General Conditions

00865Longitudinal Pavement Markings - Durable

OR · 2024 Standard SpecificationsBook pages 948950View official source ↗

00865.00 882 Section 00865 - Longitudinal Pavement Markings - Durable

Description

00865.00Scope - In addition to the requirements of Section 00850, install durable longitudinal

pavement markings according to the following Specifications.

Labor

00865.30Manufacturer 's Representative - Provide a manufacturer's representative according

to 00850.30.

00865.31Manufacturer -Certified Installers - Provide certified installer's according to 00850.31

Construction

00865.40General - Before installing, and in the presence of the Engineer, conduct a performance

test by applying a 150 foot test section on roofing felt. Do not place permanent Material without the Engineer's approval of the performance test. Additional performance tests may be required. Conduct performance tests at no additional cost to the Agency.

00865.45Installation - Place durable markings only when the manufacturer's representative

determines that the Pavement is ready for the pavement marking M aterial.

Apply reflective elements at a rate to obtain the following minimum initial retroreflectivity readings:

• White - 250 mcd/m 2/lx • Yellow - 200 mcd/m2/lx Apply marking M aterials by one or more of the following methods:

• Method A: Extruded Markings - Apply markings with an extrusion or ribbon type process and according to the following: For grooved markings, grind the slot depth as shown. Apply the specified marking M aterial centered in the slot as shown. The top of the marking shall be flat or slightly convex. • For profiled markings, place lines a nd bumps straight and square.

• Method B: Spray Markings - Apply two separate applications of spray markings with each application being one half the total specified thickness. Retrace the second application directly over the first application within 1/16 inch. For white colored markings, apply the second application in the same direction of the first application. For yellow colored markings that delineate two-way traffic, apply the second application in the opposite direction of the first application. For yellow colored markings on one-way Roadways, apply the second application in the same direction of the first application. Thermoplastic spray markings may be installed in one application at the total specified thickness if approved by the Engineer and after a successful performance test according to 00865.40. Apply spray markings in two applications if installing yellow colored markings over rumble strips.

• Method C: Pavement Marking Tape - Do not place tape continuously on longitudinal Pavement joints. Apply pavement marking tape as follows:

• Rolled-In Installation - Apply the tape to the fresh asphalt concrete surface prior to the final rolling of the mat. Roll the tape into the fresh surface during the finishing of the mat.

00865.75 883 • Grooved Installation - Grind slot depth to 130 to 150 mils with a smooth, uniform, and flat bottom. Apply tape into slot.

Method D: Wet Weather Markings - Apply markings with an extrusion, ribbon, or spray process and according to the following:

For grooved markings, grind t he slot depth as shown. Apply the specified marking material centered in the slot as shown. The top of the marking shall be flat or slightly convex. For profiled markings, apply markings with an extrusion or ribbon process. Place lines and bumps straight and square.

• Method AB: Non -Profiled Extruded or Sprayed Markings - Install Method A surface, non-profiled markings or Method B markings.

00865.75Manufacturer Warranty - Furnish a manufacturer warranty that unconditionally warrants

to the Agency the product(s) and installation under this Section against failure, according to this Subsection and 00170.85(c)(1). Use Agency -supplied warranty forms, available from the Engineer. "Unconditionally warrant" means that the warranty covers all failures, regardless of the source or cause of the failure, including, without limitation, whether the source or cause is or may be related to workmanship, inspection, or choice of M aterials.

The Agency inspection of any portion of the Work during the Contract and during the product installation, the Agency acceptance of the Work , corrections under the warranty, or expiration of the warranty shall not relieve the obligations under this warranty.

(a)Warranty Period - The warranty period shall be 3 years for surface mounted thermoplastic,

and 4 years all other methods and M aterials in this Section.

(b)Failure - For purposes of this warranty, failure is defined as one or more of the followi ng:

Loss of Retroreflectivity - Markings fail to maintain a minimum retroreflectivity of 150 mcd/m2/lx for white and 125 mcd/m2/lx for yellow. Insufficient Color Stability (Yellow) - Yellow markings fail to meet ASTM D6628. Insufficient Color Stability (W hite) - White markings fail to meet ASTM D6628 . Loss of Adhesion - Any 300-foot segment of marking shows 5 percent or greater loss of line due to non -adhesion. This constitutes a failure of that segment.

(c)Remedy - Upon notification by the Engineer of a failure, provide the following remedy at no

additional cost to the Agency:

Repair or replace, at the discretion of the Engineer all failed pavement markings within 6 months of the Agency's request to do so. Use Materials and procedures meeting the Specifications. Match repairs to adjoining Work . Coordinate timing of repair Work with the Engineer.

(d)Agency's Right to Make Repairs - If, in the opinion of the Engineer, a failure causes or may

cause a hazard, the failure may be temporarily corrected by Agency or other forces at no additional cost to the Agency. Replace temporary repairs with permanent repairs at no additional cost to the Agency and according to the Specifications and within the time specified in 00865.75(c).

00865.80 884 Measurement

00865.80Measurement - The quantity of durable longitudinal pavement markings will be measured

on the length basis. Durable longitudinal pavement markings will be based on a nominal line width of 4 inches. If the width of the line is other than 4 inches, measurement will be adjusted by converting to an equivalent length of nominal 4 inch line on a proportionate area basis. Measurement will be the actual stripe. Gaps between skip stripes will not be measured.

Payment

00865.90Payment - The accepted quantities of Work performed under this Section will be paid for

at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

Method A (Extruded)

(a)Methyl Methacrylate, Extruded, ____, ____ .......................................... Foot
(b)Thermoplastic, Extruded, ____, ____ ................................................... Foot

Method B (Sprayed)

(c)Methyl Methacrylate, Sprayed, Surface, Non-Profiled .......................... Foot
(d)Thermoplastic, Sprayed, Surface, Non-Profiled .................................... Foot

Method C (Pavement Marking Tape)

(e)Pavement Marking Tape, ____, ____ ................................................... Foot
(f)Pavement Marking Tape, ____, ____, Wet Weather ............................ Foot

Method D (Wet Weather Markings)

(g)Methyl Methacrylate, Wet Weather, ____, ____ ................................... Foot
(h)Thermoplastic, Wet Weather, ____, ____ ............................................. Foot

Method AB (Non -Profiled Extruded or S prayed)

(i)Methyl Methacrylate, Extruded or Sprayed, Surface, Non-Profiled ....... Foot
(j)Thermoplastic, Extruded or Sprayed, Surface, Non-Profiled ................. Foot

In items (a) and (b), the word "Surface" or "Grooved" will be inserted in the first blank and the word "Profiled" or "Non-Profiled" will be inserted in the second blank.

In items (e) and (f), "Rolled-In" or "Grooved" will be inserted in the first blank and "Patterned" or "Non -Patterned" will be inserted in the second blank. In items ( g) and ( h), the word "Surface" or "Grooved" will be inserted in the first blank and the word "Profiled" or "Non-Profiled" will be inserted in the second blank.

Payment will be payment in full for furnishing and placing all Materials, and for furnishing all Equipment , labor, and Incidentals necessary to complete the Work as specified.

Payment for Work performed under this Section will be limited to 75 percent of the amount due until the Agency has received the signed warranty.

Source: Oregon Standard Specifications for Construction, 2024 Edition. Pages 948950 of 1,268.