101-1 Description.
Perform preparatory work and operations in mobilizing for beginning work on the project, including, but not limited to, those operations necessary for the movement of personnel, equipment, supplies, and incidentals to the project site and for the establishment of temporary offices, buildings, safety equipment and first aid supplies, and sanitary and other facilities. Include the costs of bonds and any required insurance and any other preconstruction expense necessary for the start of the work, excluding the cost of construction materials.
101-2 Basis of Payment.
101-2.1 When a Separate Item is Included in the Proposal: When the proposal
includes a separate item of payment for this work, the work and incidental costs specified as being covered under this Section will be paid for at the Contract lump sum price for the item of Mobilization. Payment will be made under: Item No. 101 - 1- Mobilization -lump sum.
101-2.2 Partial Payments: When the proposal includes a separate pay item for
Mobilization and the Notice to Proceed has been issued, partial payments will be made in accordance with the following: For contracts of 120 contract days duration or less, partial payment will be made at 50% of the bid price per month for the first two months. For contracts in excess of 120 contract days duration, partial payment will be made at 25% of the bid price per month for the first four months. In no event shall more than 50% of the bid price be paid prior to commencing construction on the project site. Total partial payments for Mobilization will be limited to 10% of the original Contract amount. Any remaining amount will be pai d at Final Acceptance . Retainage, as specified in 9 -5, will be applied to all partial payments. Partial payments made on this item will in no way act to preclude or limit any of the provisions for partial payments otherwise provided for by the Contract .
101-2.3 When No Separate Item is Included in the Proposal: When the proposal does
not include a separate item for Mobilization, all work and incidental costs specified as being covered under this Section will be included for payment under the several sc heduled items of the overall Contract, and no separate payment will be made therefore. FY 2023-24 Return to Table of Contents SECTION 102 MAINTENANCE OF TRAFFIC
102-1 Description.
Maintain traffic within the limits of the project for the duration of the construction period, including any temporary suspensions of the work. Construct and maintain detours. Provide facilities for access to residences, businesses, etc., along the project . Furnish, install and maintain traffic control and safety devices during construction. Furnish and install work zone pavement markings for maintenance of traffic (MOT) in construction areas. Provide any other special requirements for safe and expeditious movement of traffic specified in the Temporary Traffic Control Plans. MOT includes all facilities, devices and operations as required for safety and convenience of the public within the work zone. Do not maintain traffic over those portions of the project where no work is to be accomplished or where construction operations will not affect existing roads. Do not obstruct or create a hazard to any traffic during the performance of the work, and repair any damage to existing pavement open to traffic.
102-2 Materials.
Meet the following requirements: Raised Pavement Marker Adhesive * ...................... Section 706 Paint* ................................ ................................ .. …Section 710 Pavement Marking Materials* ............................ …Section 971 Temporary Raised Pavement Markers * .................. Section 990 Temporary Traffic Control Device Materials * ....... Section 990 Retroreflective and Nonreflective Sheeting for Temporary Traffic Control Devices * ................ Section 994 *Use products listed on the Department’s APL.
102-2.1 Temporary Traffic Control Devices: Use only the materials meeting the
requirements of Section 990, Secti on 994, Standard Plans and the Manual on Uniform Traffic Control Devices (MUTCD).
102-2.2 Detour: Provide all materials for the construction and maintenance of all
detours.
102-2.3 Commercial Materials for Driveway Maintenance: Provide materials of the
type typically used for base, including rec laimed asphalt pavement (RAP) material, and having stability and draina ge properties that will provide a firm surface under wet conditions.
102-3 Specific Requirements.
102-3.1 Beginning Date of Contractor’s Respo nsibility: Maintain traffic starting the
day work begins on the project or on the first day Contract Time is charged, whichever is earlier.
102-3.2 Worksite Traffic Supervisor: Provide a Worksite Traffic Supervisor who is
responsible for initiating, installing, and maintaining all temporary traffic control devices as described in this Section and the Contract Documents. Provide all equipment and materials needed to set up, take d own, and maintain temporary traffic control, and handle traffic -related situations. Provide the Worksite Traffic Supervisor or designee with a tablet or smartphone with FY 2023-24 Return to Table of Contents