General Provisions (00100-00999)

600MOBILIZATION

AL · 2022 Standard SpecificationsBook pages 469469View official source ↗

600.01 Description.

Division 600

INCIDENTALS

600.01 Description.

This Section shall cover the preparatory work and operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the pro ject site; for the establishment of all offices, buildings, and other facilities necessary for work on the project; and for all other work and operations which must be performed or costs incurred prior to beginning work on the various items on the project site. The lump sum bid for mobilization shall be so distributed among the various pay items of the contract that an overrun of a particular pay item will not adversely affect the unit price of that item.

600.02 Materials.

Not applicable.

600.03 Construction Details.

Not applicable.

600.04 Method of Measurement.

a.Partial Payment . Measurement of the item of Mobilization will be on a unit basis for each project or combination of projects included in a single contract. When more than one project is included in one contract, the amount of payment to be made will be based on the percent complete and amount of the entire contract, not the percent complete and amount of each individual project. Once the amount of payment is determined, based on the entir e contract, this amount will then be prepared for payment on each individual project based on the percentage of the total contract of which the project is a part. Partial Payments for mobilization are based on the amount bid for mobilization and the total original contract amount for all items of work. Payments will be made at the time, and in the amounts shown in the following schedules. SCHEDULE OF PARTIAL PAYMENTS FOR MOBILIZATION WHEN THE CONTRACT BID PRICE FOR MOBILIZATION IS LESS THAN, OR EQUAL TO 12 % OF THE ORIGINAL CONTRACT AMOUNT (Partial Payments are a % of the Contract Amount for Mobilization) TIME OF PAYMENT AMOUNT OF PAYMENT ACCUMULATED PAYMENT First Estimate 20 % of the Bid Price for Mobilization 20 % of the Bid Price for Mobilization After the First Estimate and Upon Completion of 5 % of the Original Contract Amount Excluding Prior Payment for Mobilization 50 % of the Bid Price for Mobilization 70 % of the Bid Price for Mobilization After the First Estimate and Upon Co mpletion of 50 % of the Original Contract Amount Including Prior Payment for Mobilization 30 % of the Bid Price for Mobilization 100 % of the Bid Price for Mobilization

601.03 Equ ipment.

SCHEDULE OF PARTIAL PAYMENTS FOR MOBILIZATION WHEN THE CONTRACT BID PRICE FOR MOBILIZ ATION IS GREATER THAN 12 % OF THE ORIGINAL CONTRACT AMOUNT (Partial Payments are a % of the Original Contract Amount, Except the Final Payment) TIME OF PAYMENT AMOUNT OF PAYMENT ACCUMULATED PAYMENT First Estimate 2 % of the Original Contract Amount 2 % of Total Contract Amount After the First Estimate and Upon Completion of 5 % of the Original Contract Amount Excluding Prior Payment for Mobilization 6 % of the Original Contract Amount 8 % of Total Contract Amount After the First Estimate and Upon Completion of 50 % of the Original Contract Amount Including Prior Payment for Mobilization 4 % of the Original Contract Amount 12 % of Total Contract Amount At Acceptance for Maintenance per Item 105.15(c)3. Remainder of Contract Amount for Mobilization 100 % of Contract Amount for The total sum of all payments shall not exceed the original contract amount bid for the item of Mobilization, regardless of the fact that the Contractor may have, for any reason, shut down his work on the project or moved equipment away from the project and then back again.

b.When No Separate Payment is shown in the Proposal . When the proposal does not include a separate item for Mobilization, all work and incidental costs specified as being cov ered under this Section shall be included for payment under the several scheduled items of the overall contract, and no separate payment will be made therefor.

600.05 Basis of Payment.

a.Unit Price Coverage . The item of Mobilization, measured as noted above, will be paid for at the contract lump sum price bid. Said lump sum price bid shall be full compensation for organizing and moving all labor, tools, equipment, supplies, and incidentals to the project site and for disbanding, disorganizing, and removing all labor, tools, equipment, supplies, and incidentals from the project site, regardless of number of times such moves are made, including all preconstruction costs exclusive of bidding costs.
b.Partial Payment . Partial payments may be made in accordance with sc hedule noted in Article 600.04.
c.Payment will be made under Item No.: 600-A Mobilization - per lump sum SECTION 601 FIELD LABORATORIES

601.01 Description.

This Section shall cover furnishing for the dura tion of the contract, base, soil, and structure laboratories, and asphalt and concrete plant laboratories as specified on the plans and in these Specifications.

601.02 Materials.

Laboratories and equipment furnished shall be in satisfactory usable conditio n, and shall be maintained in that condition throughout the contract.

601.03 Equipment.

a.Base, Soil, and Structure Laboratories . Laboratories for testing soil type bases, soils, structures, and similar work shall comply in all details with the requirements of Article 106.03.
Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 469469 of 934.