110-1Description
Clear and grub within the areas shown in the Plans. Remove and dispose of all trees, stumps, roots and other such protruding objects, buildings, structures, appurtenances, existing flexible asphalt pavement, and other facilities necessary to prepare the area for the proposed construction. Remove and dispose of all product and debris not required to be salvaged or not required to complete the constr uction. Perform miscellaneous work necessary for the complete preparation of the overall project site as specified in 110-10.
110-2Standard Clearing and Grubbing
110-2.1Work Included: Completely remove and dispose of all buildings, timber, brush,
trees, stumps, roots, rubbish, debris, existing flexible pavement and base, drainage structures, culverts, and pipes. Remove all other obstructions resting on or protruding through the surface of the existing ground and the surface of excavated areas. Perform standard clearing and g rubbing within the following areas:
ditches, right -of-way ditches, etc.
If shown in the Contract Documents, remove existing pavement base.
and other pipe lines.
110-2.2Depths of Removal of Roots, Stumps, and Other Debris: In all areas where
excavation is to be performed, or roadway embankments are to be constructed, remove roots and other debris to a depth of 12 inches below the ground surface. Remove roots and other debris from all exca vated material to be used in the construction of roadway embankment or roadway base. Plow the surface to a depth of at least 6 inches, and remove all roots thereby exposed to a depth of at least 12 inches. Completely remove and dispose of all stumps within the roadway right-of-way. Remove all roots, etc., protruding through or appearing on the surface of the completed excavation within the roadway area and for structures, to a depth of at least 12 inches below the finished excavation surface. Remove or cut off all stumps, roots, etc., below the surface of the completed excavation in borrow pits, material pits, and lateral ditches. In borrow and material pits, do not perform any clearing or grubbing within 3 feet inside the right -of-way line. Within all other areas where standard clearing and g rubbing is to be performed, remove roots and other debris projecting through or appearing on the surface of the original ground to a depth of 12 inches below the surface, but do not plow or harrow these areas.
110-2.3Boulders: Remove any boulders encountered in the roadway excavation (other
than as permitted under the provisions of 120 -7.2) or found on the surface of the ground. When approved by the Engineer place boulders in neat piles inside the righ t of way. The Contractor 169 FY 2023-24 Return to Table of Contents may stockpile boulders encountered in Department -furnished borrow areas, which are not suitable for use in the embankment construction, within the borrow area.
110-2.4Asbestos Containing Materials (ACM) Not Identified Prior to the Work:
When encountering or exposing any condition indicating the presence of asbestos, cease operations immediately in the vicinity and notify the Engineer, in accordance with 110 -6.5.
110-3Selective Clearing and Grubbing
110-3.1General: Remove and dispose of vegetation, obstructions, etc., as shown in the
Plans. Provide acceptable fill material, and grade and compact holes or voids created by the removal of the stumps. Perform all selectiv e clearing and grubbing in accordance with ANSI A300. No staging, storing, stockpiling, parking or dumping will be allowed in selective clearing and grubbing areas. Only mechanical equipment related to selective clearing and grubbing activities will be a llowed in selective clearing and grubbing areas. Protect trees to remain from trunk, branch and root damage.
110-3.2Protection of Plant Preservation Areas: Areas to remain natural may be
designated in the Plans. No clearing and grubbing, staging, storage , stockpiling, parking or dumping is allowed in these areas. Do not bring equipment into these areas.
110-3.3Tree Protection Barrier : Construct a tree protection barrier in accordance with
Standard Plans Index 110 -100 and the Plans. Maintain barrier for duration of the Contract.
110-3.4Tree Root and Branch Pruning : When pruning cuts or root pruning to existing
trees are shown in the Plans, work is to be supervised on site by an International Society of Arboriculture (ISA) Certified Arborist and performe d in accordance with ANSI A300.
110-3.5Tree Removal : Remove trees as shown in the Plans
110-4Protection of Property Remaining in Place
Protect property to remain in place in accordance with 7 -11.
110-5Removal of Buildings
110-5.1Parts to be Removed: Completely remove all parts of the buildings, including
utilities, plumbing, foundations, floors, basements, steps, connecting concrete sidewalks or other pavement, septic tanks, and any other appurtenances, by any practical manner which is not detrimental to other property and improvements. Remove utilities to the point of connection to the utility authority’s cut -in. After removing the sewer connections to the point of cut -in, construct a concrete plug at the cut -in point, as directed by the Enginee r, except where the utility owners may elect to perform their own plugging. Contact the appropriate utility companies prior to removal of any part of the building to ensure disconnection of services. Submit demolition schedule 15 working days before beginning any demolition or renovation of a building.
110-5.2Removal by Others: Where buildings within the area to be cleared and grubbed
are so specified to be removed by others, remove and dispose of any foundations, curtain walls, concrete floors, basemen ts or other foundation parts which might be left in place after such removal of buildings by others.
110-6Removal of Existing Bridges
110-6.1General: The work under this Article includes bridges, as defined in 1 -3
Remove and dispose of the materials from existing bridges. Remove 170 FY 2023-24 Return to Table of Contents
Plans to be removed,
the limits of the area to be cleared and grubbed, and directed by the Engineer to be removed,
necessary to be removed in order to complete the work, and
Contract Documents to be included as an item of payment for the work under this Article. Submit schedule information and demolition plan for approval 15 working days before beginning any demolition or renovation of any structures.
110-6.2Method of Removal:
110-6.2.1 General: Remove the structures in such a way so as to leave no obstructions to any proposed new bridge or to any waterways. Pull, cut off, or break off pilings to the requirements of the permit or other Contract Documents, or if not specified, not less than 2 feet below the finished graded surface . In the event that the Plans indicate channel excavation to be done by others, consider the finished graded surface as the limits of such excavation. For materials which are to remain the property of the Department or are to be salvaged for use in temporary bridges, avoid damage to such materials, and entirely remove all bolts, nails, etc. from timbers to be so salvaged. Mark structural steel members for ident ification as directed. 110-6.2.2 Removal of Steel Members with Hazardous Coatings: Submit to the Engineer for approval the “Contractor’s Lead in Construction Compliance Program”, QP2 certification from the Society for Protective Coatings (SSPC) from the firm actually removing and disposing of these steel members before any members are disturbed. Vacuum power tool clean any coated steel member to bare metal as defined by SSPC -SP11 a minimum of 4 inches either side of any area to be heated (e.g. torch cutting, sawing, grinding, etc.) in accordance with 29 CFR 1926.354. Abrasive blasting is prohibited.
110-6.3Partial Removal of Bridges: On concrete bridges to be partially removed and
widened, remove concrete by manually or mechanically operated pavement breakers, by concrete saws, by chipping hammers, or by hydro -demolition methods. Do not use explosives. Where concrete is to be removed to neat lines, use concrete saws or hydro -demolition methods capable of providing a reasonably uniform cleavage face. If the equipment used will not provide a uniform cut without surface spalling, first score the outlines of the work with small trenches or grooves. For all demolition methods, submit for review and approval of the Engineer, a demolition plan that describes t he method of removal, equipment to be used, types of rebar splices or couplers, and method of straightening or cutting rebar. In addition, for hydro - demolition, describe the method for control of water or slurry runoff and measures for safe containment of concrete fragments that are thrown out by the hydro -demolition machine.
110-6.4Authority of U.S. Coast Guard: For bridges in navigable waters, when
constructing the project under authority of a U.S. Coast Guard permit, the U.S. Coast Guard may inspect an d approve the work to remove any existing bridges involved therein, prior to acceptance by the Department.
110-6.5Asbestos Containing Materials (ACM) Not Identified Prior to the Work:
When encountering or exposing any condition indicating the presence of asbestos, cease operations immediately in the vicinity and notify the Engineer. Make every effort to minimize the disturbance of the ACM. Immediately provide provisions for the health and safety of all jobsite personnel and the public that may be expose d to 171 FY 2023-24 Return to Table of Contents any ACM. Provisions shall meet all applicable Federal, State, and Local Rules and Regulations regarding potentially hazardous conditions due to ACM. The Engineer will notify the District Contamination Impact Coordinator (DCIC) who will engage the se rvices of the Department’s Contamination Assessment/Remediation Contractor (CAR). Provide access to the potential contamination area. Preliminary investigation by the CAR Contractor will determine the course of action necessary for site security and the steps necessary to resolve the contamination issue. The CAR Contractor will perform an asbestos survey to delineate the asbestos areas, and identify any staging or holding areas that will be needed for assessment or abatement of the asbestos material. The CAR Contractor will maintain jurisdiction over activities within areas contaminated with ACM including staging and holding areas. The CAR Contractor will be responsible for the health and safety of workers within these delineated areas. Provide continuous access to these areas for the CAR Contractor and representatives of regulatory or enforcement agencies having jurisdiction. Coordinate with the CAR Contractor and Engineer to develop a work plan with projected completion dates for the final resolution of the contamination, in coordination with any regulatory agencies as appropriate. Use the work plan and schedule as a basis for planning the completion of all work efforts. The Engineer may grant Contract Time extensions according to
the provisions of 8-7.3.2.
Cooperate with the CAR Contractor to expedite integration of the CAR
Contractor’s operations into the construction project. Adjustments to quantities or to Contract
unit prices will be made according to work additions or reductions on the part of the Prime
Contractor in accordance with 4-3.
The Engineer will inform the Prime Contractor when operations may resume in
the affected area.
110-7Removal of Existing Concrete
Remove and dispose of existing Portland cement concrete pavement, sidewalk, slope
pavement, ditch pavement, curb, and curb and gutter, etc., where shown in the Plans.
Remove all gravity walls, noise/sound walls, retaining walls, MSE walls, perimeter walls,
and roadway concrete barriers, where shown in the Plans. All ancillary elements of these
concrete features being removed including, but not limited to, base, leveling pads, copings,
reinforcing steel or straps, footings, edgedrains, etc, are incidental and included in the cost of the
removal.
110-8Ownership of Materials
Except as may be otherwise specified in the Contract Documents, take ownership of all
buildings, structures, appurtenances, and other materials removed and dispose of them in
accordance with 110-9.
110-9Disposal of Materials
110-9.1General: Either stack materials designated to remain the property of the
Department in neat piles within the right-of-way, load onto the Department’s vehicles, or deliver
to location designated in the Plans. 172FY 2023-24Return to Table of Contents
Dispose of timber, stumps, brush, roots, rubbish, and other material resulting from
clearing and grubbing in areas and by methods meeting the applicable requirements of all
Federal, State and Local Rules and Regulations. Do not block waterways by the disposal of
debris.
With the approval of the Engineer, wood chips may be evenly distributed to a
depth of no more than one inch in designated areas in the Department’s right-of-way.
110-9.2Burning Debris: Where burning of such materials is permitted, perform all such
burning in accordance with the applicable Federal, State and Local rules and regulations.
Perform all burning at locations where trees and shrubs adjacent to the cleared area will not be
harmed.
110-9.3Timber and Crops: The Contractor may sell any merchantable timber, fruit
trees, and crops that are cleared under the operations of clearing and grubbing for his own
benefit, subject to the provisions of 7-1.2, which may require that the timber, fruit trees, or crops
be burned at or near the site of their removal, as directed by the Engineer. The Contractor is
liable for any claims which may arise pursuant to the provisions of this Subarticle.
110-9.4Disposal of Treated Wood: Treated wood must be handled and disposed of
properly during removal. Treated wood should not be cut or otherwise mechanically altered in a
manner that would generate dust or particles without proper respiratory and dermal protection.
The treated wood must be disposed of in at least a lined solid waste facility or through
recycling/reuse. Treated wood shall not be disposed by burning or placement in a construction
and demolition (C&D) debris landfill.
110-9.5Hazardous Materials/Waste: Handle, transport, and dispose of hazardous
materials/waste in accordance with all Federal, State, and Local Rules and Regulations
including, but not limited to, the following:
Accept responsibility for the collection, sampling, classification, packaging,
labeling, accumulation time, storage, manifesting, transportation, treatment and disposal of
hazardous materials/waste, both solid and liquid. Separate all solid and liquid waste and collect
all liquids used at hygiene stations and handle as hazardous materials/waste. Obtain written
approval from the Engineer for all hazardous materials/waste stabilization methods before
implementation.
Obtain an EPA/FDEP Hazardous Waste Identification Number
(EPA/FDEP ID Number) before transporting and/or disposal of any hazardous materials/waste.
List the Department as the generator for hazardous materials/waste resulting from
removal or demolition of Department materials.
Submit the following for the Engineers’ approval before transporting, treatment or
disposal of any hazardous materials/waste:
Transport all hazardous materials/waste in accordance with applicable Federal,
State, and Local Rules and Regulations including, but not limited to, the 40 CFR 263 Standards. 173FY 2023-24Return to Table of Contents
Submit all final Hazardous Materials/Waste manifest/bills of lading and certificates of disposal
to the Engineer within 21 days of each shipment.
110-9.5.1 Steel Members with Hazardous Coating: Dispose of steel members
with hazardous coating in one of the following manners:
recycling or treatment facility capable of processing steel members with hazardous coating.
by the Engineer for use as an offshore artificial reef. Deliver any other hazardous materials/waste
to a licensed hazardous materials/waste recycling treatment facility.
Dismantle and/or cut steel members to meet the required dimensions of
the recycling facility, treatment facility or offshore artificial reef agency.
All compensation for the cost of removal and disposal of hazardous
materials/waste will be included in the Cost of Removal of Existing Structures.
110-9.5.2 Certification of Compliance: Submit certification of Compliance from
the firm actually removing and disposing of the hazardous materials/waste stipulating, the
hazardous materials/waste has been handled, transported and disposed of in accordance with this
Specification. The Certification of Compliance shall be attested to by a person having legal
authority to bind the company.
Maintain all records required by this Specification and ensure these
records are available to the Department upon request.
110-10Miscellaneous Operations
110-10.1Water Wells Required to be Plugged: Fill or plug all water wells within the
right-of-way, including areas of borrow pits and lateral ditches, that are not to remain in service,
in accordance with applicable Federal, State, and Local Rules and Regulations.
Cut off the casing of cased wells at least 12 inches below the existing surface or
12 inches below the elevation of the finished graded surface, whichever is lower. Water wells, as
referred to herein, are defined either as artesian or non-artesian, as follows:
supplies may be obtained and which penetrates any water-bearing rock, the water in which is
raised to the surface by natural flow or which rises to an elevation above the top of the water-
bearing bed. Artesian wells are further defined to include all holes drilled as a source of water
that penetrate any water-bearing beds that are a part of the artesian water system of Florida, as
determined by representatives of the applicable Water Management District.
is an unconfined aquifer. The water in a non-artesian well does not rise above the source bed.
110-10.2Leveling Terrain: Within the areas between the limits of construction and the
outer limits of clearing and grubbing, fill all holes and other depressions, and cut down all
mounds and ridges. Make the area of a sufficient uniform contour so that the Department’s
subsequent mowing and cutting operations are not hindered by irregularity of terrain. Perform
this work regardless of whether the irregularities were the result of construction operations or
existed originally.
110-10.3Mailboxes: When the Contract Documents require furnishing and installing
mailboxes, permit each owner to remove the existing mailbox. Work with the Local Postmaster
to develop a method of temporary mail service for the period between removal and installation of
the new mailboxes. Install the mailboxes in accordance with the Standard Plans. 174FY 2023-24Return to Table of Contents
110-11Method of Measurement
110-11.1Clearing and Grubbing: The quantity to be paid for will be the lump sum
quantity.
110-11.2Selective Clearing and Grubbing: The quantity to be paid will be the plan
quantity area in acres designated for Selective Clearing and Grubbing. The quantity to be paid
for Tree Protection Barrier will be the linear foot measurement as shown in the Plans. Tree Root,
Branch Pruning, and Tree Removal will be paid per each tree. Tree Removal per each will not be
used where Clearing and Grubbing or Selective Clearing and Grubbing per acre is used.
110-11.3Removal of Existing Bridges: The quantity to be paid for will be the lump sum
quantity or quantities for the specific structures, or portions of structures to be removed.
110-11.4Removal of Existing Concrete:
The quantity to be paid for will be the number of square yards of existing concrete
elements, acceptably removed and disposed of, as specified. The quantity will be determined by
actual measurement along the surface of the element before its removal. Measurements for
appurtenances which have irregular surface configurations, such as curb and gutter, steps, and
ditch pavement, will be the area as projected to an approximate horizontal plane. Where the
removal of pavement areas is necessary only for the construction of box culverts, pipe culverts,
storm sewers, inlets, manholes, etc., these areas will not be included in the measurements.
Area measurements for walls will be based on exposed vertical face
measurements times the horizontal length of the wall.
110-11.5Plugging Water Wells: The quantity to be paid for will be the number of water
wells plugged, for each type of well (artesian or non-artesian).
110-11.6Mailboxes: The quantity to be paid for will be the number of mailboxes
acceptably furnished and installed.
110-11.7Delivery of Salvageable Material to the Department The quantity to be paid
for will be the Lump Sum quantity for delivery of salvageable materials to the Department, as
indicated in the Plans.
110-11.8General: In each case, except as provided below, where no item of separate
payment for such work is included in the proposal, all costs of such work will be included in the
various scheduled items in the Contract, or under specific items as specified herein below or
elsewhere in the Contract.
110-12Basis of Payment
110-12.1Clearing and Grubbing:
110-12.1.1 Lump Sum Payment: Price and payment will be full compensation
for all clearing and grubbing required for the roadway right-of-way and for lateral ditches,
channel changes, or other outfall areas, and any other clearing and grubbing indicated, or
required for the construction of the entire project, including all necessary hauling, furnishing
equipment, equipment operation, furnishing any areas required for disposal of debris, leveling of
terrain and the landscaping work of trimming, etc.
Where construction easements are specified in the Plans and the limits of
clearing and grubbing for such easements are dependent upon the final construction
requirements, no adjustment will be made in the lump sum price and payment, either over or
under, for variations from the limits of the easement defined in the Plans.
110-12.1.2 When No Direct Payment is Provided: When no item for clearing
and grubbing is included in the proposal, the Contractor shall include the cost of any work of
clearing and grubbing which is necessary for the proper construction of the project in the 175FY 2023-24Return to Table of Contents
Contract price for the structure or other item of work for which such clearing and grubbing is
required. The Contractor shall include the cost of all clearing and grubbing which might be
necessary in pits or areas from which base material is obtained in the Contract price for the base
in which such material is used. The clearing and grubbing of areas for obtaining stabilizing
materials, where required only for the purpose of obtaining materials for stabilizing, will not be
paid for separately.
110-12.2Selective Clearing and Grubbing: Price and payment will be full
compensation for all selective clearing and grubbing, including all necessary hauling, furnishing
equipment, Certified Arborist, equipment operation, furnishing any areas required for disposal of
debris, leveling of terrain, root pruning and tree protection.
110-12.3Removal of Existing Bridges: Price and payment will be full compensation for
all work of removal and disposal of the designated bridges.
When direct payment for the removal of existing bridges is not provided in the
proposal, the Contractor shall include the cost of removing all bridges in the Contract price for
clearing and grubbing or, if no item of clearing and grubbing is included, in the compensation for
the other items covering the new bridge being constructed.
110-12.4Removal of Existing Concrete: Price and payment will be full compensation
for performing and completing all the work of removal and satisfactory disposal.
When no separate item for this work is included, the Contractor shall include the
costs of this work in the Contract price for the item of clearing and grubbing or for the pipe or
other structure for which the concrete removal is required.
110-12.5Plugging Water Wells: Price and payment will be full compensation for each
type of well acceptably plugged.
If a water well requiring plugging is encountered and the Contract contains no
price for plugging wells of that specific type, the plugging of such well will be paid for as
unforeseeable work.
110-12.6Mailboxes: Price and payment will be full compensation for all work and
materials required, including supports and numbers.
110-12.7Delivery of Salvageable Material to the Department: Price and payment will
be full compensation for all work required for delivery of the materials to the Department.
110-12.8Payment Items: Payment will be made under:
Item No. 110- 1- Clearing and Grubbing - lump sum.
Item No. 110- 2- Selective Clearing and Grubbing Area - acre.
Item No. 110- 3- Removal of Existing Bridges - lump sum.
Item No. 110- 4- Removal of Existing Concrete - per square yard.
Item No. 110- 5- Plugging Water Wells (Artesian) - each.
Item No. 110- 6- Plugging Water Wells (Non-Artesian) - each.
Item No. 110- 7- Mailbox (Furnish and Install) - each.
Item No. 110- 21 Tree Protection Barrier - per linear foot.
Item No. 110- 22 Tree Root and Branch Pruning - per each tree.
Item No. 110- 23 Tree Removal - per each tree.
Item No. 110- 86- Delivery of Salvageable Material to FDOT - lump sum. 176FY 2023-24Return to Table of Contents
EARTHWORK AND RELATED OPERATIONS EXCAVATION AND EMBANKMENT
120-1Description
120-1.1General: Excavate and construct embankments as required for the roadway,
ditches, channel changes and borrow material. Use suitable excavated material or authorized borrow to prepare subgrades and foundations. Construct embankments in accordance with Standard Plans, Index 120-001. Compact and dress excavated areas and embankments. Meet the requirements of Section 110 for excavation of material for clearing and grubbing and Section 125 for excavation and backfilling of structures and pipe. Material displaced by th e storm sewer or drainage structure system is not included in the earthwork quantities shown in the Contract Documents . The existing surface may be a combination of the following:
The finished graded surface includes the completed grades of side slopes, unpaved shoulders, and the bo ttom of the base for flexible or rigid pavement.
120-1.2Unidentified Areas of Contamination: When encountering or exposing any
abnormal condition indicating the presence of contaminated materials, cease operations immediately in the vicinity and notify t he Engineer. The presence of tanks or barrels; discolored earth, metal, wood, ground water, etc.; visible fumes; abnormal odors; excessively hot earth; smoke; or other conditions that appear abnormal may indicate the presence of contaminated materials and must be treated with extreme caution. Make every effort to minimize the spread of contamination into uncontaminated areas. Immediately provide for the health and safety of all workers at the job site and make provisions necessary for the health and safet y of the public that may be exposed to any potentially hazardous conditions. Ensure provisions adhere to all applicable laws, rules or regulations covering potentially hazardous conditions and will be in a manner commensurate with the gravity of the conditions. The Engineer will notify the District Contamination Impact Coordinator (DCIC) who will coordinate selecting and tasking the Department’s Contamination Assessment/Remediation Contractor (CAR). Provide access to the potentially contaminated area. Preliminary investigation by the CAR Contractor will determine the course of action necessary for site security and the steps necessary under applicable laws, rules, and regulations for additional assessment and/or remediation work to re solve the contamination issue. The CAR Contractor will delineate the contamination areas, any staging or holding area required; and, in cooperation with the Prime Contractor and Engineer, develop a work plan that will provide the CAR Contractor’s operati ons schedule with projected completion dates for the final resolution of the contamination issue. The CAR Contractor will maintain jurisdiction over activities inside any outlined contaminated areas and any associated staging holding areas. The CAR Contr actor will be responsible for the health and safety of workers within the delineated areas. Provide continuous 177 FY 2023-24 Return to Table of Contents
CLEARING AND GRUBBING in other states
Get an email when 110 changes
Florida revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.