ITEM 205 CHEMICALLY STABILIZED EMBANKMENT
205.01 Description. This work consists of constructing a chemically stabilized embankment by
mixing cement or lime into the embankment soil using the method for the specified chemical. The Contract Documents include an estimated quantity for the specified chemical.
205.02 Materials. Furnish materials conforming to:
Portland cement .................. 701.04, 701.15 Lime (quick lime) ........................ 712.04.B Furnish water conforming to 499.02. Furnish suitable natural soil, from on or off the project site, conforming to 703.16 and 203.03.
205.03 Submittals. Submit, for the Engineer ’s acceptance, a report that lists the type of
equipment to be used, speed of the intended equipment usage, rate of application of the chemical, and calculations that demonstrate how the required percentage of chemical will be applied. Submit the report to the Engineer for acceptance at least 2 workdays before the stabilization work begins. If the pay item for Mixture Design for Chemically Stabilized Soils is included in the Contract Documents, prepare and submit reports according to Supplement 1120.
205.04 Construction. Perform chemically stabilized embankment work when the air
temperature is 40 F or above and when the soil is not frozen. Do not perform this work during wet or unsuitable weather. Drain and maintain the work according to 203.04.A.
205.05 Mixture Design for Chemically Stabilized Soils. When included in the plans, perform
a mixture design for chemically stabilized soils according to Supplement 1120.
205.06 Method of Measurement . The Department will measure chemically stabilized
embankment by the number of cubic yards used in the complete and accepted work, as determined by Item 203. The Department will measure cement and lime by the number of tons incorporated in the complete and accepted work.
205.07 Basis of Payment. The Department will pay lump sum for all work, labor, and equipment
described in 205.05. The Department will pay two -thirds of the lump sum amount bid when the sampling and testing is complete and the report is accepted by the Department. The Department will pay one-third of the lump sum amount bid when the chemically stabilized embankment i s completed and accepted by the Department, and the field verification test results are all submitted. The Department will not apply the quantity underrun adjustment factors in Table 104.02-2 to the bid unit prices for Cement and Lime. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 205 Cubic Yard Cement Stabilized Embankment 205 Cubic Yard Lime Stabilized Embankment 205 Ton Cement 205 Ton Lime 205 Lump Sum Mixture Design for Chemically Stabilized Soils