ITEM 605 UNDERDRAINS
605.01 Description. This work consists of excavating, installing, and backfilling unclassified
pipe underdrains, shallow pipe underdrains, deep pipe underdrains, base pipe underdrains, or rock cut underdrains with or without a Geotextile Fabric , construction underdrains, prefabricated edge underdrains and aggregate drains. Use removed or excavated materials in the Work when the material conforms to the specifications; if not, then recycle or dispose of the material according to 105.16 and 105.17.
605.02 Materials.
Concrete, Class QC-Misc........ 499 and 511 Reinforcing steel .............................. 509.02 Geotextile Fabric, Type A................ 712.09 Backfill unclassified pipe underdrains, shallow pipe underdrains, deep pipe underdrains, base pipe underdrains, rock cut underdrains, with or without a Geotextile Fabric , construction underdrains and aggregate drains with granular material consisting of ACBFS, limestone, or gravel. Furnish granular material meeting Size Nos. 8, 9, or 89. Gradations may be modified in accordance with Supplement
1069.11 C. Use granular material with a maximum sodium sulfate soundness loss of 15 percent.
Backfill prefabricated edge underdrains with granular material consisting of No. 8 size air -cooled blast furnace slag, limestone, or gravel. Use granular material with a maximum sodium sulfate soundness loss of 15 percent. For 605.02.A through 605.02.B, use the pipe of the same size and kind listed in the Proposal . If the kind of pipe is not specifically itemized in the Proposal, use types as listed below.
605.03 Pipe Underdrains Construction. Construct underdrains as follows:
204.05 for Rock Cut underdrains unless otherwise specified in the plans.
If underdrains are to be placed within or beneath an embankment, construct the embankment to the elevation of the top of the subgrade before trenching for the underdrain. If fabric is specified, line the underdrain trench with Geotextile Fabric. Place the Geotextile Fabric to completely surround the granular material. Overlap the Geotextile Fabric at the top of the trench. Match the overlap to the trench width. At other seams, overlap Geotextile Fabric a minimum of 12 inches (0.3 m).
605.04 Construction Underdrains. Construct construction underdrains as follows:
605.05 Prefabricated Edge Underdrains. Install the prefabricated edge underdrains against the
outside wall of a 4 inch (100 mm) trench, and backfill the trench adjacent to the pavement with granular material. Place the granular material in one or more lifts with a vibratory compactor run over the final lift to compact the granular material before placing the asphalt plug. Place the first layer of the granular material simultaneously with the trenching operation to hold the edge underdrains flush against the trench wall. Splice the prefabricated edge underdrains as required before placing in the trench, using material furnished by the manufacturer and according to the manufacturer’s directions. Require the manufacturer to furnish all material required for the splices, and furnish any equipment required for splicing. Construct splices to prevent separation of adjoining sections of the prefabricated edge underdrain panels.
605.06 Underdrain Outlets. Construct pipe outlets concurrently with underdrains. Provide all
outlets on the slope with a precast reinforced concrete outlet according to Item 611 and a tied concrete block mat Type 1 grouted according to 601.12. Construct the underdrains outlets according to Item 611 using outlet fittings. Require the manufacturer to supply outlet fittings that transition between the underdrains and the outlet pipe. Provide smooth-lined or corrugated outlet fittings. Have the underdrains and outlets on fractured slab projects, such as crack and seat, rubblized, or break and seat projects, in place and functional before fracturing the existing pavement. Mark all underdrain outlets with a wooden lath prior to final seeding. Clean all debris from the outlets after final seeding.
605.07 Aggregate Drains. Construct the aggregate drains after the completion of granular
pavement courses.
605.08 Method of Measurement. The Department will measure Unclassified Pipe Underdrains,
Shallow Pipe Underdrains, Deep Pipe Underdrains, Base Pipe Underdrains Construction Underdrains, Rock Cut Underdrains, and Prefabricated Edge Underdrains by the number of feet (meters) completed and accepted in place, measured from end to end of each run. The Department will measure Aggregate Drains by the number of feet (meters) completed and accepted in place, measured along the bottom of the trench.
605.09 Basis of Payment. The Department will pay for pipe outlets under 611.
The Department will pay for precast reinforced concrete outlets under 611 Precast Reinforced Concrete Outlet. The Department will pay for tied concrete block mats Type 1 grouted under 601 Tied Concrete Block Mat. Rock Cut Underdrains are placed in rock and all required trenching in the rock is included under Rock Cut Underdrain. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 605 Foot (Meter) ____ " (____ mm) Unclassified Pipe 605 Foot (Meter) 6" (150 mm) Construction Underdrains 707.31 605 Foot (Meter) ____ " (____ mm) Shallow Pipe Underdrains 605 Foot (Meter) ____ " (____ mm) Deep Pipe Underdrains 605 Foot (Meter) ____ " (____ mm) Base Pipe Underdrains 605 Foot (Meter) Aggregate Drains 605 Foot (Meter) ____ " (____ mm) Rock Cut Underdrains 605 Foot (Meter) ____ " (____ mm) Prefabricated Edge ITEM 606 GUARDRAIL, ANCHOR ASSEMBLIES, IMPACT ATTENUATORS, AND NOISE BARRIER