ITEM 602 MASONRY
602.01 Description. This work consists of constructing headwalls, pipe cradles, collars, and
other brick and masonry units of the types and sizes specified. Use removed or excavated materials in the Work when the material conforms to the specifications; if not, then recycle or dispose of the material according to 105.16 and 105.17.
602.02 Materials. Furnish materials conforming to:
Backfill .................................................. 203 Concrete, Class QC1 ............... 499 and 511 Water for grout and mortar .............. 499.02 Reinforcing steel .............................. 509.02 Cement for mortar ... 701.01 through 701.07 Sand for mortar ................................ 703.03 Granular base ................ Granular material, ..................................... Type B, 703.16.C Brick and masonry units ..... 704.01, 704.02, 704.03 Nonshrink mortar ............................. 705.22 Lime for mortar. ............................... 712.04
602.03 Construction Requirements. Construct the designated items as shown on the plans.
602.04 Method of Measurement. The Department will measure Brick Masonry, Block
Masonry, and Concrete Masonry by the number of cubic yards (cubic meters) calculated from dimensions shown on the plans.
602.05 Basis of Payment. When a precast structure is used, payment is based on the number of
cubic yards (cubic meters) required for the cast in place item and is considered full compensation for construction of the precast structure. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 602 Cubic Yard Brick Masonry (Cubic Meter) 602 Cubic Yard Block Masonry (Cubic Meter) 602 Cubic Yard Concrete Masonry (Cubic Meter) ITEM 603 MAILBOX SUPPORTS
603.01 Description. This work consists of furnishing and erecting mailbox supports with
associated mounting hardware, and attaching an owner-supplied mailbox. Coordinate the timing of the movement of any mailbox to a new location with the local postmaster.
603.02 Materials. Furnish materials conforming to:
Galvanizing ...................................... 711.02 Wood Posts ..................................... 711.26 Steel Posts ........................................ 730.01 Furnish suitable natural soil conforming to 203.03 and 703.16.
603.03 Posts and Hardware. Install square wood posts that are a nominal 4” by 4” or round
wood posts with a diameter of 4”. Install steel or aluminum pipe posts that are 1 1/2” to 2” in diameter. Other mailbox support posts that meet MASH 2016 TL-3 criteria may be substituted. Support hardware shall accommodate either a single or double mailbox installation. Set or drive posts plumb in a manner that prevents battering or distorting the posts. Do not encase posts in concrete. Backfill posts with suitable natural soil and compact thoroughly. Galvanize steel posts, bolts, nuts, washers, spacers, plates, fasteners, and any other necessary hardware per 711.02.
603.04 Mailbox. In the absence of a new mailbox supplied by the owner, carefully salvage the
existing mailbox. Furnish all necessary attachment hardware and secure the new or salvaged mailbox to the new support. Exercise due care when handing the mailbox, and repair or r eplace any mailbox that is damaged during the operation, as directed by the Engineer.
603.05 Method of Measurement. The Department will measure Mailbox Support of the type
specified (single or double) by the number of each assembly furnished and erected complete. The Department will measure Mailbox Support, Removed and Reset by the number of each unit removed and reinstalled.
603.06 Basis of Payment.
The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 603 Each Mailbox Support, Single 603 Each Mailbox Support, Double 603 Each Mailbox Support, Removed and Reset