B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Incidental Construction (600-699)

601MOBILIZATION

AR · Standard Specifications✓ Full text on BuildSpec Save this section

Ask about Section 601

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

601.01 Description. This item shall consist of preparatory work

and operations, including, but not limited to, thos e necessary for the movement of personnel, equipment, supplies, and inc identals to the project site; for the establishment of the Contract or's offices, buildings, and other facilities necessary to undert ake the work on the project. This item shall also include other work and operati ons that must be performed, or for expenses incurred, before begi nning work on the various Contract items on the project site. It shall also include pre-construction costs which are necessary direct c osts to the project and are of a general nature rather than directly at tributable to other pay items under the Contract.

601.02 Measurement and Payment. Mobilization will be

measured as a complete unit and will be paid for at the contract lump sum price bid. In computing the allowable partial payments from the schedule below, the percentage of the original Contract earned will be based on all items exclusive of the item Mo bilization and any materials estimates paid. Payment for Mobilization at any of the listed stages of completion will be made on the bas is of the percentage of the item allowed less all payments ma de. PARTIAL PAYMENT SCHEDULE Percentage of Original Percentage of Bid Price Contract Amount Earned for Mobilization Allowed First Progress Estimate 25 10 50 25 100 This item will be paid for on regular estimates. P ayments on percentages of the original Contract amount other t han those set out above will not be considered. No adjustment in the amount bid for this item will be made for additional quantities or items of work required to satisfactorily complete the Contract. 388 DIVISION 600 INCIDENTAL CONSTRUCTION

Get an email when 601 changes

Arkansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: , Edition. View official source ↗

Ask about this section

Scoped to Arkansas 2014 Standard Specifications for Highway Construction, Section 601 — MOBILIZATION. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.