B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
General Provisions (00100-00999)

809Luminaires

OK · 2019 Standard Specifications✓ Full text on BuildSpecBook pages 819–819 Save this section

Ask about Section 809

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

LUMINAIRES 809.04

808.03 Equipment — Vacant

808.04 Construction Methods

Fabricate, galvanize, and construct the brackets and install on bridge piers as shown on the Plans.

808.05 Method of Measuremen T — Vacant

808.06 Basis of Payment

The Department will pay for this pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit: PIER -MOUNTED POLE BRACKET Each

809.01 Description

This work consists of providing and installing roadway and sign lighting luminaires.

809.02 Materials

Provide luminaires with a housing, ballast, reflector, refractor, and lamp of the type and lumen rating shown on the Plans. Submit to the Resident Engineer a list of luminaires to be used on the project that are listed on the QPL. For luminaires not listed on the QPL, submit two (2) hardcopies of a complete materials schedule and proposed equipment, including catalog cuts, diagrams, drawings, and other data, along with a New Product Evaluation Request form, to the Resident Engineer for approval. Fabricate, assemble, and install luminaires as shown on the Plans. Provide luminaires meeting t he Illumination Engineering Society of North America (IES) standards for the size and type of luminaire shown on the Plans. For each size and type of luminaire, submit the following to the Resident Engineer: Manufacturer’s photometric test data Manufactu rer certification that IES -approved test procedures were used

809.03 Equipment — Vacant

809.04 Construction Methods

Install luminaires in accordance with the manufacturer’s recommendations and as shown on the Plans.

810.02 Power Supplies

809.05 Method of Measuremen T - Vacant

809.06 Basis of Payment

The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit:

A.ROADWAY LUMINAIRE Each
B.UNDERPASS LUMINAIRE Each
C.POST TOP LUMINAIRE Each
D.OVERHEAD SIGN LUMINAIRE Each
E.HIGH MAST LUMINAIRE Each
F.NAVIGATIONAL LIGHT Each Include the cost of cut -off visors and other hardware in the contract unit price for the relevant luminaire pay items. SECTION 810 POWER SUPPLIES

810.01 Description

This work consists of providing and installing permanent and temporary power supply systems.

810.02 Materials

Provide materials in accordance with the following sections, subsection, and external reference: Material: Section, Subsection, or External Reference: Wood Poles ANSI 05.1 Electrical Conduit 709 Portland Cement Concrete, Class A 701 Reinforcing Steel 723 Conductors 811 For miscellaneous pole line hardware, provide standard material manufactured for pole line construction. Provide hot -dipped galvanized, or otherwise non -corrosive metal parts. Provide control equipment in accordance with NEMA 3R or 4 and UL Specifications. Provide a metered, temporary lighting service to power existing and temporary lighting.

Get an email when 809 changes

Oklahoma revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Oklahoma Standard Specifications for Highway Construction, 2019 Edition. Pages 819–819 of 935. View official source ↗

Ask about this section

Scoped to Oklahoma 2019 Standard Specifications for Highway Construction, Section 809 — Luminaires. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.