SUBSYSTEM
1226.1DESCRIPTION—This work is to furnish, install, modify, repair, replace, and remove components
of a Highway Advisory Radio (HAR) subsystem.
1226.2MATERIAL—Section 1220.2
1226.3CONSTRUCTION—Section 1220.3 and as follows:
frayed cables, damage caused by lightning, leaning, car impacts, or vandalism, and general condition. Check batteries. Clean, repaint, and repair as necessary. Verify the broadcast signal strength of the HAR transmitter via the dials located on the front panel. Verify that the HAR transmitter is clearly transmitting a signal by utilizing a car radio and turning the dial to the appropriate channel. Test communication system, including pager systems. Test power and communications line surge suppressors and replace as necessary. Test all static signing flashing warning devices associated with the HAR systems, check batteries, clean controller enclosure and solar panels that power the battery packs.
of the system including, but not limited to: flashing LED yellow lights, supports, signage legend, aluminum sheet , foundation, connections, field enclosure, dual circuit flasher controller, modems, communications, programming, services, conduit, junction boxes, wiring, sign luminaries, solar panels , and battery back-up if applicable along with any other related system equipment.
After On-call Maintenance (OM) has been completed, perform Preventive Maintenance (PM) as described in Section 1226.3(a).
1226.4MEASUREMENT AND PAYMENT—
All labor, materials, and equipment required for routine preventive maintenance are incidental to this item including, but not limited to , the Statewide Device Identification Number, cleaning materials, caulk, metal meshing, lubricants, filters, lamps, paint, surge suppressors, fuses, circuit breakers, attachment hardware, insect prevention measures, rodent control measures, clearing and grubbing, selective tree trimming, snow and ice removal, and weed control measures. Mobilization is incidental to this item.
All labor, materials, and equipment required for routine preventive maintenance are incidental to this item including, but not limited to , the Statewide Device Identification Number, cleaning materials, caulk, metal meshing, lubricants, filters, lamps, paint, surge suppressors, fuses, circuit breakers, attachment hardware, insect prevention measures, rodent control measures, clearing and grubbing, selective tree trimming, snow and ice removal, and weed control measures. Mobilization is incidental to this item.
Mobilization will not be paid for procurement of parts. Travel to and from the site and/or district stockpile is incidental to this item.
Mobilization will not be paid for procurement of parts. Travel to and from the site and/or district stockpile is incidental to this item.
Repair time will not be paid for procurement of parts. Travel to and from the site and/or district stockpile is incidental to this item. Site specific snow and ice removal requested by the Department is included within this item.
Repair time will not be paid for procurement of parts. Travel to and from the site and/or district stockpile is incidental to this item. Site specific snow and ice removal requested by the Department is included within this item.
Includes all cables, connectors, equipment racks, conductor(s), and other parts necessary for proper installation and configuration of a HAR subsystem.
Includes all cables, connectors, equipment racks, conductor(s), and other parts necessary for proper installation and configuration of a HAR subsystem.