6-28 SECTIO N 605 – UNDERDRAINS
605.0 1 DESCRIPTION . This work shall consist of constructing drainage systems using underdrains,
underdrain outlets, flushing basins, and risers.
605.0 2 MATERIALS . Materials shall meet the requirements of the following subsection s:
Granular Backfill for Structures ................................ ................................ ................. 704.08 Drainage Aggregate ................................ ................................ ................................ ...704.16 Corrugated Polyethylene Pipe (CPEP) ................................ ................................ ......710.03 Polyvinyl Chloride (PVC) Plastic Pipe ................................ ................................ ......710.0 5 Corrugated Steel Pipe, Pipe Arches , and Underdrains ................................ .............. 711.01 Corrugated Aluminum Alloy Pipe, Pipe Arches, and Underdrains ........................... 711.02 Gray Iron Castings ................................ ................................ ................................ .....715.01(b) Geotextile for Underdrain Trench Lining ................................ ................................ ..720.05 If the Contract does not specify a particular type of underdrain or carrier pipe, the Contractor may furnish underdrain and carrier pipe of the diameter indicated and in any one of the following material s:
605.0 3 PROTECTIO N OF MATERIALS . Corrugated polyethylene or PVC plastic pipe stored on the job
site prior to use shall be protected from pr olonged exposure to sunlight. The Engineer may require impact or other strength tests of the pipe prior to installation when ultraviolet light degradation is suspected.
605.0 4 Installation .
605.0 5 METHO D OF MEASUREMENT . The quantity of the specified size of Underdrain or Underdrain
Carrier Pipe to be measured for payment will be the number of linear feet installed in the complete and accepte d work . When it is necessary to cut underdrain or carrier pipe in the field, the quantity of underdrain or carrier pipe to be measured for payment will be the length necessary, rounded up to the next whole foot increment. The quantity of Underdrain Flushing Basin to be measured for payment will be the number of units installed in the complete and accepted work including the corrugated pipe and the cast iron cover.
605.0 6 BASIS OF PAYMENT . The accepted quantities of each type and size of Underdrain or
Underdrain Carrier Pipe will be paid at the respective Contract unit price per linear foot. Underdrain Flushing Basins will be paid at the respective Contract unit price for each. U nderdrain used for vertical stand pipes at flushing basin locations or risers will be paid as Underdrain Carrier Pipe. Payment will be full compensation for fabricating, furnishing, transporting, handling, and placing the material specified, including coup ling bands and fittings, drainage aggregate , geotextile fabric, and the necessary backfill material to an elevation 7 feet above the flowline, and for furnishing of all labor, tools, equipment , and incidentals necessary to complete the work . Excavation for all underdrain, carrier pipe, flushing basins, vertical stand pipes, and risers will be paid for as Trench Excavation. Payment will be made under: Pay Item Pay Unit
605.10 06 Underdrain Pipe, 6 Inch ................................ ................................ ............ Linear Foot
605.1 008 Underdrain Pipe, 8 Inch ................................ ................................ ............ Linear Foot
605.1 012 Underdrain Pipe, 12 Inch ................................ ................................ .......... Linear Foot
605.20 06 Underdrain Carrier Pipe, 6 Inch ................................ ................................ Linear Foot
605.2 008 Underdrain Carrier Pipe, 8 Inch ................................ ................................ Linear Foot
605.2 012 Underdrain Carrier Pipe, 12 Inch ................................ .............................. Linear Foot
605.95 00 Underdrain Flushing Basin ................................ ................................ .......Each
6-31 SECTIO N 608 – EQUIPMEN T RENTAL
608.0 1 DESCRIPTION . This work shall consist of furnishing, operating, and supervising the use of
equipment for performance of work shown on the Plans, in accordance with these specification s or as directed by the Engineer.
608.0 2 GENERA L REQUIREMEN TS. Equipment shall be maintained in good mechanical condition
and shall be operated by capable and experienced operators. Equipment that is to operate on paved surfaces shall be equipped with rubber tires or smooth street plates . Tracked equipment used to draw any other equipment shall be of a type that will not damage the work being done and has sufficient power to operate the drawn equipment effectively. Equipment used under this section shall meet the following specific requirements as to type, size, ca pacity, power, or dimensions . In determining whether a particular piece of equipment is classified as Type I, Type II, or Type III in Subsection 608.02(a) , Subsection 608.02(c) , Subsection 608.02(d) , Subsection 608.02( e), or Subsection 608.02( g), the make and model number shall be referenced against an equipment guide book. Whenever equipment of a certain size is requested by the Engineer and the Contractor supplies a larger size, payment will be fo r the size requested.
UNDERDRAINS in other states
Get an email when 605 changes
Vermont revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.