B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Incidental Construction (600-699)

626Mobilization

CO · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 775–776 Save this section

Ask about Section 626

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

Mobilization

Description

626.01This work consists of the mobilization of personnel, equipment and supplies at the

project site in preparation for work on the project. This item shall also include the establishment of the Contractor's offices, buildings and other necessary facilities, and all other costs incurred or labor and operations that must be performed before beginning the other items under the Contract.

Basis of Payment

626.02Partial payments for mobilization will be made once each month as the work

progresses. These partial payments will be made as follows:

(1)When 5 percent of the original contract amount is earned, 25 percent of the amount bid for

mobilization, or 2 1/2 percent of the original contract amount, whichever is less, will be paid.

(2)When 10 percent of the original contract amount is earned, 50 percent of the amount bid for

mobilization, or 5 percent of the original contract amount, whichever is less, will be paid.

(3)When 25 percent of the original contract amount is earned, 60 percent of the amount bid for

mobilization, or 6 percent of the original contract amount, whichever is less, will be paid.

(4)When 50 percent of the original contract amount is earned, 100 percent of the amount bid

for mobilization, or 10 percent of the original contract amount, whichever is less, will be paid.

(5)Upon completion of all work on the project, payment on any amount bid for mobilization in

excess of 10 percent of the original contract amount will be paid.

(6)The total sum of all payments shall not exceed the original contract amount bid for the

item, regardless of the fact that the Contractor may have, for any reason, shut down the work on the project or moved equipment away from the project and then back again. For the purpose of this Section the term “original contract amount” as used above shall mean the amount bid for the construction items in the Contract not including the amount bid for mobilization. Payments for materials on hand, as described in subsection 109.07, will not be included as a percent of original contract amount earned until said materials on hand have been incorporated into the work and accepted and paid for as contract items.

These payments shall be independent of partial payments as defined in subsection 109.06. Payment will be full compensation for all work necessary to complete the item.

Payment will be made under:

Pay Item Pay Unit Mobilization Lump Sum

Nothing shall be construed to limit or preclude partial payments for other items as provided for by the Contract.

626.02

This Page Intentionally Left Blank

627.01

Get an email when 626 changes

Colorado revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Colorado Standard Specifications for Road and Bridge Construction, 2023 Edition. Pages 775–776 of 943. View official source ↗

Ask about this section

Scoped to Colorado 2025 Standard Specifications for Road & Bridge Construction, Section 626 — Mobilization. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.