1206MAINTENANCE, ITS DEVICES - GENERAL

PA · 2026 Standard SpecificationsBook pages 13591363View official source ↗

1201. 4(b) 1201. 4(e) • Factory Demonstration Test. If in-person attendance is required.

• On-Site Standalone Test.

• System Test.

• 60-Day Test.

• 180 Day Support Period. Includes all maintenance, repairs, on- call responses, and documentation.

• Warranty Period.

(c)Not used.
(d)Electrical Service. The following items are paid separately and according to the measurement and

payment of their respective sections:

• Trench and Backfill . Section 910.4(n)

• Rigid Galvanized Steel ( RGS ) and PVC Conduit. Section 910.4(k)

• Cable Installation . Section 910.4(m)

• Complete Power Supply System . Section 910.4( o)

• Junction Box (power and communications). Section 910.4(a)

(e)Wood Pole Communication Utility Enclosure. Each

Communications service equipment housed inside enclosure will be provided by the Department . 1202.1 1202.03(b)

1202.1DESCRIPTION —This work is the coordination and documentation activities required to facilitate

integration of ITS Devices into the Advanced Traffic Management System (ATMS) and to furnish information regarding the characteristics of all relevant ITS devices installed within the project . The ATMS is the common platform used by the Department to monitor, control , and utilize all functionalities of ITS devices installed within the Commonwealth. Work to integrate the ITS device(s) must be a collaborative effort between the Contractor responsible for installation of the ITS device(s), the construction services team, and the ATMS vendor. All coordination with the ATMS vendor must go through PennDOT’s Systems and Performance Unit in the Operations and Performance Section of the Bureau of Operations. The ATMS vendor, at no cost to the Contractor, will be responsible for performing the work to integrate the ITS device(s) into the ATMS. The Contracto r is responsible for furnishing all information pertaining to the ITS device(s) relevant to integration, as described herein, and as required by the ATMS vendor.

1202.2MATERIAL —

(a)Protocol Documentation. Furnish protocol documentation for all communication protocols used by

the ITS device (s).

(b)Integration Kit. Furnish integration kit (SDK, API, Software), if applicable, that the ATMS vendor

will need to integrate device (s). Furnish documentation for integration kit.

(c)Licenses. Furnish licenses, if applicable, to support the integration of the device (s) by the ATMS.
(d)ITS Device Configuration Information. Furnish all information required herein for the respective

device (s) being installed. Information must be provided for each device being installed as part of the ITS project. Omission of any information required for integration will be considered incomplete. If information is incomple