810.02 Power Supplies
809.05 Method of Measuremen T - Vacant
809.06 Basis of Payment
The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit:
B.UNDERPASS LUMINAIRE Each
C.POST TOP LUMINAIRE Each
D.OVERHEAD SIGN LUMINAIRE Each
E.HIGH MAST LUMINAIRE Each
F.NAVIGATIONAL LIGHT Each Include the cost of cut -off visors and other hardware in the contract unit price for the relevant luminaire pay items.
810.01 Description
This work consists of providing and installing permanent and temporary power supply systems.
810.02 Materials
Provide materials in accordance with the following sections, subsection, and external reference: Material: Section, Subsection, or External Reference: Wood Poles ANSI 05.1 Electrical Conduit 709 Portland Cement Concrete, Class A 701 Reinforcing Steel 723 Conductors 811 For miscellaneous pole line hardware, provide standard material manufactured for pole line construction. Provide hot -dipped galvanized, or otherwise non -corrosive metal parts. Provide control equipment in accordance with NEMA 3R or 4 and UL Specifications. Provide a metered, temporary lighting service to power existing and temporary lighting. POWER SUPPLIES 810.04
810.03 Equipme Nt — Vacant
810.04 Construction Methods
Construct power supplies in accordance with the NIST Handbook 81 Safety Rules for the Installation and Maintenance of Electric Supply and Communication Lines. Cooperate with the local utility companies to locate, ins tall, and connect power supplies. Contact local “Excavator Alert” organizations before starting trenching or boring operations.
A.Voltage and Construction Specifications Ensure the voltages for the permanent or temporary service poles are as shown on the Plans. Construct concrete in accordance with Section 509, “Structural Concrete.” Construct reinforcing steel in accordance with Section 511, “Reinforcing Steel for Structures.”
B.Temporary Power Suppl ies Arrange for electrical power connections for the temporary service poles as soon as construction allows. Arrange power connections for locations not shown on the Plans through the local utility company, with the approval of the Resident Engineer. Erec t, energize, deactivate, and remove the temporary lighting system at various stages of the traffic control as shown on the Plans or as directed by the Resident Engineer. Space the temporary lighting on wood poles 150 ft [50 m] apart. Protect the light pol es from traffic as approved by the Resident Engineer. Do not use aerial conductors to connect power to light poles with breakaway bases. Install the temporary light and service poles. Repair damage from installation, relocation, or removal at no additional cost to the Department. Maintain all existing lighting systems during construction in accordance with Subsection 105.14, “Maintenance During Construction,” at no additional cost to the Department. If a lighti ng pole assembly is damaged or knocked down by a third party, repair or replace the damaged lighting pole assembly to its original condition. The Department will pay the additional cost at the contract unit price for pay items necessary to complete the re pair or replacement, excluding removal of the light pole and concrete footing. Connect the temporary service poles to the permanent service poles for final acceptance after completing the lighting system or Project. Carefully handle items shown on the Plan s for removal, resetting, or both. Neatly store the removed items in a location directed by the Resident Engineer. Removed service poles, light poles, mast arms, luminaires, and temporary lighting equipment become the property of the Department. Stockpil e these items at locations shown on the Plans, unless otherwise approved or directed by the Resident Engineer.
810.05 Power Supplies
Leave the temporary service poles and the temporary lighting systems in place, or remove at the end of the Project, as directed by the Resident E ngineer. If temporary service poles or temporary lighting systems provide a safe driving environment, leave in place as approved by the Resident Engineer.
1.Temporary Lighting on Wood Poles Supply electrical service to temporarily light traffic control crossovers, points of conflict, and other locations as approved by the Resident Engineer.
2.Existing Lighting Circuits Maintain existing lighting systems in operation. If construction disrupts an existing lighting system, use additional temporary lighti ng on wood poles.
3.New Permanent Lighting Circuits Use the temporary lighting service and the temporary service poles to supply electricity to the temporary lighting poles and the new permanent lighting circuits. After Project completion, connect the p ermanent service pole to the new permanent lighting circuits. Install the permanent electrical service for the new highway lighting systems as shown on the Plans.
810.05 Method of Measuremen T
Before payment, provide the Resident Engineer with copies of th e utility company’s invoice and proof of payment for Temporary Lighting Service .
810.06 Basis of Payment
The Department will pay for each pay item at the contract unit price per the specified pay unit as follows: Pay Item: Pay Unit:
B.POLE -MOUNTED TRANSFORMER STATION Each
C.PAD -MOUNTED TRANSFORMER STATION Each
D.TEMPORARY SERVICE POLE Each
E.TEMPORARY LIGHTING SERVICE Kilowatt -hour
F.WOOD POLE Each The Department or local authority will become responsible for continuing temporary lighting system maintenance and operation after project completion and final acceptance. ELECTRICAL CONDUCTORS HIGHWAY LIGHTING 811.04 SECTION 811 ELECTRICAL CONDUCTORS HIGHWAY LIGHTING
811.01 Description
This work co nsists of providing and installing electrical conductors to transmit and distribute electrical energy.
811.02 Materials
Provide materials in accordance with the following subsections: Material: Subsection: Building Wire and Cable 738.02 Underground Secondary Distribution Wire and Cable 738.02 Outdoor Aerial Neutral -Supported Secondary Distribution Wire and Cable 738.02
811.03 Equipment — Vacant
811.04 Construction Methods
A.Conductors in Conduit Complete the conduit system before installing the conductors. Provide enough slack in each conductor to allow at least 5 ft [1.5 m] at pole bases and at least 10 ft [3 m] at pull boxes.
B.Aerial Conductors Install aerial conductors in accordance with the National Electric Safety Code and the manufacturer’s recommendations for sag and t ension. Submit a copy of the cable manufacturer's charts, for each size and type of cable, to the Resident Engineer for approval of aerial conductor.
C.Splices and Taps Splice or tap the underground and indoor conductors at pull boxes, pole bases, contro l cabinets, junction boxes, or other weatherproof enclosures. Splice and tap outdoor aerial conductors as shown on the Plans. Do not pull splices into the conduit system. Provide the types of splices and taps required by the Contract. Seal, waterproof, and insulate insulated conductors in accordance with ANSI C 119.1 -2011, “Sealed Insulated Underground Connector System Rated 600 Volts.” Alternatively, complete Procedure 1 or Procedure 2.
Source: Oklahoma Standard Specifications for Highway Construction, 2019 Edition. Pages 820–822 of 935.