encompassing the verification, placement, protection, and restoration of survey monuments is performed under the supervision of a Registered Surveyor and certify that the accuracy of all measurements meets Ohio Administrative Code Section 4733-37 and the ODOT Survey and Mapping Specifications. Ensure all construction layout is performed under the supervision of either a Registered Surveyor or a Registered Engineer.
623.02 Materials. Furnish materials conforming to:
Concrete, Class QC Misc or QC 1 ........ 499 Cast frames and covers ............. 711.12, 711.13, or 711.14 Concrete sand (fine aggregate) .... 703.02.A Stainless steel bolts .......................... 730.10 Steel rods .......................................... 709.01 Pipe .................... 706.07, 706.09, or 707.45
623.03 Definitions
623.04 Survey Monument Verification. Verify the position of survey monuments shown in the
Contract Documents including the project control and those shown in the right-of-way plans and locate any additional survey monuments if discovered within the right -of-way in the project work area . Generate a report detailing the surveyed location of all monuments. Use standard acceptable surveying measurement techniques suitable to meet the requirements of Ohio Administrative Code Section 4733- 37, “Standards for Boundary Surveys”. Survey monument verification is required on all projects where survey monuments are specified in the Contract Documents including pavement resurfacing, reconstruction and repair projects where monument assemblies will be adjusted or reconstructed to grade. Use the Department’s standardized verification report template. The “ Survey Monument Verification Report” template can be downloaded from the following website: www.dot.state.oh.us/divisions/constructionmgt/admin/pages/default.aspx.
623.05 Placement, Protection and Restoration of Survey Monuments . Construct or replace
all required survey monuments specified in the Contract Documents. Do not disturb survey monuments, cornerstones, or boundary monuments during construction unless specified in the Contract Documents. Restore survey monuments damaged or destroyed by construction activities, unless directed otherwise by the Engineer. Restore damaged survey monuments at locations specified in the Contract Documents or in their original location if the monument was not included in the Contract Documents. For a survey monument that cannot be installed in the location shown on the plans, notify the Engineer who will contact the District Survey Operations Manager to provide direction. Report monuments placed in locations other than in the specified locations in the Post Construction Survey Monument Verification Report . Do not place a monument in an alternate location without the prior approval of the District Survey Operations Manager . Refer to the Department’s Real Estate Manual, Appendix K, for guidance on how to proceed with setting monuments in alternate locations.
623.06 Geodetic/Primary Project Control . Geodetic/Primary Project Control governs all
positioning for Department projects. Use project control information provided on the plans for all project related survey operations.
623.07 Right-of-Way Staking. Stake Right-of-Way lines where work will be performed before
beginning the work. Stake Right -of-Way lines by placing tall stakes, properly identified and readily discernible, at points of change in width or direction of the Right -of-Way line and at points along the line so that at least two stakes can be seen distinctly from any point on the line. The Engineer will not require the Contractor to set additional stakes to locate a utility line that is not included as a pay item in the contract, or to determine the property line between properties.
623.08 Construction Layout. Construction Layout will be performed in a manner to allow the
contractor to properly construct the improvements on, below and above the ground at locations as defined by the contract documents and to allow for proper verification of said locations by th e Department. All layout work will be relative to the Geodetic/Primary Project Control monuments. Applicable methods include, but are not limited to the following:
623.09 Providing Electronic Instrumentation. If specified as a pay item, provide the Engineer
with electronic instrumentation so that the Department can verify the construction layout, perform check sections, and document pay items. Provide a survey -grade, global navigation satellite system (GNSS) receiver and data collector. Provide equipment tha t meets the requirements of the Department’s Survey and Mapping Specifications. Provide equipment, software, and all three -dimensional models needed to verify layout, perform check sections, and document pay items. Train the Engineer on how to use the provided equipment and software and provide technical assistance during the duration of the Work. Upon completion of the Work, the electronic equipment, computer and software will remain the property of the Contractor. If using GNSS methods to construct the project and a pay item for providing electronic instrumentation is not specified, provide the Engineer with the three-dimensional models in electronic format when requested. Provide the models at no additional expense to the Department.
623.10 Method of Measurement . Estimated unit quantities for constructing new monuments,
adjusting or reconstructing monuments to grade, and replacement of Survey Monuments expected to be destroyed are included in the Contract Documents. The Contractor will be compensated on a unit basis for additional survey monuments found, located, and reconstructed or replaced within the right - of-way in the project work area but not shown on the plans. Survey Monuments on or outside of the Construction Limits are the Contractor ’s responsibility to protect and restore as required. The Department will not pay for restoration of these items.
623.11 Basis of Payment . Payment for lump sum Construction Layout Stakes and Surveying
includes payment for Construction Layout, Right of Way staking, and Placement, Protection and Restoration of Survey Monuments . Payment for lump sum items Pre/Post Construction Survey Monument Verification and Report includes payment for all surveying necessary to locate, verify and report survey monuments in Survey Monument Verification. The Department will consider the cost of locating new survey monuments to be included in the unit price bid for the survey monument. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 623 Lump Sum Construction Layout Stakes and Surveying 623 Lump Sum Providing Electronic Instrumentation 623 Each Primary Project Control Monument, Type A 623 Each Primary Project Control Monument, Type B 623 Each Monument Assembly, Type C 623 Each Monument Assembly, Type D 623 Each Monument Assembly, Adjusted to Grade 623 Each Monument Assembly, Reconstructed to Grade 623 Each Monument Assembly Removed and Reset 623 Each Reference Monument, Type A 623 Each Right of Way Monument, Type B 623 Lump Sum Preconstruction Survey Monument Verification and Report 623 Lump Sum Post Construction Survey Monument Verification and Report
Get an email when 623 changes
Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.